Petition of Department of Public Service

596 A.2d 1303, 157 Vt. 120, 1991 Vt. LEXIS 163
CourtSupreme Court of Vermont
DecidedJune 28, 1991
Docket88-266
StatusPublished
Cited by8 cases

This text of 596 A.2d 1303 (Petition of Department of Public Service) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petition of Department of Public Service, 596 A.2d 1303, 157 Vt. 120, 1991 Vt. LEXIS 163 (Vt. 1991).

Opinions

Dooley, J.

Appellant Ryegate is a small power producer seeking to overturn a decision of the Public Service Board (PSB) denying it rates set forth in an executed letter of intent with the Vermont Power Exchange, Inc. (VPX). We affirm.

Ryegate is the successor-in-interest to Decker Energy International, Inc. On December 30,1985, Decker entered into a letter of intent to sell to VPX power Decker would produce at a facility to be built in Randolph. The company’s plan was tailored to benefit from the federal Public Utility Regulatory Policies Act of 1978 (PURPA), 16 U.S.C. §§ 2601-2645 (1988), enacted to combat oil shortages and to encourage alternative forms of energy production. See In re Vicon Recovery Systems, 153 Vt. 539, 543, 572 A.2d 1355, 1357 (1990) (discussing objectives of the Act). The states are charged with implementing PURPA, under rules promulgated by the Federal Energy Regulatory Commission (FERC). In Vermont, implementation of the statute has been assigned to the Public Service Board. See 30 V.S.A. § 209(a)(8); In re Vicon, 153 Vt. at 547, 572 A.2d at 1359. The PSB’s plan implementing PURPA created a single purchasing agent to contract on behalf of all Vermont utilities for the purchase of power from qualifying small power production facilities. Vt. Pub. Serv. Bd. Rule 4.100, §§ 4.103(A)(8), 4.104(A) (as revised Aug. 28,1985). Under authority of the Rule, PSB has designated VPX to function as the purchasing agent.

[122]*122Under Rule 4.100, the Department of Public Service determines rates utilities pay for power generated by qualifying facilities, subject to the approval of the PSB. The rates and rate order at issue in this case were approved by the Board on November 18, 1985, in Docket No. 4933, providing for qualifying facilities to sell up to 150 megawatts of power through long-term contracts of up to thirty years (as late as 2018). The rates were calculated on the basis of “avoided cost,” which means the “incremental cost to electric utilities of electric energy or capacity or both, which, but for the purchase from the qualifying facility, such utilities would generate themselves or purchase from another source.” Rule 4.100, § 4.103(A)(1); see 18 C.F.R. §§ 292.101(b)(6), 292.304(b)(2) (1990).

VPX established procedures detailing the general process set forth in Rule 4.100, and, on June 25, 1984, issued a Producer’s Guide for Power Sales Under Public Service Board Rule 1.100. The guide states in relevant part:

As an option, VPX will sign a Letter of Intent with producers who are awaiting the necessary Board approvals. This offer will set out deadlines for application to the Public Service Board, signing a Purchase Agreement with VPX, and project completion. The signed Letter will hold a producer’s place in the first 25 MW decrement of power committed to the agent so long as the producer meets the agreed to development schedule.
Producers needing PSB approval for a 248 Certificate and/or levelized rates have the option of applying for a Letter of Intent. The letter will state, for the sales option selected, a minimum price for the power generated by the project and a date for filing Board petitions for permits and rate approval, and a project completion schedule. The Letter of Intent will hold the producer’s place in the decrement. The Letter of Intent is conditioned upon final Board approval of the rate option selected and remains valid so long as the producer meets the agreed to development schedule. (Emphasis added.)

Ryegate’s predecessor signed a letter of intent with VPX on December 30, 1985. The letter of intent is an agreement to enter into a long-term power purchase and sale contract if certain [123]*123conditions are satisfied. It provides that the producer’s first 8.855 megawatts of power would be sold at the “appropriate 30 year rate approved by the Vermont Public Service Board in docket number 4933.” The rate for the balance of the power does not involve Docket No. 4933 and is not in issue. The agreement is conditioned on the producer applying to the PSB for a certificate of public good within forty-five days, commencing construction within six months of receiving the certificate, and completing construction -within twenty-four months thereafter. It is also conditioned on the PSB determining an applicable rate and the producer entering into the purchase and sale agreement within sixty days thereafter.

The letter of intent was restated and signed by Ryegate and VPX in May of 1987. The site of the project was changed from Randolph to Ryegate. None of the relevant terms were changed.

PURPA rates were approved in Docket No. 4933 on November 11, 1985. The order contains extensive rate schedules, depending upon the length of the purchase and sale contract (up to 30 years) and the decrement (that is, block of 25 megawatts) within which the project falls: The applicable rate also depends upon the start date of the project. The schedules provide for start dates from the summer of 1985 through the winter of 1987-1988. There are no rate schedules applicable to projects that started to deliver power after April 30, 1988.

On September 24, 1986, the Department petitioned the PSB for a declaratory ruling that rate options being offered to producers and certain other VPX practices were illegal. The catalyst for the Department’s action was that, due to an unexpected fall in world oil prices, the rates approved in Docket No. 4933 represented significant overestimates of the avoided cost of energy. Part of the Department’s position was that the VPX letters of intent did not foreclose the PSB from denying Docket No. 4933 rates to projects like Ryegate’s if they did not start delivering power by April 30, 1988.

On August 26,1987, the PSB issued an order concluding that the VPX letters of intent were not binding obligations given the involuntary nature of the letters vis-a-vis the utilities and that “[cjontract analysis, therefore, is simply inapposite.” It also concluded that “because the letters are contingent, they are not [124]*124‘binding obligations’ within the meaning of the FERC regulations.” It ruled, however, that qualifying facilities that came on line by April 30, 1988 — the date the relevant Docket No. 4933 rate schedule was to begin — should receive the rates. Although the rate order in Docket No. 4933 had not explicitly declared that it was limited to qualifying facilities coming on line by April 30,1988, the PSB concluded that such a deadline was implied in the temporal framework of the schedule. Finally, it concluded that no claims of equitable entitlement under the letters of intent would follow unless the “sole substantial purpose” of the letters had been to secure a particular rate. Because there were other significant purposes for the letters of intent, it concluded that they did not create equitable rights.

Ryegate advances three main theories under which it claims the right to Docket No. 4933 rates irrespective of when it starts delivering power: (1) it is entitled to those rates under PURPA; (2) it has an enforceable contract with VPX for those rates; and (3) it has a vested right to those rates. We take these arguments in turn.

I. PURPA RIGHTS

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Littlejohn v. Timberquest Park at Magic, LLC
116 F. Supp. 3d 422 (D. Vermont, 2015)
Lowery v. Air Support International, Inc.
982 S.W.2d 326 (Missouri Court of Appeals, 1998)
In Re Vermont Electric Power Producers, Inc.
683 A.2d 716 (Supreme Court of Vermont, 1996)
In Re East Georgia Cogeneration Ltd. Partnership
614 A.2d 799 (Supreme Court of Vermont, 1992)
Petition of Department of Public Service
596 A.2d 1303 (Supreme Court of Vermont, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
596 A.2d 1303, 157 Vt. 120, 1991 Vt. LEXIS 163, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petition-of-department-of-public-service-vt-1991.