Pieri v. Rosebrook

275 P.2d 67, 128 Cal. App. 2d 250, 1954 Cal. App. LEXIS 1458
CourtCalifornia Court of Appeal
DecidedOctober 21, 1954
DocketCiv. 16084
StatusPublished
Cited by1 cases

This text of 275 P.2d 67 (Pieri v. Rosebrook) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pieri v. Rosebrook, 275 P.2d 67, 128 Cal. App. 2d 250, 1954 Cal. App. LEXIS 1458 (Cal. Ct. App. 1954).

Opinion

PETERS, P. J.

Plaintiff, D. Fieri, hired the defendant, Guy L. Rosebrook, a licensed architect, to design a home, to supervise its construction, and to segregate the subcontracts of *252 the subcontractors. Plaintiff was dissatisfied with the cost of the completed house, and dissatisfied with the supervision of its construction by defendant. He brought this action against defendant for negligence in building a house that cost over $60,000, claiming that the architect had agreed to design a house not to cost over $30,000, and also charging negligent supervision and construction of a sun deck, charging defendant with taking a power saw belonging to plaintiff, and averring that defendant has charged for certain fire screens that never were delivered. Total damages of over $50,000 were alleged. Defendant answered, and cross-complained for the balance of his unpaid fees, alleged to be about $6,000. A nonsuit was granted as to the cause of action based on the fire screens, and no objection to this ruling is now made. At the trial defendant admitted he had received the power saw and owed plaintiff $311.90 for it. The trial court found that plaintiff had orally agreed to pay defendant a fee of 6 per cent of the total construction cost for supervision of construction, and an additional fee of 4 per cent of the total construction cost for the segregation of the subcontracts. Total construction cost was found to be $62,192, making defendant’s total fee $6,219.20, of which $2,800 was found to have been paid, leaving $3,419.20 unpaid. The trial court also found that defendant had been negligent in the supervision of the sun deck, and awarded plaintiff a $2,500 setoff as the reasonable cost of repairing the defects, and also awarded plaintiff $311.90 for the power saw. Thus, a balance of $607.30 was found owing to defendant and he was awarded this sum by the judgment. Both plaintiff and defendant appeal.

The evidence is highly conflicting in many rfespects. There can be little doubt but that plaintiff originally retained defendant to design a house that was not to cost over $30,000, and that defendant represented that the type of house then desired could be built for that sum. The evidence shows that the plaintiff originally ordered a house substantially similar to one constructed by a neighbor, and which had been designed by defendant, and that defendant started to design such a house. The agreed fee for the plans was $800. The evidence also shows that while defendant was working on the preliminary sketches, the plaintiff and his wife ordered various changes. These involved substantial changes in design, larger and additional rooms, and more garage space. Defendant testified that he warned plaintiff on numerous occasions that, if the house were made bigger than originally intended, it would cost more money. The plans were drawn and the $800 fee *253 paid. Before such payment the plaintiff had orally agreed to hire defendant to supervise construction of the house for a 6 per cent fee. Plaintiff testified that this was to be 6 per cent of $30,000, but defendant testified, and the trial court found, that it was to be 6 per cent of the total construction cost. The finding is supported. When this agreement was entered into it was contemplated that the house was to be built by a general contractor under the supervision of defendant as architect. When the plans were submitted to general contractors for bids the lowest bid was $56,750.' This was more money than plaintiff wanted to spend. It was then orally agreed between the parties that no general contractor would be hired and that defendant would be paid an extra fee for segregating the subcontractor’s contracts. Defendant testified that it was agreed that his compensation for these services was to be 5 per cent of the total amount of the segregated contracts. After work on the house had started defendant brought over to plaintiff a standard form used in such circumstances, read to plaintiff the pertinent provisions of this contract, and" explained the provisions to him in order to inform him of the nature of the services to be rendered for this additional fee for segregation. It -is an added fee allowed for the additional work involved in getting subcontracts, segregating the subcontracts, and in writing them, duties normally performed by the general contractor. This form contract was not signed by the parties. It contained a provision for a 4 per cent fee for such services. In addition, plaintiff testified that it had been agreed that the fee was to be 4 per cent for these services. The trial court fixed this fee at 4 per cent of the total cost of construction. It was also agreed between plaintiff and defendant that defendant was not to keep the books on the transaction, but that such duty would be performed by plaintiff’s daughter, a college student, without pay. Construction proceeded on a cash basis. As work progressed bills for labor and materials were submitted to defendant, and, upon his approval, he gave them to plaintiff, who paid them.

It is plaintiff’s contention, and he so testified, that construction started before complete plans had been prepared, that defendant awarded many subcontracts before such plans had been completed, and, as a result, made many changes in construction without informing plaintiff that they would substantially increase the cost of construction. Plaintiff testified that the house was half constructed before he discovered the cost was going to exceed $30,000. Defendant testified that *254 plaintiff paid bills exceeding $50,000 before plaintiff asked him about the costs, or made any objection thereto.

There were undoubtedly many major changes made in the house during the course of construction. An additional bedroom and an additional bathroom were added, as was a tile roof. A change in the floor level of the house made after construction had started added an additional $15,000. Defendant testified that these changes and many others were all made at plaintiff’s request, and the trial court so found.

When the house was completed it had cost $62,192. In addition to being very unhappy about this cost, plaintiff charged in his complaint that there were defects in the construction caused by negligent supervision of the work. The principal defect was rain leakage caused by an overload of concrete on a sun deck. This overload caused the deck to sag and caused the sliding door frames to bind, and also resulted in the flashings between the wall and the deck becoming ineffective in stopping leakage. It was because of these defects that the trial court allowed plaintiff a $2,500 setoff.

Appeal of Plainiiff

One of plaintiff’s major contentions is that the trial court committed prejudicial error in allowing defendant 4 per cent of the total construction cost for segregation of the contracts. Plaintiff points out that defendant at one time pleaded, * and certainly testified, that he had an express oral agreement for 5 per cent, but the trial court fixed the percentage at 4 per cent, which, he contends, must have been based on the reasonable value of such services. Plaintiff then points out that he was precluded from proving generally the reasonable value of such services, and contends that under such circumstances defendant had to recover 5 per cent or nothing at all.

.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams Engineering, Inc. v. Goodyear
496 So. 2d 1012 (Supreme Court of Louisiana, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
275 P.2d 67, 128 Cal. App. 2d 250, 1954 Cal. App. LEXIS 1458, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pieri-v-rosebrook-calctapp-1954.