Petro Paint Manufacturing Co. v. Taylor

265 P. 155, 147 Wash. 158, 1928 Wash. LEXIS 519
CourtWashington Supreme Court
DecidedMarch 20, 1928
DocketNo. 20854. Department Two.
StatusPublished
Cited by14 cases

This text of 265 P. 155 (Petro Paint Manufacturing Co. v. Taylor) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petro Paint Manufacturing Co. v. Taylor, 265 P. 155, 147 Wash. 158, 1928 Wash. LEXIS 519 (Wash. 1928).

Opinion

Holcomb, J.

This action was brought by respondent, Petro Paint Manufacturing Company, as plain *159 tiff, to foreclose liens for material alleged to have been furnished respondent Taylor, who was then the owner of the premises, in the construction of five certain dwelling houses situated in King county. Appellant cross-complained to foreclose liens upon the same properties. One of the properties is not involved in this appeal. The other properties, properly described in the pleadings and findings, are referred to on appeal as house No. 1, house No. 2, house No. 3 and house No. 4.

Taylor was not only the owner of the premises in question at the time construction was begun, but was also in the general building business in Seattle. Construction was begun on at least one of the houses in February, 1926, it having been shown that appellant, Pioneer Sand & G-ravel Company, delivered cement to that property on February 26. On April 9, 1926, it commenced to deliver cement on lot No. 3; on April 17 it commenced to deliver cement on lot No. 2; on April 24 it commenced to deliver cement on lot No. 4. On June 1, 1926, Taylor, the then owner, transferred the lots designated as 2, 3 and 4 to respondent Johnson. At that time, the houses were not quite completed, but Taylor agreed with Johnson that he would complete them. There remained only some patching up to be done in the houses, the garage floors, driveways and sidewalks to be constructed. Taylor had become considerably delinquent in his account with appellant, owing it at that time almost the entire amount found to be due it by the court, or nearly $784.07. Appellant had made several attempts to collect from Taylor, without success. On July 4, appellant caused the premises to be inspected by its agent to ascertain when the jobs would be completed, and sent word to Taylor to call at its office. Taylor called on appellant on July 6, stated that he was not able to pay the account, and *160 that he needed more material. He said that he could not get money until the houses were completed and asked for more time on his account. He then ordered two sacks of cement for each house, which were to be delivered to the premises, and for which, when delivered, he receipted himself. The cement was in fact delivered and thrown in a shed, at his request and for his convenience, and was not in fact delivered to or used in any of the properties. Taylor did nothing more to complete the work on the several properties, and the houses were finished by another for the owner.

Appellant is engaged in the business of selling sand, gravel and cement to builders. It is claimed that in February, 1926, before construction was begun on the five houses, an agreement was entered into between Taylor and appellant, whereby Taylor agreed to purchase the sand, gravel and cement needed by him in the construction of the five houses at prices then prevailing. Although Taylor may have made such an agreement, the record shows that he did not purchase from appellant all the sand, gravel and cement needed by him in the construction of the houses, but purchased portions thereof from two other concerns in Seattle. The others also attempted to extend time for filing liens by the later delivery of two sacks of cement to each house, and to foreclose liens thereon, which were denied by the court upon the same grounds.

It is claimed by appellant that, by reason of the contract above mentioned, there was one continuing entire contract between the parties which justified the filing of appellant’s liens against the several premises within ninety days after July 6, 1926, or on September 15,1926, when the liens were filed. The evidence, however, also discloses that all the work that was to be done in any of the five houses, which was very indefinite under the testimony of Taylor, was some insignifi *161 cant patching up of basement floors to make them more level and to cover over some exposed rocks in the walls in some places. It is also shown that the walks, sidewalks and drives upon the grounds of each of the houses could not be constructed until a much later time on account of the condition of the street and the grounds as to grading. The two sacks of cement, ostensibly furnished by appellant for each house, were very insignificant in amount and in value. The amount would not be sufficient to construct any appreciable portion of the walks, sidewalks and drives which were at that time un-constructed. Nor did the contract between Taylor and appellant apparently cover sand, gravel and cement for walks, sidewalks and drives, but, as stated, referred only to the construction of the houses. In each of the lien claims filed by appellant against the premises involved, it was recited that the cement furnished was to be used in the dwelling house, and no mention was made of materials to be used for sidewalks and driveways. From the record it is to be noted that the last delivery of material by appellant to house No. 1 was one hundred and thirty days prior to the delivery of July 6; to house No. 2, eighty days prior to that delivery; to house No. 3, eighty-eight days prior to that delivery; and to house No. 4, seventy-three days.

After trial, the court gave appellant judgment against Taylor personally for the value of the material, but refused a decree of foreclosure on the ground that the deliveries of July 6 were not made in good faith, and that the lien notice had not been filed within ninety days after the last delivery. A motion for a new trial was made and denied. This appeal is from the decree of the court denying foreclosure.

Appellant urges as grounds for reversal of the decree of the trial court that the court erred in admitting *162 testimony showing or tending to show lack of good faith on the part of appellant; and erred in finding that the delivery of material on July 6 was not in good faith, but for the purpose of extending the time in which liens might be filed. The other errors assigned are comprehended within the two above mentioned.

It is urged by appellant:

(1) That neither bad faith nor fraud was shown by the testimony.

(2) That bad faith is not a defense where material is ordered by an owner or Ms agent.

(3) That the material v/as delivered in accordance with the contract.

(4) That the time for filing had not expired when the liens were filed.

(5) That a change of ownership during the progress of the work does not affect one who has a contract for furnishing material.

(6) That bad faith, as used in the decisions, is synonymous with fraud, and that fraud cannot be proved unless it is pleaded.

(7) That the failure to name the wife of the record owner of community property in the lien notice is not material.

The trial court made' findings, and among other things found that appellant delivered all the cement purported to be delivered at a shed on the lot here designated as No. 4. It also found that the delivery of July 6 was not made in good faith, only for use in the dwelling houses, nor pursuant to the original contract between the parties, but was made by appellant solely for the purpose of extending the time for filing its lien claims against the property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Intermountain Elec., Inc. v. GAT BROS. CONST., INC.
62 P.3d 548 (Court of Appeals of Washington, 2003)
Intermountain Electric, Inc. v. G-A-T Bros. Construction, Inc.
115 Wash. App. 384 (Court of Appeals of Washington, 2003)
Tackett v. Milburn
218 P.2d 298 (Washington Supreme Court, 1950)
Bleiler v. Wolff
161 P.2d 145 (Washington Supreme Court, 1945)
Swensson v. Carlton
135 P.2d 450 (Washington Supreme Court, 1943)
Daloia v. Boyd
133 P.2d 950 (Washington Supreme Court, 1943)
Columbia Lumber Co. v. Bush
126 P.2d 584 (Washington Supreme Court, 1942)
Warner v. Keebler
94 P.2d 175 (Washington Supreme Court, 1939)
Flint v. Bronson
86 P.2d 218 (Washington Supreme Court, 1939)
Automatic Canteen Co. v. Automatic Canteen Co.
45 P.2d 41 (Washington Supreme Court, 1935)
Grimes v. Fraser
35 P.2d 88 (Washington Supreme Court, 1934)
Brewster v. State
16 P.2d 813 (Washington Supreme Court, 1932)
Herz v. Ransom
12 P.2d 750 (Washington Supreme Court, 1932)
Warming v. Hargis
294 P. 248 (Washington Supreme Court, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
265 P. 155, 147 Wash. 158, 1928 Wash. LEXIS 519, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petro-paint-manufacturing-co-v-taylor-wash-1928.