PIEDMONT ENVIRONMENTAL COUNCIL v. Strock

394 F. Supp. 2d 803, 2005 U.S. Dist. LEXIS 26552, 2005 WL 1330542
CourtDistrict Court, N.D. West Virginia
DecidedMay 6, 2005
DocketCiv.A. 3:02CV34
StatusPublished

This text of 394 F. Supp. 2d 803 (PIEDMONT ENVIRONMENTAL COUNCIL v. Strock) is published on Counsel Stack Legal Research, covering District Court, N.D. West Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PIEDMONT ENVIRONMENTAL COUNCIL v. Strock, 394 F. Supp. 2d 803, 2005 U.S. Dist. LEXIS 26552, 2005 WL 1330542 (N.D.W. Va. 2005).

Opinion

MEMORANDUM OPINION GRANTING DEFENDANTS’ MOTIONS FOR SUMMARY JUDGMENT

BROADWATER, District Judge.

I. Introduction

Plaintiffs Piedmont Environmental Council, Route 9 Opposition Legal Fund, West Virginia Rivers Coalition, Friends of Summit Point, Nancy Wilson, and John Porter (“Plaintiffs”), filed this action in this Court on April 23, 2002 against Major General Carl A. Strock, Chief Engineer and Commander, United States Army Corps of Engineers and Fred Vankirk, Secretary, West Virginia Department of Transportation, (“the Corps”, ‘WVDOT”, or collectively “the agencies”), seeking to restrain the construction of a 4.6 mile four-lane highway from Charles Town, West Virginia to the Virginia state line. Pending before the Court are the agencies’ motions for summary judgment (Docket numbers 91 and 93) and Plaintiffs’ motion for summary judgment (Docket number 87). For the reasons set forth herein, the Court GRANTS the agencies’ motions for summary judgment and DENIES Plaintiffs’ motion for summary judgment.

II. Factual and Procedural Background

This action is the second case involving Plaintiffs’ efforts to stop the construction of a new four lane divided highway from Charles Town, West Virginia to the Virginia state line. The first litigation began on December 13, 2001, when Plaintiffs sued the Federal Highway Administration (“FHWA”) and WVDOT asserting that FHWA’s environmental impact statement *806 (“EIS”) was arbitrary and capricious and not in accordance with the law. (“Route 9 I”). By order dated August 2, 2002, this Court granted Defendants’ motions for summary judgment, ruling that the EIS was not arbitrary capricious or contrary to law. See Route 9 Opposition Legal Fund v. Mineta, 213 F.Supp.2d 637 (N.D.W.Va.2002). The United States Court of Appeals for the Fourth Circuit affirmed this Court’s decision. See Route 9 Opposition Legal Fund v. Mineta, No. 02-2007, 2003 WL 22119924, at *1 (4th Cir. Sept. 15, 2003) (unpublished).

This case involves virtually the same Plaintiffs and their continued efforts to stop the construction of a new West Virginia Route 9. The current Route 9 is a winding two lane road which runs from Berkeley Springs, West Virginia to the western portion of Loudoun County, Virginia. Because of the increased amount of residential and commercial growth in the Eastern Panhandle of West Virginia and the surrounding region, in the early 1990s the State of West Virginia, along with local community leaders, determined that the existing Route 9 was no longer meeting the transportation needs of the region’s commuters and residents. WVDOT therefore began studying the possibilities of upgrading or replacing the existing Route 9.

After federal funding was secured, FHWA began a review of the environmental impacts of the project in accordance with the National Environmental Policy Act (“NEPA”), 42 U.S.C. §§ 4321-70 (2003). As required by the statute, FHWA’s NEPA review consisted of preparing an EIS. In early 1993, the Corps agreed to become a cooperating agency in the FHWA’s EIS and participated in the NEPA review process. In October 2000, FHWA issued a Final EIS (“FEIS”) for public comment. After comments were received, FHWA selected and approved on January 4, 2001, WVDOT’s preferred alternative which was to build a new four-lane divided highway from Charles Town, West Virginia to the Virginia state line. As part of the new highway, a new four-lane bridge over the Shenandoah River would be built, a small perennial stream (Grog Spring Run) would be relocated, and two farm ponds east of the river would be filled.

