Petition of SC Loveland Co.

170 F. Supp. 786, 1959 U.S. Dist. LEXIS 3783
CourtDistrict Court, E.D. Pennsylvania
DecidedFebruary 17, 1959
Docket117 of 1955
StatusPublished
Cited by10 cases

This text of 170 F. Supp. 786 (Petition of SC Loveland Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petition of SC Loveland Co., 170 F. Supp. 786, 1959 U.S. Dist. LEXIS 3783 (E.D. Pa. 1959).

Opinion

VAN DUSEN, District Judge.

I. History of the Case

The Petition of S. C. Loveland Co., Inc., in exoneration from, or limitation of, liability as late owner and operator of the barge Fell Loveland, was filed in this court on April 15, 1955. Subsequently, answers and claims were filed by three parties, who withdrew their claims prior to November 1958, 1 at which time the petitioner asked the trial judge to proceed with decision in the case as to the remaining claimants because of inability to reach a settlement with them. In November and December 1958, Requests for Findings of Fact and Conclusions of Law were filed on behalf of the petitioner and the following claimants, who are the only three parties continuing as parties to this proceeding:

A. Florence Pipe Foundry and Machine Co. (hereinafter called “Florence”), the owner of the pig iron loaded aboard the barge Fell Loveland at the time she sank (see Answer of Florence filed 6/15/55 as Document No. 5 in Clerk’s file and Claim of Florence filed the same day as Document No. 6 in Clerk’s file).

B. Quaker City Navigation Co. (hereinafter called “Quaker”), claiming that it was unable to discharge its car *788 goes of coke at the pier due to the obstruction of the sunken barge (see Answer of Quaker filed 6/17/55 as Document No. 12 in Clerk’s file and Claim of Quaker filed the same day as Document No. 11 in Clerk’s file). 2

The trial of the case was held in February 1958. At the beginning of the trial, it was agreed that the issue of the amount of damages would be “reserved and passed on to a Commissioner” (N. T. 5 & 6). After the testimony was transcribed, counsel for Chester and counsel for petitioner asked the trial judge for more time to file their Requests for Findings of Fact and Conclusions of Law since “some headway was being made toward settlement of the issues.” 3 It proved impossible for petitioner to reach a settlement with Florence and Quaker and the above-mentioned Requests, together with supporting briefs, were filed in the last two months of 1958. Oral argument was heard on December 29, 1958.

The restraining order filed April 14, 1955, as amended May 14, 1956, will be further amended in accordance with the terms of Admiralty Rule 51 to make clear that it does not bar the institution of S. C. Loveland Co., Inc., etc., v. Florence Pipe Foundry & Machine Co., No. 59 of 1958 in Admiralty, as suggested at pages 8 and 9 of the brief filed by petitioner in that action on December 24, 1958.

II. ^Findings of Fact

1. All the requested Findings of Fact of petitioner, with the following four modifications, are adopted as Findings of Fact of the trial judge:

(a) There is added at the end of paragraph 3: “(This sentence is amplified and qualified by Finding of Fact 5 of the trial judge.)”

(b) Sub-paragraph 5(e) is reworded as follows: “All claims for loss and/or damage and/or expense against petitioner were waived by Florence ‘except for General Average, Sue and Labor and Collision Liability’ (see paragraph 10).” (See Exhibit L-3.)

(c) Paragraph 7 is modified by inserting at the beginning of the sentence “On the night of March 11, 1955” and by deleting the first word, “and,” in the second line.

(d) Paragraph 8 is modified by adding at its end the words “for carriage of 1000 tons of pig iron from Chester, Pa., to Florence, New Jersey.”

2. All the requested Findings of Fact of Florence Pipe Foundry and Machine Co. (hereinafter called “Florence”), except for paragraphs 5, 6, and 8, and with the following added at the end of paragraph 3, are adopted as Findings of Fact of the trial judge: “(This sentence is amplified and qualified by Finding of Fact 5 of the trial judge.)”

3. Subsequent to World War II, the barge Fell Loveland was converted 4 for use solely on the inland waterways, since it became uneconomical to operate barges of her size in the coastwise trade.

4. The Fell Loveland carried the following loads in excess of 1000 tons between Chester, Pa., and Florence, N. J., *789 prior to March 10, 1955, and .petitioner’s accountant had records showing that it was paid freight on the basis of these loads (Exhibits L-37 and L-32):

Weight In Date of Shipment Gross Tons (L-37) Date Bill Sent To Petitioner by Florence (L-32)
1012-1015 November 30, 1954 December 13, 1954
1016- 1020 December 29, 1954 January 7, 1955
1017- 1022 January 6, 1955 January 14, 1955
1022-1024 January 13, 1955 January 21, 1955
1079-1082 February 14, 1955 February 21, 1955
1066-1071 February 19, 1955 February 28, 1955
1061-1069 February 25, 1955 March 7, 1955

The president of petitioner did not know that the barge had carried in excess of 1000 tons on any of these loads prior to the sinking of the Fell Loveland (N.T. 41).

5. Barge Captain James’ duties included properly maintaining the barge (N.T. 34), checking the barge for water (N.T. 190), taking care that the barge was loaded in such a way that it would not be damaged or unnecessarily strained (N.T. 66, 189, and Answer to Interrogatory 18 in C.P. 3, Sept. Term 1955, No. 5003), but it was not his duty to determine the size of the load the barge was to carry (N.T. 192). Once, in February 1955, petitioner’s marine superintendent cautioned James about not putting too much weight in the barge (N.T. 195, 199, 267). 5

6. James had the opportunity to call the marine superintendent or president of petitioner for instructions concerning the removal of the alleged extra carload of pig iron on the barge on the evening of March 11, 1958.

7. It was not possible to use the pier at which the Fell Loveland had been moored from March 12, 1955, when it sank, until the remains of the sunken barge were removed in June 1955.

8. Petitioner only decided to abandon the barge at the pier when they learned that the cost of salvaging it would be in excess of $25,000 and Chester would not “split * * * the expense with us of raising the barge” (N.T. 27-28).

9. There is no evidence that petitioner believed, or knew that Quaker was doing business regularly at the above-mentioned pier or that it had any contract with Chester or any other person involving the use of this pier.

III. Discussion

This is a petition of a barge owner in exoneration from, or limitation of, liability.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aikens v. Baltimore and Ohio R. Co.
501 A.2d 277 (Supreme Court of Pennsylvania, 1985)
Getty Refining & Marketing Co. v. Mt Fadi B
766 F.2d 829 (Third Circuit, 1985)
Getty Refining And Marketing Company v. Mt Fadi B
766 F.2d 829 (Third Circuit, 1985)
Federal Commerce & Navigation Co. v. the M/V Marathonian
392 F. Supp. 908 (S.D. New York, 1975)
Reilly v. Pyle
49 Pa. D. & C.2d 570 (Bucks County Court of Common Pleas, 1970)
R. D. Wood Company v. Phoenix Steel Corporation
327 F.2d 921 (Third Circuit, 1964)
R. D. Wood Co. v. Phoenix Steel Corp.
211 F. Supp. 924 (E.D. Pennsylvania, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
170 F. Supp. 786, 1959 U.S. Dist. LEXIS 3783, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petition-of-sc-loveland-co-paed-1959.