Piccolella v. Lycoming County Zoning Hearing Board

984 A.2d 1046, 2009 Pa. Commw. LEXIS 1623, 2009 WL 4432371
CourtCommonwealth Court of Pennsylvania
DecidedDecember 4, 2009
DocketNo. 124 C.D. 2009
StatusPublished
Cited by7 cases

This text of 984 A.2d 1046 (Piccolella v. Lycoming County Zoning Hearing Board) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Piccolella v. Lycoming County Zoning Hearing Board, 984 A.2d 1046, 2009 Pa. Commw. LEXIS 1623, 2009 WL 4432371 (Pa. Ct. App. 2009).

Opinion

OPINION BY

Judge SIMPSON.

In this zoning appeal, Frank M. Piccolel-la, Sr. (Objector), representing himself, *1049 asks whether the Lycoming County Zoning Hearing Board (ZHB) erred in dismissing his appeal from the Lycoming County Zoning Administrator’s (Zoning Administrator) grant of a zoning permit to Laurel Hill Wind Energy, LLC (Laurel Hill). Laurel Hill applied for the zoning permit in order to construct a proposed wind energy facility. Objector argues the ZHB erred in dismissing his appeal where Laurel Hill’s permit application did not satisfy the applicable requirements of the Lycoming County Zoning Ordinance (zoning ordinance). Objector also claims the ZHB violated his right to due process. Discerning no merit in these contentions, we affirm.

In February 2008, Laurel Hill filed a detailed application for a zoning permit for a project it refers to as the “Laurel Hill Wind Energy Project.” Specifically, Laurel Hill proposed to construct a 70.5 megawatt wind-powered electric-generating, transmitting and interconnecting facility consisting of: 35 individual wind turbines located along Laurel Hill Ridge; an approximate two-mile long, 34.5 kilovolt, overhead transmission line; and, a new switch yard and substation that would provide interconnection to the existing electric transmission system of the Pennsylvania Electric Company. The project would occupy an area of approximately 706 leased acres located in both the Agricultural and Resource Protection Districts in Jackson and McIntyre Townships, Lycoming County-

Laurel Hill’s zoning permit application included: a 19-page community and environmental impact analysis; three tables showing estimated project expenditures; an evaluation of the indirect economic activity from construction and annual economic contribution of the project; a FEMA map; and, several appendices, which include a general site plan, a permit/approval project schedule, a hydrologic evaluation of wind turbine construction, a hydrogeologic evaluation plan summary; a report on the effect of wind development on local property values; and, a draft emergency response plan. In addition to the application itself, Laurel Hill provided the Zoning Administrator with a decommissioning plan, a resolution of approval from the McIntyre Township Board of Supervisors with an attached Wind Fund Agreement, a Pennsylvania Game Commission Wind Energy Voluntary Cooperation Agreement, and supplemental information regarding proposed routes of construction and access roads.

After his review, the Zoning Administrator approved the application in May 2009. Among other things, the Zoning Administrator explained:

[Pjlease be aware that pursuant to Section 3230C.l(2)(a) of the [zoning ordinance], evidence of permits and conditions to satisfy all applicable [s]tate and [flederal agencies is required prior to the issuance of a[c]ertificate of [occupancy. Land development approval is required in accordance with [zoning ordinance] Section 10130C.
The issuance of this permit evidences my approval of your [application conditioned on satisfying the requirements noted above....

Certified Record (C.R.), ZHB Hearing, 7/23/08, Zoning Administrator Ex. 13; ZHB Op., Finding of Fact (F.F.) No. 11.

Shortly thereafter, Objector appealed the Zoning Administrator’s approval of the permit, asserting Laurel Hill’s application contained 28 deficiencies. Among other things, Objector argued the application did not satisfy Section 3230C.1 (relating to wind energy facilities) and Section 10240 (relating to general site plan requirements) of the zoning ordinance. A hearing ensued before the ZHB, at which Objector *1050 provided an explanation of the alleged deficiencies in Laurel Hill’s permit application, and the Zoning Administrator presented numerous documents relating to his review of Laurel Hill’s permit application.

After hearing, the ZHB issued a decision in which it determined Laurel Hill’s application was sufficiently complete to warrant the Zoning Administrator’s issuance of the permit. The ZHB specifically found, as part of the permit review process, Laurel Hill submitted, and the Zoning Administrator reviewed, information required by the zoning ordinance including, but not limited to, a site plan, a community and environmental impact analysis, a detailed explanation of tower safety, operations, setbacks, tower locations, signal interference, liability insurance, host municipality agreements, and a decommissioning agreement.

The ZHB further found, although Objector alleged various deficiencies in the information provided, it was clear that Laurel Hill’s detailed and specific plans were “consistent with the procedures outlined by the requirements of the [zjoning [ordinance, and, in fact, [were] substantially complete.” F.F. No. 17. The ZHB also found it clear from the record that, through the permit review process, the Zoning Administrator elicited clarifications and additional information from Laurel Hill to further detail and explain the project. In addition, the ZHB found:

19. The substantial, competent and credible evidence of record shows that the [application itself is sufficiently complete for the issuance of a permit, although details of the project may be subject to change under the supervision of the Zoning Administrator and the Planning Commission for compliance with the terms of the [z]oning [ordinance and the [planning [c]ode.
20. The [ZHB] does not find credible the assertion of [Objector] that the [application is so incomplete, so lacking in detail, so vague or ambiguous as to preclude [z]oning review for the permitted use described by [Section 3230C.1 of the zoning ordinance], or that the Zoning Administrator failed to undertake the necessary review. To the contrary, the Zoning Administrator[’s][e]xhibits above-listed credibly show that such assertions are without merit by detailing information obtained, clarifications requested, conditions to be met, and a process of ongoing review.

F.F. Nos. 19-20. The ZHB also determined:

6. It is clear, based upon the undisputed facts of record, that the [p]ermit [alp-plication filed by Laurel Hill describes a wind energy facility to be located in a Resource Protection and Agricultural Zone, as those Zones are defined by the [zoning ordinance]. Moreover, it is clear that a wind energy facility is a permitted use in both Resource Protection and Agricultural Zones under the terms of the [zoning ordinance], [Section 3230C.1 of the zoning ordinance; Table of Uses Section 3120].
7. [Zoning] [opdinance Section 3230C.1 requires the Zoning Administrator to confirm that the [applicant has submitted sufficient information to allow for the supervision of this permitted use.
8. Indeed, the [p]ermit [application itself, which allows for the issuance of a permit to commence the project, is not intended to include all the information necessary for the Zoning Administrator to issue a certificate of occupancy, the latter of which would be required before the facility could begin operation.
9.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

B&A Property, LLC v. Bensalem Twp. ZHB
Commonwealth Court of Pennsylvania, 2024
A.A. Goode v. Housing Authority of the City of Shamokin
Commonwealth Court of Pennsylvania, 2019
S.D. v. D.D.
Superior Court of Pennsylvania, 2017
Hummelstown Swim Club v. Borough of Hummelstown
Commonwealth Court of Pennsylvania, 2017
Pa. State Police v. Slaughter
138 A.3d 65 (Commonwealth Court of Pennsylvania, 2016)
TETSO v. State
45 A.3d 788 (Court of Special Appeals of Maryland, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
984 A.2d 1046, 2009 Pa. Commw. LEXIS 1623, 2009 WL 4432371, Counsel Stack Legal Research, https://law.counselstack.com/opinion/piccolella-v-lycoming-county-zoning-hearing-board-pacommwct-2009.