Phillips Pipe Line Co. v. McKown

580 S.W.2d 435, 1979 Tex. App. LEXIS 3507
CourtCourt of Appeals of Texas
DecidedApril 12, 1979
Docket1165
StatusPublished
Cited by16 cases

This text of 580 S.W.2d 435 (Phillips Pipe Line Co. v. McKown) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phillips Pipe Line Co. v. McKown, 580 S.W.2d 435, 1979 Tex. App. LEXIS 3507 (Tex. Ct. App. 1979).

Opinion

MOORE, Justice.

The opinion delivered on January 11, 1979, is withdrawn and the following opinion substituted in lieu thereof.

Plaintiffs, O. B. McKown, Jr., and 1826 Associates, Ltd., 1 brought suit against Phillips Pipe Line Company, Inc. (Phillips), and Panhandle Construction Company, Inc. *437 (Panhandle), for damages arising out of the construction of a pipeline across plaintiffs’ land on which Phillips owned a right-of-way easement. As grounds for a cause of action plaintiffs alleged: (1) that Phillips and its contractor, Panhandle, were guilty of negligence in the manner in which the land was used which resulted in damages to the land; (2) that they had trespassed on more land than was reasonably necessary for the construction of the line; (3) that Phillips breached its contract to restore the land to its original condition after the pipeline had been laid; and (4) that Phillips breached its agreement not to encroach, in any degree, on that portion of the lands which had been designated as a cemetery area. Plaintiffs further alleged that Phillips was responsible for the acts and omissions of its contractor, Panhandle, and prayed for a judgment against both defendants jointly and severally-

Phillips answered with a general denial and affirmatively alleged that it owned a right-of-way easement across plaintiffs’ property, and therefore had a right to use the land for the purpose of constructing the pipeline. Phillips further denied that it contracted to pay plaintiffs for damages to the land and specially denied that either it or its agents, servants or employees were guilty of negligence in the construction of the pipeline across plaintiffs’ land.

On the day of the trial plaintiffs settled with Panhandle for the sum of $22,500.00 and dismissed its cause against Panhandle with prejudice. Phillips then filed a petition alleging Panhandle was an independent contractor and therefore Phillips was not liable for the acts and conduct of its independent contractor in constructing the line. Phillips further alleged that Panhandle was Phillips’ indemnitor and that the conduct of the plaintiffs in releasing and dismissing Panhandle from the suit, also had the effect of releasing Phillips from any and all liability for plaintiffs’ claim for damages. After a trial before a jury, the trial court entered judgment on the verdict, awarding plaintiffs damages in the amount of $33,293.39, 2 from which Phillips perfected this appeal.

We affirm in part and reverse and render in part.

The evidence shows that the plaintiffs were the owners of two adjoining tracts of land in Travis County lying to the southwest of the city of Austin. Mr. McKown individually owned 82.01 acres and 1826 Associates, Ltd., owned an adjoining tract consisting of approximately 280 acres.

By instruments dated December 5, 1928, and February 25, 1929, plaintiffs’ predecessor in title conveyed to Shell Pipe Line Corporation an easement across the property in question. Effective April 30, 1953, Phillips acquired all rights to this easement and to a 10-inch diameter pipeline located thereunder. Shell Pipe Line Corporation also maintained another pipeline under the easement so that at the time of this suit plaintiffs’ property was burdened with two pipelines a short distance apart. The easement did not restrict the width of the pipeline right-of-way nor did it restrict the width in which the easement owner was permitted to work in the course of repairing, replacing or relocating any of the pipelines thereunder. Under the terms of the easement the grantee agreed to pay only for such damages as might arise to “crops, timber, fences, and buildings” caused by the construction of pipelines across the land.

