Philip Myers v. Wisconsin Department of Natural Resources

2019 WI 5, 922 N.W.2d 47, 385 Wis. 2d 176
CourtWisconsin Supreme Court
DecidedJanuary 18, 2019
Docket2016AP001517
StatusPublished
Cited by13 cases

This text of 2019 WI 5 (Philip Myers v. Wisconsin Department of Natural Resources) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Philip Myers v. Wisconsin Department of Natural Resources, 2019 WI 5, 922 N.W.2d 47, 385 Wis. 2d 176 (Wis. 2019).

Opinions

REBECCA FRANK DALLET, J.

*49*179¶ 1 Philip and Terrie Myers seek review of an unpublished per curiam decision of the court of appeals1 affirming in part and reversing in part the circuit court.2 The Myers seek review of the Wisconsin Department of Natural Resources' (DNR) unilateral amendment to their pier permit.

¶ 2 In 2001, the Myers were granted a permit by the DNR and built a pier at their waterfront property on Lake Superior. In 2012 and 2013, the DNR received *180complaints from a neighboring property owner about the Myers' pier. The DNR conducted an investigation and requested that the Myers substantially modify their pier. The Myers declined to make the DNR's proposed changes. The DNR then issued a "Notice of Pending Amendment," held a public informational hearing, and ultimately issued a formal permit amendment requiring the Myers to significantly change their pier in one of two ways.

¶ 3 The Myers declined to comply with the DNR's permit amendment and instead filed a petition for Wis. Stat. ch. 227 (2015-16)3 judicial review in the Ashland County Circuit Court. The circuit court denied the Myers' petition, finding that the DNR had the authority to issue an amendment to the Myers' pier permit. The circuit court then remanded the case to the DNR, finding that more fact-finding was needed as to the applicability of several statutory exemptions which could bar the DNR's action. Both parties appealed the circuit court's decision.

¶ 4 The court of appeals affirmed the circuit court's conclusion that the DNR had the authority to issue the Myers' permit amendment. The court of appeals reversed the circuit court as to the statutory exemptions, concluding as a matter of law that the statutory exemptions did not apply.

¶ 5 On petition to this court, the Myers seek review of three issues: (1) whether the DNR had the authority to amend their permit; (2) whether two exemptions in Wis. Stat. § 30.12(1k) barred the DNR's actions; and (3) whether the court of appeals could rely on "implicit findings" made by the DNR at a public *181informational hearing to conclude that the statutory exemptions in § 30.12(1k) did not apply to the Myers' pier.

¶ 6 We conclude that the DNR did not have the authority to unilaterally amend the Myers' permit. We therefore reverse the decision of the court of appeals. Because the DNR did not have the authority to amend the Myers' permit, we need not reach the issues related to the application of the statutory exemptions set forth in Wis. Stat. § 30.12(1k).

I. FACTUAL BACKGROUND AND PROCEDURAL POSTURE

¶ 7 The Myers own waterfront property on Madeline Island on Lake Superior. In December 1999, the Myers filed an application, pursuant to Wis. Stat. § 30.12, to construct a rock-filled pier next to the remnants of a dock that had been built on their property in the 1930s. The DNR received several objections to the Myers' application. The objectors were concerned that the proposed pier would result in beach erosion and other shoreline changes *50related to "littoral drift," the process of moving sediment along the shore.

¶ 8 In June 2001, the DNR held a contested hearing on the Myers' permit application. On July 23, 2001, an administrative law judge (ALJ) granted the Myers "a permit under Wis. Stat. § 30.12 for the construction of a structure." The permit granted the Myers permission to construct a pier consisting of "rock-filled cribs 10 feet in width extending 70 feet waterward from an existing 16-foot crib." The pier design also included a 14-foot L-extension with a 12-foot "flow-through opening" that would allow water *182and sediment to flow underneath and through the structure. The ALJ concluded that it was "unlikely that there [would] be detrimental impacts relating to shoreline alterations." However, the ALJ found that it was not always possible to predict the impact of a particular structure so he included the following language in the Myers' permit: "[t]he authority herein granted can be amended or rescinded if the structure becomes a material obstruction to navigation or becomes detrimental to the public interest" ("Condition 1"). The ALJ explained that Condition 1 would be "protective of unexpected impacts on neighboring properties relating to sand accumulation or beach starvation."

¶ 9 The Myers completed construction of their pier in October 2001 in accordance with the specifications set forth in the permit. In 2012 and 2013, the DNR received complaints from a neighboring riparian property owner who alleged that there was shoreline erosion and a loss of riparian property4 due to the Myers' pier.

¶ 10 As a result of these complaints, the DNR conducted an investigation and consulted with a coastal engineer, Gene Clark. Clark visited the Myers' property and wrote a report, detailing his opinion as to the effects of the Myers' pier. Clark ultimately concluded that because of "complexity of the mix of older and newer structures," as well as the fact that some littoral material "existed with just the older structures in place several decades ago," it was "extremely difficult to estimate how much if any additional littoral *183material trapping is occurring due only to the [Myers'] newer pier structures." The DNR sent the Myers a letter in July 2013, informing them that their pier was not in compliance with the 2001 permit. The DNR informed the Myers that the flow-through opening was not functioning as intended. Further, the DNR required the Myers to remove the two 24-foot cribs and replace the "bridge" between the crib and the L with a different system that allowed for the free movement of water and sediment. The Myers declined to institute the DNR's proposed changes.5

¶ 11 In November 2013, the DNR issued a Class I "Notice of Pending Amendment" indicating that it proposed to amend the Myers' 2001 permit to require expansion of the flow-through opening from 12 to 60 feet. The notice requested public comment on the proposed amendment. On January 7, 2014, the DNR held a public informational hearing on the amendment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Heather Gudex v. Franklin Collection Service, Inc.
Court of Appeals of Wisconsin, 2024
Scot Van Oudenhoven v. Wisconsin Department of Justice
2024 WI App 38 (Court of Appeals of Wisconsin, 2024)
Clean Wisconsin, Inc. v. DNR
2021 WI 72 (Wisconsin Supreme Court, 2021)
Anthony Greene v. Mark Mone
Court of Appeals of Wisconsin, 2021
Wisconsin Department of Revenue v. Deere and Company
Court of Appeals of Wisconsin, 2021
Demonta Antonio Hall v. Wisconsin Department of Justice
2020 WI App 12 (Court of Appeals of Wisconsin, 2020)
State v. Scott L. Nutting
Court of Appeals of Wisconsin, 2019
Moran v. Wis. Dep't of Justice
2019 WI App 38 (Court of Appeals of Wisconsin, 2019)
Philip Myers v. Wisconsin Department of Natural Resources
2019 WI 5 (Wisconsin Supreme Court, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2019 WI 5, 922 N.W.2d 47, 385 Wis. 2d 176, Counsel Stack Legal Research, https://law.counselstack.com/opinion/philip-myers-v-wisconsin-department-of-natural-resources-wis-2019.