Not only as a cooperating agency with FHWA, the Corps participated in the EIS process because several of the proposed alternatives would have an impact on navigable waters. As such, on October 2, 2001, WVDOT applied for a permit from the Corps under Section 404 of the Clean Water Act, 33 U.S.C. § 1344 (2003), (“CWA”) in relation to the project. The application described the project as constructing a six-span bridge over the Shenandoah River, a causeway for construction of piers, the relocation of 2,458 feet of Grog Spring Run, and the filling of two ponds totaling 0.64 acres of open water and 0.14 acres of wetland fringe. In addition to the review required under the CWA, the Corps also undertook its own analysis as required under NEPA. After completing the environmental analysis required under NEPA, which included receiving public comments and meeting with various Federal, State, and Local Agencies, the Corps issued an Environmental Assessment (“EA”)/Finding of No Significant Impact (“FONSI”) on October 16, 2002. On October 23, 2003, the Corps issued to WVDOT a permit under the CWA Section 404 for the project. Plaintiffs seek judicial review of the Corps issuance of the permit under Section 404 of CWA and the Corps NEPA review.

The instant complaint was filed on April 23, 2002 and alleges that the Corps violated CWA because the decision to issue the Section 404 permit was arbitrary, capri *807 cious, and not in accordance with law. The complaint also alleges that the Section 404 permit decision is not legally adequate under NEPA and its implementing regulations. The complaint also contained a claim that Defendants violated the Administrative Procedures Act (“APA”). On December 27, 2002, Plaintiffs filed a First Amended Complaint. On March 31, 2004, the Court granted Defendant’s motion to dismiss the APA claim finding that the statute did not provide Plaintiffs with a separate cognizable cause of action; rather, the APA was merely a procedural vehicle to bring the CWA and NEPA claims. See Piedmont Environmental Council v. Flowers, 319 F.Supp.2d 678, 682 (N.D.W.Va.2004). That same order granted Defendants’ motion in limine barring Plaintiffs from relitigating NEPA claims from Route 9 I. Specifically, the Court ruled in Route 9 I that FHWA’s FEIS adequately contained a discussion of alternatives and considered the indirect environmental impacts of constructing the road. See id. at 681-82. Thus, that ruling may not be relitigated in this action.

As a result of these rulings, Plaintiffs filed a motion for leave to file a Second Amended Complaint on June 15, 2004, seeking to add new allegations relating the Corps’ NEPA review and a more specific CWA claim. On August 19, 2004, the Court denied the motion as to the CWA claim (Count I) and granted the motion as to the NEPA claim (Count II). Thus, the claims that are properly before the Court are the CWA claim from the First Amended Complaint (Count I) and the NEPA claim from the Second Amended Complaint (Count II).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sierra Club v. U.S. Army Corps of Engineers
295 F.3d 1209 (Eleventh Circuit, 2002)
Citizens to Preserve Overton Park, Inc. v. Volpe
401 U.S. 402 (Supreme Court, 1971)
United States v. Riverside Bayview Homes, Inc.
474 U.S. 121 (Supreme Court, 1985)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Christianson v. Colt Industries Operating Corp.
486 U.S. 800 (Supreme Court, 1988)
Robertson v. Methow Valley Citizens Council
490 U.S. 332 (Supreme Court, 1989)
Marsh v. Oregon Natural Resources Council
490 U.S. 360 (Supreme Court, 1989)
Piedmont Environmental Council v. Flowers
319 F. Supp. 2d 678 (N.D. West Virginia, 2004)
Route 9 Opposition Legal Fund v. Mineta
213 F. Supp. 2d 637 (N.D. West Virginia, 2002)
Hughes River Watershed Conservancy v. Glickman
81 F.3d 437 (Fourth Circuit, 1996)
Kentuckians for the Commonwealth, Inc. v. Rivenburgh
317 F.3d 425 (Fourth Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
394 F. Supp. 2d 803, 2005 U.S. Dist. LEXIS 26552, 2005 WL 1330542, Counsel Stack Legal Research, https://law.counselstack.com/opinion/piedmont-environmental-council-v-strock-wvnd-2005.