Philadelphia Newspapers, Inc. v. Nuclear Regulatory Commission

727 F.2d 1195, 82 A.L.R. Fed. 449, 234 U.S. App. D.C. 96, 1984 U.S. App. LEXIS 25589
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 10, 1984
Docket83-1698
StatusPublished
Cited by12 cases

This text of 727 F.2d 1195 (Philadelphia Newspapers, Inc. v. Nuclear Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Philadelphia Newspapers, Inc. v. Nuclear Regulatory Commission, 727 F.2d 1195, 82 A.L.R. Fed. 449, 234 U.S. App. D.C. 96, 1984 U.S. App. LEXIS 25589 (D.C. Cir. 1984).

Opinion

Opinion for the court filed by Circuit Judge J. SKELLY WRIGHT.

J. SKELLY WRIGHT, Circuit Judge:

New events in recent years have so stirred the public to alarm as the nuclear accident on March 28, 1979 at Three Mile Island Unit 2 (TMI-2). Widespread anxiety persists to this day, particularly among those who live in the shadows of the twin reactors at the site. These residents of Pennsylvania, and the newspapers that serve them, have followed with a keen eye the Nuclear Regulatory Commission’s investigation into safety at Three Mile Island. Recently public attention has focused on the Commission’s deliberations over whether Unit 1 (TMI-1), which was ordered shut down in the aftermath of the accident at TMI-2, should be permitted to restart.

In this case we evaluate the propriety of the Commission’s decision to exclude the public from a meeting involving discussion of whether to restart TMI-1. The Commission had scheduled a meeting for May 10, 1983, to discuss “Steps to Decision in TMI-1 Restart.” See Sunshine Federal Register Notice, NRC, Week of May 9, 1983, 48 Fed. Reg. 20845 (1983), Joint Appendix (JA) 7. Normally such a meeting would be open to the public under the Government in the *1197 Sunshine Act, 5 U.S.C. § 552b (1982). 1 The Commission sought to close the meeting pursuant to an exemption that permits exclusion of the public from portions of meetings that “specifically concern * * * the initiation, conduct, or disposition of a particular case of formal agency adjudication pursuant to the procedures in section 554 of this title [the Administrative Procedure Act] or otherwise involving a determination on the record after opportunity for a hearing.” 5 U.S.C. § 552b(c)(10). Appellant, publisher of the Philadelphia Inquirer, challenged NRC’s attempt to close the meeting. The District Court initially granted a temporary restraining order against closing the meeting. The Commission then cancelled the meeting and it has never been held. On the merits of the case the District Court, in Philadelphia Newspapers v. NRC, D.D.C. Civil Action No. 83-1330 (June 3, 1983), JA 220, held that the Commission could properly close the meeting.

We reverse and remand to the District Court with instructions to remand to the Commission for further proceedings. The Commission’s decision to close the “Steps to Decision in TMI-1 Restart” meeting can be squared with neither the specific commands of the Sunshine Act nor the principle of broad public accountability that undergirds the Act. Most topics that the Commission plans to discuss at this meeting do not “specifically concern a particular case of formal agency adjudication,” and thus fall outside the intended scope of the exemption the Commission invoked. All portions of any meeting involving discussions of such nonexempt topics must be open to the public. On remand the Commission must carefully evaluate the agenda for the proposed meeting and may close only those portions of the meeting that will specifically concern formal adjudication connected with TMI-1 restart.

I. Background

When disaster struck at the TMI-2 reactor in March 1979, TMI-1, its twin in design and construction, was at the time shut down for routine maintenance. TMI-1 has remained in cold shutdown while the Commission has evaluated whether restarting the reactor will jeopardize public safety. The Commission’s evaluation of what actions to take with respect to TMI-1 comprises several lines of inquiry that the Commission has been careful to conduct separately. In the immediate wake of the TMI-2 incident the Commission initiated an on-the-record hearing procedure to recommend specific steps for improving safety at TMI-1 based on information learned as a result of the accident at TMI-2 (the On-the-Record Proceeding). Somewhat later the Commission established three informal deci-sional processes. In the first the Commission will determine whether the operators of Three Mile Island have resolved safety problems at TMI-1 unconnected with the design and construction defects discovered as a result of the accident at TMI-2. In the second the Commission will decide whether TMI-1 should be restarted on an interim basis pending final disposition of all issues. In the third the Commission will make a final decision as to whether TMI has met the safety recommendations of the On-the-Record Proceeding.

A. The On-the-Record Proceeding

As a first response to the disaster NRC conducted an investigation of both reactors, and decided that many of the deficiencies *1198 that caused the accident at TMI-2 also marred TMI-1. The Commission therefore prohibited restart of TMI-1 until short-term steps to cure these deficiencies had been completed and long-term steps to ensure safety had been substantially begun. See In re Metropolitan Edison Co. (Order and Notice of Hearing of August 9, 1979), 10 N.R.C. 141 (1979), JA 189.

This August 9th order established a hearing procedure for determining needed short-term steps and long-term goals, and for monitoring TMI’s efforts to meet these requirements. The order created an Atomic Safety and Licensing Board (Licensing Board) to conduct the hearings in accordance with NRC’s on-the-record procedures set out in subpart G of 10 C.F.R. Part 2 (1983). The Licensing Board was to make short-term and long-term safety recommendations, and could recommend restart if it found that the needed short-term steps had been completed and sufficient progress had been made toward long-term goals. Appeal from the Licensing Board’s decision on these matters was originally to go directly to the Commission, but in 1981 the Commission amended this process to provide for a level of intermediate review by an Appeals Board. These hearings, and concomitant review, will be referred to as the On-the-Record Proceeding.

B. The Informal Decisional Processes

1. The non-nexus issues. During the course of the proceedings before the Board several additional issues arose regarding the safety of TMI-1. These issues included concerns about repair of corroded steam generator tubes and about the seismic qualifications of the emergency feedwater cooling system in TMI-1. Though the Appeals Board sought to have these additional issues incorporated into the On-the-Record Proceedings before the Safety and Licensing Board, the Commission refused. The Commission believed that because these safety concerns were unrelated to those arising out of the TMI-2 accident they were beyond the scope of that proceeding. In re Metropolitan Edison Co. (Order of July 16, 1982) , 16 N.R.C. 1 (1982), JA 32. Thus these issues, which the Commission has labeled “non-nexus” issues, are being handled outside the On-the-Record Proceeding, even though the issues have a substantial bearing on the decision whether to restart TMI-1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nat Resrc Def Cncl v. NRC
216 F.3d 1180 (D.C. Circuit, 2000)
Wilkinson v. Legal Services Corp.
865 F. Supp. 891 (District of Columbia, 1994)
Deukmejian v. Nuclear Regulatory Commission
751 F.2d 1287 (D.C. Circuit, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
727 F.2d 1195, 82 A.L.R. Fed. 449, 234 U.S. App. D.C. 96, 1984 U.S. App. LEXIS 25589, Counsel Stack Legal Research, https://law.counselstack.com/opinion/philadelphia-newspapers-inc-v-nuclear-regulatory-commission-cadc-1984.