Phillips and Jordan Inc v. McCarthy Improvement Inc

CourtDistrict Court, D. South Carolina
DecidedDecember 1, 2019
Docket5:18-cv-00559
StatusUnknown

This text of Phillips and Jordan Inc v. McCarthy Improvement Inc (Phillips and Jordan Inc v. McCarthy Improvement Inc) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phillips and Jordan Inc v. McCarthy Improvement Inc, (D.S.C. 2019).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF SOUTH CAROLINA ORANGEBURG DIVISION

Phillips and Jordan, Inc., ) Civil Action No. 5:18-cv-00559-JMC ) Plaintiff, ) ) v. ) ORDER AND OPINION ) Western Surety Company; ) McCarthy Improvement Company, ) ) Defendants. ) ____________________________________)

This action arises from a contract dispute between Plaintiff Phillips and Jordan, Inc., and Defendants Western Surety Company1 (“WSC”) and McCarthy Improvement Company (“MIC”) (collectively “Defendants”). The matters before the court are Plaintiff’s and Defendants’ Motions for Partial Summary Judgment (ECF Nos. 83, 84, 85). For the reasons set forth below, the court DENIES Plaintiff’s and Defendants’ motions. I. JURISDICTION The court has subject matter jurisdiction pursuant to 28 U.S.C. § 1332(a) (2012). (ECF Nos. 11 at 1 ¶ 4; 18 at 15, 18 ¶¶ 1-2, 18.) Diversity jurisdiction requires complete diversity of parties and an amount in controversy in excess of $75,000.00, exclusive of interest and costs. See 28 U.S.C. §1332(a). Complete diversity of parties in a case means that no party on one side may be a citizen of the same state as any party on the other side. See Owen Equip. & Erection Co. v. Kroger, 437 U.S. 365, 372 (1978). There is diversity jurisdiction in this case because the parties

1 MIC obtained a payment bond from WSC as required by South Carolina law, with MIC as the principal and WSC as the surety. WSC agreed to be bound jointly and severally with MIC to all persons furnishing labor or materials to the project if MIC failed to make prompt payment to such persons. (ECF No. 1-2 at 1-4.) have sufficiently pleaded that Plaintiff is organized under the laws of North Carolina and has a principal place of business in Tennessee; WSC is organized under the laws of, and has a principal place of business in, South Dakota; and that MIC is organized under the laws of, and has a principal place of business in, Iowa. (ECF Nos. 11 at 1 ¶¶ 1-3; 18 at 15 ¶ 2.) II. FACTUAL AND PROCEDURAL BACKGROUND

On September 23, 2013, MIC contracted with the South Carolina Department of Transportation (“SCDOT”) on a design-build project known as the “Interstate 95/U.S. Route 301 Interchange & South Carolina Route 6 Connector” in Orangeburg, South Carolina. (ECF No. 1-1 at 1-79.) MIC entered a subcontract with Plaintiff on October 14, 2014 to work on part of the project. (ECF No. 1-3 at 1 (“By means of this Agreement, [Plaintiff] does agree to furnish, erect[,] and install all materials and perform all work and in every respect complete the [project] . . . .”).) Plaintiff characterizes the subcontract as an agreement “to perform dirt work on the [p]roject.” (ECF No. 83 at 5 (citing ECF No. 1-3 at 1-55).) Plaintiff claims that shortly after the execution of the subcontract, MIC issued a schedule to Plaintiff with a date of completion in June 2015. (ECF

Nos. 83-2 at 19; 84-10 at 9.) MIC’s plan for securing and providing the quantities of fill to build the roadway embankment “primarily relied upon an assumption that enough quantities of acceptable soils could be obtained by over-excavating the onsite detention ponds.” (ECF No. 4, 5 ¶ 28; see e.g., 83-1 at 3.) However, Plaintiff alleges that soon after it began performance in 2014, “the quality of the onsite soils to be excavated and used as fill became suspect.” (Id. at 6 ¶ 34.) Plaintiff alleges that “substantial quantities of the onsite soils failed to meet the required specifications for use as fill material, which was contrary to MIC’s design and plan for the [p]roject,” and “MIC was slow to import suitable material for use by Plaintiff as fill, as required by the subcontract.” (Id. at 6 ¶ 35.) According to the parties, the subcontract does not include any obligation or requirement for Plaintiff to furnish or supply any fill material. (ECF Nos. 11 at 7 ¶ 40; 18 at 5 ¶ 40 (citing ECF No. 1-3 at 1-55).) Defendants generally deny Plaintiff’s allegations and contend that “the parties did later discuss [Plaintiff] paying for imported fill as means to allow [Plaintiff] to increase its inadequate production rates for its work” by way of a “gentleman’s agreement.” (ECF No. 83-6 at 15-18.)

