Peschel v. Jones

760 P.2d 51, 232 Mont. 516, 45 State Rptr. 1244, 1988 Mont. LEXIS 189
CourtMontana Supreme Court
DecidedJuly 14, 1988
Docket88-058
StatusPublished
Cited by24 cases

This text of 760 P.2d 51 (Peschel v. Jones) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peschel v. Jones, 760 P.2d 51, 232 Mont. 516, 45 State Rptr. 1244, 1988 Mont. LEXIS 189 (Mo. 1988).

Opinion

MR. JUSTICE HARRISON

delivered the Opinion of the Court.

Plaintiff/appellant, Walter H. Peschel, appeals a summary judgment granted in favor of defendant/respondent, William Evan Jones. Summary judgment was granted on two separate dates, December 11, 1986 and December 8, 1987, in the Fourth Judicial District, Missoula County. We affirm.

In October of 1978, Walter Peschel (Peschel) was involved in the development and construction of an apartment complex which was to be known as the “Mountain Wood Apartments.” Peschel was the sole general partner of a limited partnership. In June, 1978, Peschel entered an oral agreement, known as the MacDonald Agreement, with Charles Isaly (Isaly) for the construction of the complex. Isaly represented the construction contractor, Martin Development Company (Martin Development).

The principal lender was the Washington Mortgage Company (Washington Mortgage), the loan was guaranteed by the Department of Housing and Urban Development (HUD), and the parties entered a HUD form construction contract June 6, 1978. The loan amount obtained from Washington Mortgage did not include the total amount needed for construction. Peschel desired to construct a complex of a quality which would cost more than the guarantee obtained from HUD. Peschel intended to personally finance the amounts above that provided in the principal loan.

Construction of the complex began in July, 1978 and financing *518 problems developed shortly thereafter. Peschel later hired defendant, William Evan Jones (Jones) an attorney at law, to assist in negotiations regarding the financing difficulties. On October 2, 1979, Washington Mortgage notified Peschel that he had defaulted on his loan and that the loan was going to be assigned to HUD. On November 10, 1979, Peschel and the contractor Martin Development entered into a written agreement, entitled Addenda No. 1. The agreement was signed by these two parties only and was an attempt to cure the financing problems so as to allow construction to continue. The Addenda agreement released and discharged both parties from all disputes existing between them on that date. Work resumed on the project'into December, 1979. However, when Martin Development prepared construction loan requisition No. 13 (Draw No. 13), Washington Mortgage refused to pay the disbursement because it intended to reassign the construction loan to HUD. As a result, no further construction loan draws would be authorized and disbursed until HUD accepted the assignment and approved the draws. Many subcontractor bills were not paid on time and construction ceased.

Peschel filed a “complaint for damages for professional negligence” against Jones on November 14,1985. The complaint alleged that the agreement negotiated by Jones, Addenda No. 1, was inadequate and proximately caused damages totaling $1,095,740 for increased construction costs, monies which could not be refunded from escrow, legal fees, accounting fees, rent impoundment charges, and an interest rate increase incurred when forced to refinance the project. Peschel alleged Addenda No. 1 was defective because, inter alia, it failed to obtain consent from HUD, the contractor’s bonding company, and Washington Mortgage. Additionally, the complaint alleged various other defects including: Jones failed to negotiate a resolution as to the current defaults with Washington Mortgage, failed to advise Peschel that construction would cease unless additional parties consented, released the contractor Martin Development from all claims, and incorrectly advised Peschel of liability limitations.

The District Court granted a partial summary judgment in favor of defendant Jones December 11, 1986, based on a theory of collateral estoppel. The District Court granted summary judgment for Jones as to the remainder of the complaint December 8,1987, holding that the statute of limitations prohibited the remaining issues from going forward.

Peschel raises two issues on appeal:

*519 1. Did the District Court correctly determine that defendant was entitled to partial summary judgment based on collateral estoppel?

