Peter A. Camilli & Sons, Inc. v. State

41 Misc. 2d 218, 245 N.Y.S.2d 521, 1963 N.Y. Misc. LEXIS 1782
CourtNew York Court of Claims
DecidedJuly 19, 1963
DocketClaim No. 37839
StatusPublished
Cited by10 cases

This text of 41 Misc. 2d 218 (Peter A. Camilli & Sons, Inc. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peter A. Camilli & Sons, Inc. v. State, 41 Misc. 2d 218, 245 N.Y.S.2d 521, 1963 N.Y. Misc. LEXIS 1782 (N.Y. Super. Ct. 1963).

Opinion

John P. Gualtieri, P. J.

This is a claim for breach Of contract and for damages resulting from a contract dated May 9, 1955, between the claimant and the New York State Thruway Authority for the construction at Sloatsburg, Eockland County, of a Super “A” gas station and restaurant and a utility building on the easterly side of the Thruw'ay; a type “ CM” gas station and restaurant on the westerly side of the Thruway; and a pedestrian bridge over the Thruway connecting the two sites.

The claimant’s contract called for the construction of the building and structures; Hoyle Construction Co., Inc., had the heating contract; Jeb Electrical Co., the electrical contract; Novak and Company had the contracts for the sewerage lines and for the installation of plumbing; and Union Building and Construction Co., Inc., contracted to do the site work, grading, paving and other work of a similar character.

Claimant seeks damages in the sum of $199,377.06 broken down as follows: (a) $50,882.24 for extra rock excavation ($6,784 of this amount was allowed by the Authority in its final estimate and is to be deducted from any award made for this item); (b) $14,403.84 for the cost and expense of hauling water to the contract site; (c) $5,166.34 for pumping and cleaning of excavation on the * AA ’ ’ site because of interference with the claimant’s operations by the site contractor, the Union Building Company; (d) $31,685.46 claimed to be due because it was obliged to extend its time of performance to 26 months instead of the 11-month period contemplated in the contract; (e) $6,942 damages claimed to be due by reason of the fact that the Authority interfered with the claimant’s work by allowing the site contractor on the job too early in the construe[220]*220tion schedule; (f) $10,460.80 interest on $79,720.38 which the Authority conceded to he due the claimant in its final estimate and which it is alleged was not tendered until March 16, 1960; (g) $6,900 claimed by reason of the Authority’s refusal to allow the claimant to correct its total bid resulting from what it claims to have been a mathematical error in addition.

Items (a), (b) and (c) of the claim totalling $70,452.42 will be considered together because the court feels that the same legal principles will control the result as to these three items.

Certain provisions of the contract should be mentioned at this point:

Article 12, paragraph 48 provides as follows: “The State Architect of the Department of Public Works shall have supervision and direction of the work ’ ’.

Article 12, paragraph 49: “ Should any portion of the drawings or specifications be obscure or in dispute, they shall be referred to the State Architect and he shall decide as to the true meaning and intent.”

Article 12, paragraph 50: “ Should any disagreement or difference arise on any point concerning the character, acceptability or nature of the several kinds of work or materials * * * the decision of the State Architect shall be final and binding upon all parties to the contract.” (Emphasis ours.)

“ The State Architect shall decide all matters relating to the execution and progress of the work and his decision thereon shall be final.” (Emphasis ours.)

Article 4 under the heading “ principles ” appear the following provisions:

“Whenever the word ‘State’ or ‘Owner’ appears in the Proposal, the Agreement, the General Conditions, the drawings, the Specifications or any addenda or amendments to the foregoing, it shall be understood to refer to the New York State Thruway Authority.
“Wherever the words ‘ Architect ’, ‘ State Architect ’, ‘ Department of Public Works ’, ‘ Engineer ’, ‘ Superintendent of Public Works ’ or ‘ Division of Construction ’ appear in such documents or drawings, they shall be understood to refer to the firm of Eggers and Higgins with offices at 100 E. 42nd St., New York 17, N. Y.’ After atoard of the Contract, a,ll supervision and all other matters encountered during the course of the contract which would normally be referred to or performed by the State Architect will, instead be directed to and performed by said firm of Eggers and Higgins.” (Emphasis ours.)

[221]*221Article 29, paragraph 129 provides as follows: “ Orders on Contract shall enumerate the work to be performed.” (Emphasis ours.)

It also provides that: “ If the nature of the work is such that an Order on Contract as above cannot be issued until the work has been advanced sufficiently to obtain exact quantities, said work will be authorized in writing by the State Architect, with the accompanying statement that an Order on Contract will be issued when the necessary information is at hand.”

Article 29, paragraph 129 further provides as follows: “Except as provided in the above paragraph no change shall be made unless in pursuance of an Order on Contract.”

A proper application of these contractual provisions will aid in the disposition of damage items (a), (b) and (c) enumerated above.

Item (a) for $50,882.24 is for extra rock excavation. A controversy developed during the course of construction because of language ambiguity, as to whether or not this work was to be done by the claimant or by the site contractor. After much discussion, written and oral, the Architect determined that this was part of the claimant’s contract and after the work had been completed issued an order on contract to the claimant for said sum of $50,882.24; that the State Architect closely followed the quantity of excavation being performed by the claimant and the amount justly due it for this item is indicated by the fact that the claimant originally put in a requisition for $52,912 for this item and later because the Architect’s computations of quantities were somewhat less, the claimant accepted the Architect’s figures and the amount was adjusted to the amount put in the order on contract by the Architect, namely, $50,882.24.

Item (b) was a claim for extra compensation in the sum of $14,403.84 for hauling water to the contract site. The contract provided that at a specified time water for the job would be provided by the plumbing contractor which obligation the plumbing contractor totally failed to fulfill. In order not to interrupt the progress of the work, the Authority’s Architect authorized the claimant to obtain its own water supply for extra compensation. This arrangement was confirmed by letter of the claimant. After the cost of this extra work was determined the Architect prepared an order on contract for said sum of $14,403.84.

That the Authority is not seriously contesting the propriety of this item is demonstrated by the fact that it has withheld this [222]*222am mint, from moneys due the plumbing contractor indicating that the cost of this extra work for hauling water which should have been done by the plumbing contractor will be charged back to the plumbing contractor if the Authority is obliged to pay it to the claimant.

Item (c) in the amount of $5,166.34 is claimed to be due the claimant for pumping and cleaning of excavations resulting from the fact that the Authority permitted the site contractor to commence its operations too soon. The site contractor brought heavy equipment in the area where the claimant was working.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
41 Misc. 2d 218, 245 N.Y.S.2d 521, 1963 N.Y. Misc. LEXIS 1782, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peter-a-camilli-sons-inc-v-state-nyclaimsct-1963.