In 1973, Phillips commenced replacing a 47-mile long stretch of pipeline through Hayes, Travis, and Bastrop counties. The work on the pipeline located on plaintiffs’ land was performed between April and August of 1973. Prior to the time of the commencement of the pipeline, Phillips entered into a written contract with Panhandle to do the construction work. Under the terms of the contract, Panhandle was to do all of the construction work for a fixed price and no part of the work was to be performed by Phillips. It was agreed between Phillips and Panhandle that the max *438 imum width of the right-of-way in which Panhandle would construct the line would be 50 feet. Panhandle further agreed to indemnify and hold Phillips harmless from any and all damages resulting from the construction of the pipeline. The evidence shows that Panhandle performed all of the construction work. There are no findings that Phillips was guilty of any independent negligence apart from Panhandle or of any concurrent acts which contributed to the damages complained of by plaintiffs.

The cause was submitted to the jury on twenty-eight special issues, each of which assumed that Phillips was the principal actor and was primarily liable to the plaintiffs. The judgment recites that the total amount of damages awarded to plaintiffs was based exclusively on the jury’s findings to Special Issues 14, 16, 23, 27 and 28. Although the jury made other findings that Phillips breached its contract to pay plaintiffs for damages to the land and awarded damages therefor, the court refused to enter judgment on those findings (Special Issues 5 and 26).

Since the trial court did not render judgment based on Phillips’ alleged breach of its contractual agreement to pay damages for injury to the land, and since plaintiffs failed to complain of this on appeal, the questions to be determined are whether, when the plaintiffs released Panhandle, Phillips may be held liable to plaintiffs for (1) the acts and conduct of Panhandle, its independent contractor and indemnitor, for injury to the land; and (2) the acts and conduct of Panhandle in trespassing on plaintiff O. B. McKown’s cemetery area, causing him physical pain and mental anguish.

Phillips contends under its first point of error that by the conduct of the plaintiffs in releasing and promising to protect Panhandle, its independent contractor and indemnitor, plaintiffs are precluded from recovering any further damages to the land from Phillips because the release of Panhandle also had the effect of releasing Phillips. Therefore, Phillips takes the position that the court erred in awarding plaintiffs a judgment for permanent damages to the land and damages for restoration of the land as found by the jury in response to Special Issues 14,27 and 28. As we view the record, this contention must be sustained.

Instead of constructing the line itself, Phillips employed Panhandle to do the work. The line was to be constructed according to detailed plans and specifications as set forth in a lengthy written contract. Panhandle was to do all the work at a fixed price and repair and restore the land after the completion of the work. Under the terms of the contract, Phillips had no concern for the undertaking except the finished product. Although Phillips had a right to have its inspectors on the job see that the contract was complied with, the contract recited that Panhandle was an independent contractor. There is nothing in the record showing that Phillips exercised any control over the work or had a right to exercise any control over the details of the work. Under the holding in

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Day Cruises Maritime, L.L.C. v. Christus Spohn Health System
267 S.W.3d 42 (Court of Appeals of Texas, 2008)
Refinery Holding Co. v. TRMI Holdings, Inc.
302 F.3d 343 (Fifth Circuit, 2002)
Wolfenberger v. Houston Lighting & Power Co.
73 S.W.3d 444 (Court of Appeals of Texas, 2002)
Shaffer v. Acme Limestone Co., Inc.
524 S.E.2d 688 (West Virginia Supreme Court, 1999)
Channel Equipment Co. v. Community State Bank
996 S.W.2d 374 (Court of Appeals of Texas, 1999)
Fina, Inc. v. Arco
16 F. Supp. 2d 716 (E.D. Texas, 1998)
Duran v. Furr's Supermarkets, Inc.
921 S.W.2d 778 (Court of Appeals of Texas, 1996)
Taylor v. Sunbelt Management, Inc.
905 S.W.2d 743 (Court of Appeals of Texas, 1995)
Ross v. Texas One Partnership
796 S.W.2d 206 (Court of Appeals of Texas, 1990)
Starcraft Co. v. C.J. Heck Co. of Texas, Inc.
748 F.2d 982 (Fifth Circuit, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
580 S.W.2d 435, 1979 Tex. App. LEXIS 3507, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phillips-pipe-line-co-v-mckown-texapp-1979.