On June 1, 2018, Plaintiff filed an Amended Complaint asserting five claims: Count I: Breach of Contract against MIC (ECF No. 11 at 11 ¶¶ 77-83); Count II: Quantum Meruit / Unjust Enrichment against MIC2 (ECF No. 11 at 12 ¶¶ 84-90); Count III: Violation of South Carolina’s Prompt Pay Act, S.C. Code Ann. § 29-6-30 (2019), against MIC (ECF No. 11 at 13 ¶¶ 91-95); Count IV: Recovery of Attorney’s Fees and Interest for Improvement of Real Estate against MIC and WSC pursuant to S.C. Code Ann. § 27-1-15 (2019) (ECF No. 11 at 14 ¶¶ 96-105); and Count V: Breach of Payment Bond against MIC and WSC. (ECF No. 11 at 15 ¶¶ 106-112). Defendants filed an Answer and Counterclaim against Plaintiff on June 15, 2018, asserting one count of breach of contract. (ECF No. 18 at 17 ¶¶ 15-18.) On October 15, 2019, Plaintiff filed a Motion for Partial

Summary Judgment. (ECF No. 84.) Defendants filed separate Motions for Partial Summary Judgment the same day. (ECF Nos. 84, 85.) The parties filed Responses on October 29, 2019 (ECF Nos. 92, 94, 95), and Replies on November 5, 2019 (ECF Nos. 108, 109, 110). III. LEGAL STANDARD Summary judgment should be granted “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P.

2 Plaintiff has dismissed Count II: Quantum Meruit / Unjust Enrichment, stating: “[MIC] moves for summary judgment on [Plaintiff’s] quantum meruit claim [because] [Plaintiff’s] Complaint claimed, and [MIC’s] Answer admitted, that the subcontract is a valid contract. [Plaintiff] agrees that because the validity of the subcontract is not in dispute, the quantum meruit claim may be dismissed at this point.” (ECF No. 92 at 23.) 56(a). A fact is “material” if proof of its existence or non-existence would affect the disposition of the case under the applicable law. See Anderson v. Liberty Lobby Inc., 477 U.S. 242, 248–49 (1986). A genuine question of material fact exists where, after reviewing the record, the court finds that a reasonable jury could return a verdict for the nonmoving party. See Newport News Holdings Corp. v. Virtual City Vision, 650 F.3d 423, 434 (4th Cir. 2011). In ruling on a motion for summary

judgment, a court must view the evidence in the light most favorable to the nonmoving party. Perini Corp. v. Perini Constr., Inc., 915 F.2d 121, 123-24 (4th Cir. 1990). The nonmoving party may not oppose a motion for summary judgment with mere allegations or denial of the movant’s pleading, but instead must “set forth specific facts” demonstrating a genuine issue for trial. See Fed. R. Civ. P. 56(e); see also Celotex Corp. v. Catrett, 477 U.S. 317, 324, (1986); Anderson, 477 U.S. at 252; Shealy v. Winston, 929 F.2d 1009, 1012 (4th Cir. 1991).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Owen Equipment & Erection Co. v. Kroger
437 U.S. 365 (Supreme Court, 1978)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Perini Corporation v. Perini Construction, Inc.
915 F.2d 121 (Fourth Circuit, 1990)
South Carolina National Bank v. Silks
367 S.E.2d 421 (Court of Appeals of South Carolina, 1988)
Carolina Amusement Co. v. Connecticut National Life Insurance
437 S.E.2d 122 (Court of Appeals of South Carolina, 1993)
Schulmeyer v. State Farm Fire & Casualty Co.
579 S.E.2d 132 (Supreme Court of South Carolina, 2003)
Ellis v. Taylor
449 S.E.2d 487 (Supreme Court of South Carolina, 1994)
McPeters v. Yeargin Const. Co., Inc.
350 S.E.2d 208 (Court of Appeals of South Carolina, 1986)
McGill v. Moore
672 S.E.2d 571 (Supreme Court of South Carolina, 2009)
Bishop v. Benson
374 S.E.2d 517 (Court of Appeals of South Carolina, 1988)
Spur at Williams Brice Owners Ass'n v. Lalla
781 S.E.2d 115 (Court of Appeals of South Carolina, 2015)
APAC-Carolina, Inc. v. Towns of Allendale & Fair Fax
868 F. Supp. 815 (D. South Carolina, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Phillips and Jordan Inc v. McCarthy Improvement Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phillips-and-jordan-inc-v-mccarthy-improvement-inc-scd-2019.