Peter D. Holdings v. Wold Oil Properties

Court of Appeals for the Tenth Circuit·Decided February 7, 2022·No. 20-8050·Unpublished

Opinion

FILED

United States Court of Appeals UNITED STATES COURT OF APPEALS Tenth Circuit

FOR THE TENTH CIRCUIT February 7, 2022

Christopher M. Wolpert

Clerk of Court

PETER D. HOLDINGS, LLC, assignee of Black Diamond Energy, Inc., and assignee of Black Diamond Energy of Delaware, Inc.,

Plaintiff - Appellant, No. 20-8050

v. (D.C. No. 1:17-CV-00212-KHR)

(D. Wyo.)

WOLD OIL PROPERTIES, LLC, a Wyoming limited liability corporation; CHIPCORE, LLC, a Wyoming limited liability corporation,

Defendants - Appellees.

ORDER AND JUDGMENT *

Before PHILLIPS, McHUGH, and MORITZ, Circuit Judges.

This is an assignee’s remorse case. At bottom, Peter D. Holdings, LLC (“Peter D.”) thought it financially advantageous to accept an assignment of Black Diamond Energy, Inc.’s contractual interests in certain coalbed methane-gas wells. The assignment was in exchange for Peter D.’s release of debts owed to Peter Dochinez

*

This order and judgment is not binding precedent, except under the doctrines of law of the case, res judicata, and collateral estoppel. It may be cited, however, for its persuasive value consistent with Fed. R. App. P. 32.1 and 10th Cir. R. 32.1.

Appellate Case: 20-8050 Document: 010110641796 Date Filed: 02/07/2022 Page: 2

(Peter D.’s sole member) by Black Diamond’s founder, Erik Koval. But the assignment failed to live up to Peter D.’s expectations.

As part of the deal, Dochinez and Koval had agreed to work together to recover monies owed to Black Diamond under its contract with Wold Oil Properties LLC. Specifically, Dochinez and Koval thought that Black Diamond was owed additional interest in certain wells. So, in December 2017, Peter D. sued Wold Oil and Chipcore, LLC 1 (collectively, “Wold”) in the District of Wyoming. The suit resulted in a four-day bench trial in November 2019.

After the trial, the court dismissed Peter D.’s claims because, among other reasons, it was not a real party in interest. As an alternative basis for dismissal, the court held that Black Diamond hadn’t earned the well interests that Peter D. believed it had. Peter D. now appeals.

Exercising jurisdiction under 28 U.S.C. § 1291, we affirm the district court’s judgment that Peter D.’s claims fail on the merits. We express no opinion on the district court’s alternative bases for dismissing Peter D.’s suit. 2 See United Automobile, Aerospace v. N.L.R.B., 462 F.2d 298, 300 (D.C. Cir. 1972) (“It is a uniform course of appellate review procedure to decline to review questions not necessary to a decision by an appellate court.”) (citation omitted); see also Fla.

1 Chipcore was assigned some of Wold Oil’s contractual interests.

2 For example, we see no need to address the district court’s holdings regarding real party in interest, judicial estoppel, and statute of limitations issues with respect to certain claims, focusing instead on the better-briefed dispositive arguments before us.

Wildlife Fed’n Inc. v. United States Army Corps of Eng’rs, 859 F.3d 1306, 1320 (11th Cir. 2017).

BACKGROUND

I. Black Diamond, Wold Oil, and Chipcore In the late 1990s, natural gas was in high demand. Oil-and-gas companies flocked to the Powder River Basin straddling Wyoming and Montana to lay claim to that region’s untapped potential. Among the arrivals were Erik Koval and his newly founded company, Black Diamond. Black Diamond soon partnered with Wold Oil, which was already the lessee on a sizeable area in the Basin.

In September 2003, Black Diamond and Wold Oil entered a Farmout Agreement, which set out the parties’ respective rights and obligations vis-à-vis what the agreement calls the “Contract Area”—about 5,400 acres in the Powder River Basin. Under the Farmout Agreement, Black Diamond could secure up to 50% of Wold Oil’s interest in the Contract Area. Black Diamond first purchased a 25% interest in the Contract Area, opting to earn the remainder under the terms negotiated in the Farmout Agreement. If Black Diamond met those terms, it could earn an additional 25% of certain interests that Wold Oil held in the Contract Area.

