Piccadilly Square v. Intercontinental Construction Co.

782 S.W.2d 178, 1989 Tenn. App. LEXIS 595
CourtCourt of Appeals of Tennessee
DecidedSeptember 8, 1989
StatusPublished
Cited by11 cases

This text of 782 S.W.2d 178 (Piccadilly Square v. Intercontinental Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Piccadilly Square v. Intercontinental Construction Co., 782 S.W.2d 178, 1989 Tenn. App. LEXIS 595 (Tenn. Ct. App. 1989).

Opinion

OPINION

LEWIS, Judge.

Plaintiff, Piccadilly Square, a Joint Venture of Crowe-Proctor, Inc., Allen Khalili and Harold Morris, filed its complaint against defendants, Intercontinental Construction Co., Inc. (Intercontinental), Ali Noureddini and Akbar Arab, 1 for an alleged breach of contract and fraud. Following a bench trial the Chancellor entered a judgment against the defendants “in the amount of $112,000.00, plus interest at the rate of ten percent from November 29, 1984 to date of entry of the judgment.”

Plaintiff’s complaint sought to enforce a contract (hereafter Construction Agreement) entered into on 28 October, 1983, with Intercontinental. The Construction Agreement provided, inter alia, that Intercontinental would construct duplex townhouses in a development in Davidson County, Tennessee, known as Piccadilly Square. Intercontinental agreed to construct each unit for a turn-key price. The units would be pre-sold by plaintiff to purchasers for a higher price than the turn-key price. Plaintiff would be entitled to the difference between the turn-key price and the price for which plaintiff had pre-sold the unit. The Agreement further provided that Intercontinental would construct “a minimum of eleven (11) or a maximum of thirty-five (35) of these buildings,” at plaintiff’s option.

Differences arose between plaintiff and Intercontinental and, on 22 October 1984, a Compromise and Settlement Agreement was entered into which, among other things, modified the Construction Agreement by increasing the turn-key price Intercontinental would receive. Intercontinental had commenced the construction of ten units and the Compromise and Settlement Agreement relieved it from constructing the remaining twenty-five units.

*180 Defendants Ali Noureddini and Akbar Arab, the principals of Intercontinental, were sued individually for fraud on the ground that they caused Intercontinental to fraudulently convey the units to themselves. Plaintiff alleged that they then sold the units and kept the proceeds in excess of the turn-key price even though under the Construction Agreement Intercontinental was to remit the difference between the turn-key price and the sales price to plaintiff.

The trial began on 29 September 1986. During cross-examination of plaintiffs first witness, defendants moved to amend their answer, asserting that they had just learned facts which would support a recision of the Compromise and Settlement Agreement. A continuance was granted and thereafter defendants filed an amended answer alleging that the Compromise and Settlement Agreement was void because it was fraudulently induced. Defendants-asserted that a major consideration of Intercontinental in signing the Compromise and Settlement Agreement was to obtain relief from the provision of the Construction Agreement which required Intercontinental to continue to build units on the remaining lots at the plaintiffs option. Defendants insisted that the plaintiff fraudulently concealed the fact that it had transferred the remaining lots prior to the negotiation of the Compromise and Settlement Agreement and withheld this information in order to induce Intercontinental to enter into the Compromise and Settlement Agreement. Approximately thirteen months later, on 2 November 1987, the trial resumed. Evidence was completed on 3 November 1987 and the Chancellor took the matter under advisement, rendering a Memorandum Opinion on 16 August 1988. The Memorandum Opinion was amended on 19 September 1988.

THE FACTS

Plaintiff was formed in the summer of 1983 as a joint venture between Crowe-Proctor, Inc., Allen Khalili and Harold Morris for the purpose of developing real property.

