Pierce v. Ozark Border Electric Cooperative

378 S.W.2d 504, 1964 Mo. LEXIS 756
CourtSupreme Court of Missouri
DecidedMay 11, 1964
Docket49717
StatusPublished
Cited by7 cases

This text of 378 S.W.2d 504 (Pierce v. Ozark Border Electric Cooperative) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pierce v. Ozark Border Electric Cooperative, 378 S.W.2d 504, 1964 Mo. LEXIS 756 (Mo. 1964).

Opinion

HOUSER, Commissioner.

This is an appeal from an order dismissing a third-party petition for indemnity, deemed a final judgment for the purposes of appeal. See Sup.Ct. Rule 82.06, V.A. M.R.

Third-party plaintiff Ozark Border Electric Cooperative, a corporation, hereinafter “Ozark,” filed a third-party petition against J. W. Githens and E. E. Githens, doing business as J. W. Githens Company, hereinafter “contractors,” praying for judgment against contractors for all damages and costs that might be adjudged against it in favor of plaintiff Leon Pierce in his negligence suit against Ozark.

Pierce’s petition against Ozark sought damages for personal injuries sustained by Pierce, when as an employee of contractors, engaged in the building of a bridge, Pierce received a high charge of electricity as he grasped a bucket being lowered by a crane operated by contractors, the crane having come in contact with Ozark’s overhead uninsulated electric power *506 line. Pierce, alleging serious and permanent personal injuries and the loss of a member, prayed for $150,000 damages.

Ozark’s third-party petition charged contractors with active, primary, positive negligence and alleged that its own negligence, if any, was passive, secondary and remote.

Third-party defendant contractors filed a motion to dismiss the third-party petition, on the ground that it failed to state a cause of action. The circuit court sustained the motion and dismissed the third-party petition. Ozark has appealed from the order of dismissal.

After this appeal was taken Pierce and Ozark compromised and settled their differences. Ozark paid $34,500 to Pierce, who dismissed his cause of action with prejudice. After Ozark’s appeal to this court was .perfected Ozark filed here a verified motion to add to the record the fact that an amount in excess of $15,000 is involved on this appeal by reason of the settlement.

We have jurisdiction. Appellate jurisdiction over the subject matter is determined upon the record at the time the appeal is granted and “nothing subsequently occurring will defeat or confer jurisdiction on this court,” Hunter v. Hunter, 355 Mo. 599, 197 S.W.2d 299, 300, 1 so we look to the record as of August 17, 1962, which shows that plaintiff was then making a bona fide claim to $150,000 damages in his action against Ozark. This fixes the amount in dispute for the purpose of our jurisdiction. Crouch v. Tourtelot, Mo.Sup., 350 S.W.2d 799, 803 [5].

Plaintiff Pierce alleged these facts: Contractors were engaged in the construction of a concrete bridge over a ditch on County Route BB in Ripley County. Ozark’s high voltage electric transmission lines crossed the road at the place where the bridge was being constructed. The wires were .so placed in position that persons working on the highway and on machinery required in- the construction work would be likely to come, in. contact with the wires. Contractors requested Ozark to move the wires or de-energize them at the point in question so as to provide a safe place for plaintiff and other employees to work. Ozark was aware .that the bridge construction was taking place and that heavy construction equipment including draglines and cranes were being used in the construction work at that point, and that the equipment would likely come in contact with the wires, but Ozark failed, neglected and refused to move the wires or de-energize the lines. The lines were uninsulated and no type or kind of shield or guard was provided at or near the wires to prevent persons from coming in contact with them. Employees of contractors were operating a crane or dragline on the highway at said point, transferring liquid cement from a mixer to the deck of the bridge upon which plaintiff was standing. The crane came in contact with the high voltage, transmission line and thereby transferred a deadly current of electricity, from the crane to plaintiff, who in the course of his employment, grasped the crane’s bucket preparatory to unloading it. As a result plaintiff sustained very severe injuries.

Pierce charged Ozark with negligence in the following particulars: maintaining the wires in an uninsulated condition; failure to provide any type or kind of shield' or guard at or near the wires so as to prevent contact with persons working in close proximity; failure to warn plaintiff of the presence and location of the wires and that they were uninsulated; failure to maintain the wires at a height above the ground that was safe and adequate to prevent contact therewith by persons working in close proximity.

Ozark filed a general denial and a plea of contributory negligence.

Ozark’s third-party petition as amended charged that at the request of contractors *507 a representative of Ozark visited the site, and made recommendations as a result of which, without request by any public regulatory body or entity, Ozark at its own cost raised its wires approximately ten feet over the construction area and elevated them to a height in excess of the requirements of the National Safety Code; that Pierce’s injuries were the result of the “primary and active negligence” of contractors, as follows : operation of the crane in unusually close proximity to the transmission line; failure to warn plaintiff of the danger of working near the transmission line; failure to warn plaintiff of the proximity of the boom and cable to the transmission line when the crane was moving the concrete; placing the crane in a position near the transmission line; failure to notify Ozark of their intention to operate a crane in close proximity to the transmission line; failure to notify Ozark of their intention to pour concrete at that site on the day of the accident; failure to request Ozark to de-energize the wires; failure to request Ozark to place insulating materials over the energized wires; failure to request Ozark to have an employee present at the time and place. Ozark further alleged that any negligence on its part was passive, secondary and remote, and that if it is held liable to plaintiff by reason of the active negligence of contractors, Ozark is entitled to be fully indemnified and held harmless by contractors. Ozark referred to and attached to its amended third-party petition Pierce’s second amended petition for damages.

In answer to a request for admissions Ozark conceded that its line crosses the highway at the point in question, and that it knew generally that a culvert was to be constructed on Route BB in Ripley County, but denied that it knew when the culvert was to be constructed or on what day the concrete was to be poured; denied that it was advised that concrete would be poured that day; denied having been requested to de-energize its lines that day or at any other time at that site; denied knowledge that Pierce was working at the site that day; denied that it was requested to have an employee there that day; and claimed that it voluntarily relocated its wires by raising its primary wires to a height above the code requirements and in accordance with accepted engineering standards for the location of primary wire crossings of farm-to-market roads, by substituting a 45-foot pole for a 35-foot pole, thereby raising the line more than ten feet.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jorgensen v. City of Kansas City
725 S.W.2d 98 (Missouri Court of Appeals, 1987)
General Telephone Co. v. New Berlin Transit, Inc.
467 N.E.2d 382 (Appellate Court of Illinois, 1984)
State Ex Rel. Ashcroft v. Gibbar
575 S.W.2d 924 (Missouri Court of Appeals, 1978)
Simon v. Kansas City Rug Company
460 S.W.2d 596 (Supreme Court of Missouri, 1970)
Krug v. Sterling Drug, Inc.
416 S.W.2d 143 (Supreme Court of Missouri, 1967)
Western Casualty & Surety Co. v. Shell Oil Co.
413 S.W.2d 550 (Missouri Court of Appeals, 1967)
Listerman v. Day and Night Plumbing & Heating Serv.
384 S.W.2d 111 (Missouri Court of Appeals, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
378 S.W.2d 504, 1964 Mo. LEXIS 756, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pierce-v-ozark-border-electric-cooperative-mo-1964.