First, Black Diamond had to “drill and complete” two “Initial Wells” by December 31, 2003. The Farmout Agreement states that the term drill and complete “means to drill and complete a well . . . that is capable of producing coalbed methane gas and commence dewatering operations in anticipation of producing coalbed

Appellate Case: 20-8050 Document: 010110641796 Date Filed: 02/07/2022 Page: 4

methane gas.” R. Vol. 4 at 793. Second, if Black Diamond timely drilled and completed the Initial Wells, it then needed to drill and complete eight “Additional Wells” by May 1, 2004. Third, if Black Diamond timely drilled and completed the Initial and Additional Wells, it could earn the additional 25% interest by expending a contractually-designated amount known as the “Program Deposit”—essentially an investment commitment.

Though the Farmout Agreement set the Program Deposit at $2.5 million, it contained another provision that reduced the Program Deposit based on Black Diamond’s interest in the Contract Area. All of Black Diamond’s drilling costs were to be subtracted from the Program Deposit, but the agreement assumed that Black Diamond would incur less than $2.5 million in drilling costs. Thus, Black Diamond was only required to expend “the balance” of the $2.5 million—what it hadn’t expended on drilling—to “hook up” the wells. The Farmout Agreement clarifies that

[t]he term “hook up,” as used herein means, to install such equipment and other facilities as are reasonably necessary to produce coal bed methane gas from the Initial Wells and Additional Wells, including, but not limited to, equipping the wells, installing electrical infrastructure, gas metering, pod house, water handling, water discharge facilities, screw compressors, reciprocating compressors, water lines, gas gathering lines, and sales line entry/tap in cost.

R. Vol. 4 at 795. But Black Diamond neglected these obligations under the contract. That is, Black Diamond spudded 3 the two Initial Wells but didn’t dewater them,

3 The Farmout Agreement does not define the term “spud,” but the Wyoming Oil and Gas Conservation Commission defines it as “the commencement of operations for the first boring of a hole for the drilling of an oil, gas, or injection well . . . .” WOGCC Rules & Regs 055.0001.1 §2(aaa) (Definitions).

Appellate Case: 20-8050 Document: 010110641796 Date Filed: 02/07/2022 Page: 5

which means they couldn’t produce natural gas. Nor did Black Diamond ever hook up these wells. The same goes for the eight Additional Wells: Black Diamond timely spudded them, but neither dewatered them nor hooked them up.

These breaches were consequential for Wold Oil. As a result, the wells were functionally unusable until after Wold Oil took over managing them in 2009. Still, despite not being required to do so by the Farmout Agreement, Black Diamond kept on drilling. It drilled another four wells in 2005, leading to fourteen drilled wells, but none were dewatered or hooked up. 4 Given these failures, Wold Oil concluded that its relationship with Black Diamond needed a change. It terminated the Farmout Agreement in December 2007, citing Black Diamond’s failure to expend the balance of the $2.5 million Program Deposit to hook up the wells drilled, its failure to dewater the wells, and its failure to develop the infrastructure “to put the wells on production.” R. Vol. 4 at 880. For these reasons, Wold Oil advised Black Diamond that it had failed to earn the additional 25% interest in the Contract Area.

But Wold Oil’s breakup with Black Diamond didn’t stick. From July to September 2008, Black Diamond sent Wold Oil invoices for Wold’s proportionate

Free access — add to your briefcase to read the full text and ask questions with AI

Peter D. Holdings v. Wold Oil Properties, (10th Cir. 2022).

Peter D. Holdings v. Wold Oil Properties (Peter D. Holdings v. Wold Oil Properties) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ferguson v. Reed
822 P.2d 1287 (Wyoming Supreme Court, 1991)
Y-O Investments, Inc. v. Emken
2006 WY 112 (Wyoming Supreme Court, 2006)
Mathis v. Huff & Puff Trucking, Inc.
787 F.3d 1297 (Tenth Circuit, 2015)
Schlinger v. McGhee
2012 WY 7A (Wyoming Supreme Court, 2012)
Gould v. Ochsner
2015 WY 101 (Wyoming Supreme Court, 2015)
Larson v. Burton Constr., Inc.
421 P.3d 538 (Wyoming Supreme Court, 2018)
J. W. Denio Milling Co. v. Malin
165 P. 1113 (Wyoming Supreme Court, 1917)
Morrow v. Xanterra Parks & Resorts
925 F. Supp. 2d 1231 (D. Wyoming, 2013)