Following the formation of the joint venture, an evaluation of various properties was begun. On 27 September 1983, plaintiff entered into a real estate sales contract with Wellington Enterprises, Inc. for the purchase of twenty-two lots located on Antioch Pike in Davidson County, Tennessee (The Piccadilly Square Subdivision property). Plaintiff also had an option to purchase thirteen additional lots. Plaintiff, after having secured the property, performed market studies and financial projections. The evidence is that numerous hours were spent determining which type of buildings should go on the property, projecting rental income, and calculating potential return on the investment in the units and developing plans and specifications. After this was done, the next step was to find a contractor.

After talking with several contractors, plaintiff entered into the Construction Agreement with Intercontinental on 28 October 1983. Intercontinental is a company that has always represented itself to be an experienced construction company.

The Construction Agreement contains the following pertinent provisions: (1) Intercontinental would acquire eleven of the lots which plaintiff had contracted to buy from Wellington Enterprises, Inc. and build eleven duplex townhouses. It also provided for the construction of additional units at the option of plaintiff; (2) Intercontinental would construct the units for $67,490 per duplex building. This would include the cost of the lot, loan costs, interest and costs and fees incurred in selling the constructed duplex to purchasers; (3) Intercontinental would obtain construction loans in its own name; (4) Intercontinental would acquire the lots in its own name and pay the lot price from the construction loan; (5) plaintiff would pre-sell the units by getting purchasers to obtain commitments for permanent loans and “take-out” Intercontinental from the construction loan; (6) Intercontinental would pay all charges incurred as a result of delay in construction regardless of who caused the delay; (7) if Intercontinental failed to complete the units in “strict compliance” with the plans and specifica *181 tions, neither the plaintiff nor the investor would have an obligation to close; (8) if Intercontinental could not complete any phase of the construction for any reason, regardless of fault, or if plaintiff decided the construction loan pay-off substantially exceeded the construction price, plaintiff had the “unequivocal right to terminate the contract and to be indemnified” by Intercontinental; (9) plaintiff would pre-sell the units to investors and Intercontinental was required to execute a contract with the investor; (10) Intercontinental could not modify or alter the terms of the designated contract, either unilaterally or with the approval of the other contracting party; (11) if Intercontinental breached the contract with the third-party purchaser, it constituted a breach of Intercontinental’s obligation to plaintiff; and (12) the contract sales price for which the units could be sold to a third party was set by plaintiff, from which the sum $5,150 would be immediately paid to plaintiff to off-set “front-end” marketing and “negative cash flow expenses.”

Through plaintiffs efforts, Dave Rowland agreed to purchase eleven units. Pursuant to the Construction Agreement, on 20 December 1983, Intercontinental entered into a “Contract For The Sale of Real Estate” with Dave Rowland. Mr. Rowland agreed to purchase eleven 2-story duplex townhouses and Intercontinental agreed to construct the eleven duplex townhouses in the Piccadilly Square Subdivision. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Branhaven, LLC v. BeefTek, Inc.
965 F. Supp. 2d 650 (D. Maryland, 2013)
Joyann E. Butler v. James Michael Butler
Court of Appeals of Tennessee, 2008
Bennett v. Visa U.S.A. Inc.
198 S.W.3d 747 (Court of Appeals of Tennessee, 2006)
Helen S. Rogers v. Tom E. Watts, Jr. - Concurring
Court of Appeals of Tennessee, 1997
In Re Carolina Steel Corp.
179 B.R. 413 (S.D. New York, 1995)
Plough, Inc., Cross v. Rei, Inc.
9 F.3d 1548 (Sixth Circuit, 1993)
Hill v. John Banks Buick, Inc.
875 S.W.2d 667 (Court of Appeals of Tennessee, 1993)
Beasley v. Horrell
864 S.W.2d 45 (Court of Appeals of Tennessee, 1993)
Axline v. Kutner
863 S.W.2d 421 (Court of Appeals of Tennessee, 1993)
Dobbs v. Guenther
846 S.W.2d 270 (Court of Appeals of Tennessee, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
782 S.W.2d 178, 1989 Tenn. App. LEXIS 595, Counsel Stack Legal Research, https://law.counselstack.com/opinion/piccadilly-square-v-intercontinental-construction-co-tennctapp-1989.