Perry v. Schaumann

716 P.2d 1368, 110 Idaho 596, 1986 Ida. App. LEXIS 393
CourtIdaho Court of Appeals
DecidedMarch 31, 1986
Docket15639
StatusPublished
Cited by12 cases

This text of 716 P.2d 1368 (Perry v. Schaumann) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perry v. Schaumann, 716 P.2d 1368, 110 Idaho 596, 1986 Ida. App. LEXIS 393 (Idaho Ct. App. 1986).

Opinion

SWANSTROM, Judge.

This is an appeal by Gary and Vicki Schaumann from a judgment in favor of Douglas L. and Linda Lee Perry (the Per-rys), doing business as Perry Construction Company, for money due on an oral contract to remodel the Schaumann house. The sole issue on appeal is whether the trial court erred by failing to allow the Schaumanns credit for a payment they made to a supplier of materials. For reasons explained below, we affirm and remand the case for entry of a modified judgment.

The dispute arises out of an oral agreement between Douglas Perry (Perry) and the Schaumanns. The parties agreed that Perry, as a general contractor, would build an addition to and extensively remodel the Schaumann house on a cost plus ten percent basis. It was further agreed that Perry would bill the Schaumanns monthly for the cost of materials and labor incurred on the project. Perry encountered several difficulties during the course of construction, including discovery that the foundation of the existing house was out of square, the walls leaned, and the floors were unlevel. The Schaumann family continued to occupy the home throughout the construction. Due to these difficulties the job went slowly, causing a dispute between the Schaumanns and Perry. Ultimately, the Schaumanns refused to make further payments until the addition to the house was closed in. In response to this ultimatum Perry terminated the job because of his inability to pay further costs of construction. Subsequently, Boise Cascade, a supplier of materials to the project, filed a complaint against the Perrys and the Schaumanns, among others, seeking payment for the costs of materials furnished. The Perrys filed a cross-complaint against the Schaumanns for the amount due under the construction contract.

Before trial, the Schaumanns and Boise Cascade entered into a settlement of the Boise Cascade claim. A stipulation for dismissal was filed in the district court. The stipulation dated July 9, 1982, stated that:

The Plaintiff [Boise Cascade] acknowledges receipt from Schaumanns of the sum of $6,897.87 in the form of a $5,000.00 negotiable draft, paid in hand, and Schaumann’s unconditional authorization to Plaintiff to apply Schaumann’s credit account with Plaintiff in the sum of $1,897.87 to the amounts claimed owing by Plaintiff in the above-captioned matter.

Pursuant to the stipulation the court dismissed Boise Cascade’s claim against the Schaumanns. Over a year later, Boise Cascade and the Perrys also stipulated for dismissal of Boise Cascade’s claim against the Perrys “for the reason that the same has been fully compromised and settled.” An order of dismissal was entered.

Subsequently, a court trial was held upon the Perrys’ cross-claim. After the court *598 entered its findings of fact and conclusions of law, the Schaumanns and the Perrys submitted motions to amend the findings. The Schaumanns argued that when the trial court computed the amount due Perry the court erroneously omitted giving the Schaumanns credit for payment of the Boise Cascade bill for materials.

After a hearing the district court denied the Schaumanns’ motions, ruling that:

In particular, there is insufficient evidence to finding [sic] that the Schau-manns paid the remaining sum owed by Perry to Boise Cascade in the amount of $7,477.40. No check or document was entered into evidence in support of such claim. No testimony was elicited that any alleged payment by the Schaumanns to Boise Cascade was credited to the remaining amount owed by Perry to Boise Cascade.

The order makes no mention of the Boise Cascade-Schaumann stipulation and we have no record of the arguments made at the hearing. Therefore, we do not know for what reasons the court failed to give effect to the stipulation.

The court entered judgment in accordance with its findings of fact and conclusions of law. In its findings of fact, the court added together the cost of the materials purchased by Perry on behalf of the Schaumanns, the labor expended on the project and miscellaneous expenses. In accordance with the parties’ oral agreement, the court added ten percent, deriving a total of $50,145.58. The court then subtracted from the total the amount Schau-mann had paid to Perry, $37,637.40. The Perrys were awarded the difference, the sum of $12,508.18.

The Schaumanns contend that the court included the price of materials purchased from Boise Cascade in computing the total cost of materials without allowing an offsetting credit to the Schaumanns for settlement of the Boise Cascade claim. When Perry terminated work on the Schaumann home a balance of $7477 remained owing to Boise Cascade for materials, according to the Perrys’ own evidence. 1 The Schau-manns argue that this balance was discharged by them as shown by the stipulation and by the evidence. They claim entitlement to an offset of $7477 or in the alternative for an offset of $6897, the amount they actually paid to settle the Boise Cascade claim.

When parties settle and compromise their disputed obligations, the settlement is binding on the parties. Rasmussen v. Martin, 104 Idaho 401, 659 P.2d 155 (Ct.App.1983). Stipulations are a form of judicial admission. Northwestern National Casualty Co. v. State, 682 P.2d 486 (Colo.App.1983). A judicial admission “obviates the necessity for proof of facts within the ambit of a distinct and unequivocal admission or stipulation so made.” McLean v. City of Spirit Lake, 91 Idaho 779, 783, 430 P.2d 670, 674 (1967). However, the parties cannot by stipulation affect the rights of a third party not joining in the stipulation. Arnett v. Throop, 75 Idaho 331, 272 P.2d 308 (1954). The stipulation stating that the Schaumanns had paid Boise Cascade was made between the Schaumanns and Boise Cascade; the Perrys were not parties to the stipulation and were not bound by it. See Driscoll v. Harmon, 116 Ariz. 332, 569 P.2d 274 (Ariz.App.1977).

Here, however, there is no reason why the stipulation cannot be viewed as evidence of the fact that the debt owed to Boise Cascade had been paid. The stipulation is an acknowledgement by the creditor, Boise Cascade, that at least the amount of $6,897.87 has been paid. The acknowledgment of payment is prima facie evidence of that payment. Sturmville Lumber Company v. Davis, 416 S.W.2d 49 (Mo.App.1967). “Once a creditor has applied a payment to an obligation, the debt is reduced.” Johnson Equipment, Inc. v. Nielson, 108 *599 Idaho 867, 870, 702 P.2d 905, 908 (Ct.App.1985). The trial court may take judicial notice of its own records in the case before it. Larson v. State,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Medical Recovery Services, LLC v. Baird
Idaho Court of Appeals, 2024
Smith v. Smith
Idaho Supreme Court, 2020
Hilary Beth Candland Firmage v. Howard Hunter Snow
347 P.3d 191 (Idaho Supreme Court, 2015)
Hilary Firmage v. Howard Snow
Idaho Supreme Court, 2015
Reding v. Reding
109 P.3d 1111 (Idaho Supreme Court, 2005)
State v. Kotis
984 P.2d 78 (Hawaii Supreme Court, 1999)
Strouse v. K-Tek, Inc.
930 P.2d 1361 (Idaho Court of Appeals, 1997)
Ratliff v. Ratliff
925 P.2d 1121 (Idaho Supreme Court, 1996)
Pueblo v. Echevarría Rodríguez
128 P.R. Dec. 299 (Supreme Court of Puerto Rico, 1991)
Dursteler v. Dursteler
733 P.2d 815 (Idaho Court of Appeals, 1987)
Costello v. Watson
720 P.2d 1033 (Idaho Court of Appeals, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
716 P.2d 1368, 110 Idaho 596, 1986 Ida. App. LEXIS 393, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perry-v-schaumann-idahoctapp-1986.