2. Did the statute of limitations prohibit plaintiff from his cause of action?

1. Collateral Estoppel.

The facts surrounding this case are somewhat involved and have spawned a significant amount of litigation. In Martin Development Co. v. Keeney Construction Co. (Mont. 1985), [216 Mont. 212,] 703 P.2d 143, 42 St.Rep. 752, we affirmed a District Court award of $40,000 to Martin Development for lost profits and against Peschel. We also held that the Addenda represented the entire agreement of the parties and reversed an award of attorney’s fees and an award of interest based on lost profits. Martin Development Co., 703 P.2d at 148, 42 St.Rep. at 758. In the present case, plaintiff Peschel is bound by the facts and law as established by this prior case.

Defendant Jones entered a motion for summary judgment on November 10, 1986. Jones alleged that portions of the acts or omissions alleged by Peschel to constitute legal malpractice had been effectively determined by prior litigation and that Jones was entitled to summary judgment as to those acts or omissions according to the theory of collateral estoppel. The District Court granted partial summary judgment December 11, 1986, and denied a motion by plaintiff Peschel to alter or amend the partial summary judgment February 9, 1987. The District Court also issued two orders clarifying the extent of the partial summary judgment on June 5, 1987 and August 12, 1987.

Simply stated, Peschel’s claim is that Jones produced a defective document and offered Peschel defective legal advice when he presented Addenda No. 1 to Peschel and advised him to sign it. More specifically, Peschel listed the following twelve acts or omissions in his complaint labeled a. through 1. of paragraph V:

“a. Defendant failed to procure the consent of HUD to ‘Addenda No. 1,’ agreement between Plaintiff and the contractor.
“b. Defendant failed to obtain the consent of the contractor’s bonding company to ‘Addenda No. 1.’
“c. Defendant failed to obtain the consent of Washington Mortgage Company to “Addenda No. 1’ or to attempt to negotiate resolution of current defaults with that firm.
“d. Defendant advised Plaintiff that the consent of the foregoing *520 parties was not necessary for ‘Addenda No. 1’ to be effective and for the project to continue.
“e. Defendant drafted and advised Plaintiff to agree to paragraph 11 of ‘Addenda No. 1,’ which released and discharged the contractor from all claims.
“f. Defendant failed to obtain commitment from HUD to release draw No. 13 in conjunction with carrying out ‘Addenda No. 1.’
“g. Defendant advised Plaintiff that commitment of HUD to release Draw No. 13 was not necessary.
“h.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ehrman v. Kaufman, Vidal, Hileman & Ramlow, PC
2010 MT 284 (Montana Supreme Court, 2010)
Ereth v. Cascade County
2003 MT 328 (Montana Supreme Court, 2003)
Spolar v. Datsopoulos
2003 MT 54 (Montana Supreme Court, 2003)
Johnson v. Barrett
1999 MT 176 (Montana Supreme Court, 1999)
Matter of Beneficial Water Use Permits
923 P.2d 1073 (Montana Supreme Court, 1996)
Matter of Application for Beneficia
Montana Supreme Court, 1996
Uhler v. Doak
885 P.2d 1297 (Montana Supreme Court, 1994)
Cate v. First Bank (N.A.) - Billings
865 P.2d 277 (Montana Supreme Court, 1993)
Dees v. American National Fire Insurance
861 P.2d 141 (Montana Supreme Court, 1993)
Owen v. Ostrum
855 P.2d 1015 (Montana Supreme Court, 1993)
Rouane v. Lynaugh
855 P.2d 114 (Montana Supreme Court, 1993)
Kuhns v. Scott
853 P.2d 1200 (Montana Supreme Court, 1993)
Minnie v. City of Roundup
849 P.2d 212 (Montana Supreme Court, 1993)
Young v. Datsopoulos
817 P.2d 225 (Montana Supreme Court, 1991)
Boles v. Simonton
791 P.2d 755 (Montana Supreme Court, 1990)
Walker v. St. Paul Fire & Marine Insurance
786 P.2d 1157 (Montana Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
760 P.2d 51, 232 Mont. 516, 45 State Rptr. 1244, 1988 Mont. LEXIS 189, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peschel-v-jones-mont-1988.