Peter Minshall v. DC Dept. of Consumer & Regulatory Affairs

184 A.3d 352
CourtDistrict of Columbia Court of Appeals
DecidedMay 17, 2018
Docket16-AA-587
StatusPublished
Cited by2 cases

This text of 184 A.3d 352 (Peter Minshall v. DC Dept. of Consumer & Regulatory Affairs) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peter Minshall v. DC Dept. of Consumer & Regulatory Affairs, 184 A.3d 352 (D.C. 2018).

Opinion

Fisher, Associate Judge:

This case concerns a disagreement between neighbors over the construction and height of a wall that separates their properties in Georgetown. Petitioners ask us to reverse the Administrative Law Judge's ("ALJ") Order which held that their challenges to construction of the wall were untimely. They argue that the time to appeal did not begin until the Department of Consumer and Regulatory Affairs ("DCRA") issued a third building permit in November of 2014. We affirm the ALJ's decision to dismiss for untimeliness because petitioners should have appealed, at the latest, when a stop work order was lifted in March of 2014. We also affirm the ALJ's conclusion that issuance of the 2014 building permit did not renew the time for challenging the already-completed construction of the wall.

I. Background and Procedural History

Petitioners Peter and Diana Minshall own a home in the Georgetown Historic District next door to property owned by intervenor Sean Glass. In 2011 intervenor applied for a permit to renovate his home and to build a two-story rear addition with a penthouse and a basement, an in-ground pool, and exterior stone walls. DCRA approved the application and issued the permit on March 23, 2012.

Intervenor filed a second application that further described his proposed in-ground swimming pool and set out a "pool/fencing site plan." DCRA issued the second permit on May 25, 2012. Despite receiving a notification form from intervenor that indicated he intended to build "a pool [and] fence near [the] property line," petitioners did not challenge the first or second building permit. Intervenor completed *354 construction of the fence/wall in 2013.

Although petitioners communicated with intervenor by email on multiple occasions between 2012 and 2014 concerning the construction and height of the fence/wall, they did not initiate any legal proceedings during 2013. On February 18, 2014, petitioners complained to the Historic Preservation Office of the District of Columbia Office of Planning ("HPO"). HPO sent an investigator to look at the property and on February 20, 2014, he issued a stop work order ("SWO") for alleged violations of the District of Columbia Construction Code. The violations included failing to obtain a "separate rear yard perimeter fence wall permit in a historic district" and building a "concrete/wood fence wall [that] exceeds the 7 ft. residential height limit with no record of an adjoining property owner agreement."

Intervenor appealed the SWO and a hearing was held before DCRA Hearing Officer Ferdinand Gamboa on March 12, 2014. Mr. Gamboa dismissed the SWO without prejudice and allowed intervenor to resume construction. Although petitioners did not attend the hearing, Mr. Gamboa let them know the outcome in an email sent on March 14, 2014. Petitioners and their attorney also met with Mr. Gamboa about a month after the hearing, but they did not appeal the officer's decision to lift the SWO.

Petitioners continued to discuss intervenor's projects with an HPO representative and on June 12, 2014, HPO solicited the recommendation of the Commission of Fine Arts ("CFA") "regarding the wall and fences as they have been constructed." At the request of CFA, intervenor also submitted a new permit application to DCRA that included detailed site plans, elevations, and drawings of the existing fence/wall. Although CFA recommended lowering the wooden fence and putting stucco on petitioners' side of the concrete wall, it reported on September 18, 2014, that it did not object to the issuance of the permit. DCRA issued the permit on November 26, 2014, describing the work to be performed as lowering the existing wooden fence and adding stucco and stone veneers to the existing concrete wall. Petitioners then appealed to OAH on December 29, 2014, requesting that OAH revoke the 2014 permit and order intervenor to remove or redesign the concrete wall. 1

Petitioners' administrative appeal was originally assigned to an ALJ who presided over two days of evidentiary hearings. The case was then reassigned to Judge Paul B. Handy; he issued an Order converting day three of the proceeding into a hearing on intervenor's argument that the appeal was untimely and should be dismissed. Judge Handy ultimately determined that petitioners' claims were untimely because they were filed more than 10 business days after petitioners knew or should have known of the basis for each claim. See 12-A DCMR § 112.2.1 (2014). He found that petitioners "knew or should have known of the basis for their claim in 2012" when DCRA issued the first two building permits and "certainly in February and March 2014, when [they] knew about the Stop Work Order proceeding." Nevertheless, petitioners "failed to participate in the scheduled hearing and failed to appeal the order dismissing the Stop Work Order."

*355 Although he held that petitioners timely appealed the issuance of the 2014 permit, 2 Judge Handy concluded that it was too late for them to challenge the "overall construction" of the wall. He considered the parties' exhibits and arguments on the motion to dismiss and found that the 2012 permits provided for the construction of the entire fence/wall but that the only two changes authorized by the 2014 permit were the "application of a stucco finish" and the "lowering of the wooden slats." Petitioners did not challenge either of the two changes addressed in the 2014 permit. Judge Handy granted intervenor's motion to dismiss, and this petition for review followed.

II. Standard of Review

This court will "leave an agency's decision undisturbed if it flows rationally from findings of fact that are supported by substantial evidence in the record." Zhang v. District of Columbia Dep't of Consumer & Regulatory Affairs , 834 A.2d 97 , 101 (D.C. 2003). "To be sufficient to support a finding, evidence must be more than a mere scintilla and must be such relevant evidence as a reasonable mind might accept as adequate to support a conclusion." Woodley Park Cmty. Ass'n v. District of Columbia Bd. of Zoning Adjustment , 490 A.2d 628 , 640 (D.C. 1985) (internal quotation marks and citation omitted). With respect to the agency's legal conclusions, "we conduct a de novo review." Zhang , 834 A.2d at 101 .

III. The Timeliness of Petitioners' Appeal

The central question is whether petitioners' challenges to the height and construction of intervenor's concrete wall were timely.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

4022 Georgia Avenue v. Department of Buildings
District of Columbia Court of Appeals, 2025
Williams v. District of Columbia
District of Columbia, 2020

Cite This Page — Counsel Stack

Bluebook (online)
184 A.3d 352, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peter-minshall-v-dc-dept-of-consumer-regulatory-affairs-dc-2018.