Phillips Petroleum Co. v. Federal Energy Regulatory Commission

792 F.2d 1165, 253 U.S. App. D.C. 211, 1986 U.S. App. LEXIS 25922
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 13, 1986
DocketNo. 85-1427
StatusPublished
Cited by5 cases

This text of 792 F.2d 1165 (Phillips Petroleum Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phillips Petroleum Co. v. Federal Energy Regulatory Commission, 792 F.2d 1165, 253 U.S. App. D.C. 211, 1986 U.S. App. LEXIS 25922 (D.C. Cir. 1986).

Opinion

Opinion for the Court filed by Circuit Judge HARRY T. EDWARDS.

HARRY T. EDWARDS, Circuit Judge:

Section. 104 of the Natural Gas Policy Act of 1978 (“NGPA”) provides that the maximum lawful price for the first sale of natural gas committed to interstate commerce on November 8, 1978 shall be “the just and reasonable rate ... established by the Commission which was (or would have been) applicable to ... such natural gas on April 20, 1977.” 1 As is all too often the case with deceptively simple statutory provisions, section 104 admits of a troublesome ambiguity: there are two different sources of natural gas — gas produced by pipeline companies and gas produced by independent companies — and there were separate rate structures for these different sources of natural gas in April 1977. While pipeline-produced gas rates were set pursuant to cost-of-service rate making on a pipeline by pipeline basis, independent-producer gas rates were set on a national basis. Thus, in implementing section 104, it is unclear whether Congress intended the Federal Energy Regulatory Commission (“FERC” or “Commission”) to look to the April 1977 rate for the gas of a particular pipeline or the April 1977 rate that had been established for independent gas.

Believing itself bound by the Supreme Court’s decision in Public Service Commission of New York v. Mid-Louisiana Gas Co.,2 FERC issued regulations that set the section 104 price ceilings at the April 1977 independent-producer national levels for both pipeline-produced gas and independent-producer gas. Phillips Petroleum Company (“Phillips”), an independent producer, challenges this resolution of the statutory ambiguity, arguing that section [213]*213104 requires FERC to apply the national rates only to independent-producer gas and to price pipeline gas at the April 1977 cost-of-service rate then in effect for each pipeline.

Although under Chevron U.S.A., Inc. v. Natural Resources Defense Council, Inc.,3 the FERC interpretation is arguably a permissible reading of section 104, FERC did not purport to give its own reading to the statute; rather, it believed that its interpretation of section 104 was mandated by Mid-Louisiana. Because we conclude that the Mid-Louisiana decision required no such interpretation, we hold that, under the principles of SEC v. Chenery Corp.,4 a remand is necessary to allow FERC to reconsider the proper construction of section 104.

I. Background

This case can be understood only in the context of the evolution of natural gas price policy in the last few decades. Beginning in 1938, FERC’s predecessor, the Federal Power Commission (“FPC”), regulated sales of natural gas in interstate commerce under the Natural Gas Act (“NGA”). Initially, the FPC took the position that it need not directly review the price that independent producers charged pipelines at the wellhead because the price of natural gas was regulated at the downstream end of interstate pipelines. In other words, the Commission only evaluated the reasonableness of the price of pipeline-produced gas by examining the “cost-of-service” incurred in producing and transporting the gas. Under this cost-of-service rate making, the FPC set only the downstream rates charged to gas distributors for pipeline gas. Gas production expenses were treated merely as costs that the FPC evaluated for reasonableness.

This procedure changed in 1954 when the Supreme Court, in Phillips Petroleum Co. v. Wisconsin,5 held that the Natural Gas Act required the FPC to evaluate the reasonableness of rates charged by independent producers of gas. At first, the FPC fulfilled this obligation by simply using a cost-of-service methodology for all natural gas produced — whether by an independent producer, a pipeline company or an affiliate of a pipeline company. Ultimately, however, this approach proved impractical. The number of pipeline companies was relatively small, but the number of independent-gas producers was far too large for the use of a cost-of-service methodology. As a result, in 1960 the FPC changed its method of regulating independent producers. Instead of establishing individual rates for each producer, it established rates applicable to all producers in an assigned production region.

The FPC continued to use cost-of-service rate making for the pricing of gas produced by pipeline companies and pipeline affiliates until 1969. In that year, the FPC decided to apply the regional producer rates to all gas produced by pipeline companies from leases acquired after October 7, 1969. For the pipeline-produced gas still priced by cost-of-service rate making, however, the Commission did not set a just and reasonable rate for the wellhead price of gas. Instead, the FPC continued its practice of using cost-of-service rate making to set only the downstream rates charged gas distributors, with gas acquisition costs tested for “prudence.”

The next significant change took place in 1974, when the FPC shifted from regional rates to a single national rate applicable to both gas produced by independent companies and new gas produced by pipeline companies. Thus, by April 20, 1977, the determinative date in this case, the following regulatory structure had evovled:

(1) Pipeline-company gas from wells drilled on or before January 1, 1973, or from leases acquired on or before October 7, 1969 was priced on a cost-of-service basis.
[214]*214(2) All other pipeline-produced gas was priced in .the same manner as gas produced by independent companies.
(3) Gas produced by independent companies was priced on a nationwide basis.

In 1978, Congress radically transformed the regulation of natural- gas by enacting the Natural Gas Policy Act of 1978. Title I of that Act established eight categories of natural gas production and set a ceiling price for all “first sales” 6 of gas in each category. Section 104 of the NGPA set a price ceiling for natural gas “committed or dedicated to interstate commerce” on the day before the enactment of the NGPA. The maximum lawful price for this gas is the just and reasonable rate established by the Commission for the gas under the NGA, increased by an inflation factor:

The maximum lawful price under this section for any month shall be the higher of—
(A)(i) the just and reasonable rate, per million Btu’s, established by the Commission which was (or would have been) applicable to the first sale of such natural gas on April 20, 1977, in the case of April 1977; and
(ii) in the case of any month thereafter, the maximum lawful price, per million Btu’s, prescribed under this subparagraph for the preceding month multiplied by the monthly equivalent of the annual inflation adjustment factor applicable for such month, or
(B) any just and reasonable rate which was established by the Commission after April 27, 1977, and before the date of the enactment of this Act and which is applicable to such natural gas.7

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cafritz Co. v. District of Columbia Rental Housing Commission
615 A.2d 222 (District of Columbia Court of Appeals, 1992)
Teamsters Local Union 1714 v. Public Employee Relations Board
579 A.2d 706 (District of Columbia Court of Appeals, 1990)
Pueblo of Santa Ana v. Hodel
663 F. Supp. 1300 (District of Columbia, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
792 F.2d 1165, 253 U.S. App. D.C. 211, 1986 U.S. App. LEXIS 25922, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phillips-petroleum-co-v-federal-energy-regulatory-commission-cadc-1986.