Opinion

Mount, J.

This action was brought to recover $247.68, alleged to be the reasonable value of merchandise and services furnished to the defendants at their request. The answer of the defendants admitted that merchandise of the value of $132 was furnished, but denied that there was any debt owing to the plaintiff. As an affirmative defense and counterclaim, the defendants alleged, in substance, that one of the items furnished was an impeller for a Engsford pump; that, at [345]*345the time this impeller was ordered, the defendants were engaged upon a contract with the city of Seattle to do certain sluicing work which required the use of a pump; that the plaintiff knew these facts and was familiar with the mechanism of the pump then owned and being used by the defendants, and that the defendants were not familiar with such pumps; that the pump became out of repair and failed to work; that the plaintiff advised the defendants that it would be necessary to purchase a new impeller for the pump; that the defendants, relying upon that advice, ordered from the plaintiff a new impeller; that when the impeller was delivered and placed in the pump, it failed to work satisfactorily; that defendants, in endeavoring to make the impeller work properly, expended $259.75 thereon, and still the impeller would not perform the work which it was intended and designed to perform, and by reason of such failure, the defendants sustained loss of profits amounting to $451.75; and prayed for damages in the amount of $319.75. This affirmative matter was denied by the plaintiff.

Upon these issues, a trial was had to the court and a jury, resulting in a verdict in favor of the defendants for $126.75, the difference between $133, admitted to be owing to the plaintiff, and $259.75, claimed to have been expended in an endeavor by the defendants to make the new impeller work satisfactorily. Upon the plaintiff’s motion for a new trial, the court required a reduction from the verdict of $92, the price of the impeller, and entered a judgment for $34.75 in favor of the defendants. The plaintiff has appealed.

The principal errors assigned relate to the instructions of the court. The respondents move to strike the exceptions to the instructions because these exceptions are not embodied in the statement of facts. The record shows that the exceptions were taken in time, and allowed by order of the court. These exceptions and the order are a part of the transcript, and are certified therein by the clerk. This is sufficient un[346]*346der Rem. & Bal. Code, § 395 (P. C. 81 § 697). The motion is therefore denied.

The undisputed facts are, in substance, as follows: In January, 1914, the defendants had a contract with the city of Seattle for grading certain streets. This grading work was being done by sluicing the earth. A pump, known as a Kingsford pump, was then owned by the defendants, and was being used for pumping water for sluicing. This pump was purchased by the defendants, second-hand, from a third party who had originally purchased the pump from the plaintiff. This third party had used the pump for about a year, and sold it to the defendants.

In the progress of the work, the impeller was worn and badly damaged by a stone or some substance which had gone through the pump. The impeller was taken out of the pump and taken to the plaintiff, a dealer in Kingsford pumps, and it was requested to repair the impeller. Upon an examination of the impeller, the plaintiff said that it could repair it so that it could be used for a time, but that it would not work well, and that the defendants ought to procure a new impeller. The defendants thereupon directed the plaintiff to order a new impeller from the factory. The plaintiff did not carry extra impellers in stock, and it was directed to hurry up the order. The plaintiff thereupon wired to the factory for a new impeller, and directed that the same be shipped by express. The impeller was sent by the factory to the plaintiff, and it thereupon installed the new impeller in the pump. The price of the impeller was $92. The expressage was $22.68.

After the impeller had been placed in the pump, the defendants notified the plaintiff that the impeller did not work satisfactorily. The plaintiff thereupon advised that there must be something the matter with some of the pipes. The plaintiff made no effort to fix the impeller. Thereupon the defendants endeavored to remedy the pump, and it was used for a period of two months. Thereafter the plaintiff sent a [347]*347statement of its account to the defendants, who promised to pay the same, but never did. After several unsuccessful attempts to collect the account, this action was brought.

The principal contention of the defendants at the trial was that there was an implied warranty that this impeller would work satisfactorily in this second-hand pump. It is not claimed that there was any express warranty. But the defendants insisted in the court below, and insist here, that there was an implied warranty that the impeller ordered as above stated would make the pump work satisfactorily to the defendants.

At the close of the evidence, the plaintiff requested the court to give an instruction, in substance, that the jury should return a verdict in favor of the plaintiff for the full amount claimed. We think this instruction should have been given. It is plain, under the facts, that if there had been an express warranty, damages on account of lost profits in a contract of this kind could not be recovered. Puget Sound Iron & Steel Works v. Clemmons, 32 Wash. 36, 72 Pac. 465. We think it is equally plain that there could be no implied warranty that the new impeller would make the old pump work satisfactorily, upon the admitted facts. The rule is:

“On a sale of machinery there is in general an implied warranty that the machine is reasonably adapted to the purpose for which it is purchased. No such warranty is implied, however, on the sale of a second-hand machine. There is, moreover, no warranty that a machine designed for a general use is suitable for a particular purpose or use, or that a known and designated machine purchased by name will serve a specific purpose, especially where the machine is made according to the plans and specifications of the buyer. So too there is no implied warranty that a machine is as suitable for the purpose as other machines of the same class.” 35 Cyc. 408.

The rule is also stated in 35 Cyc. 405, as follows:

“On a sale by sample there is an implied warranty that the bulk of the goods is equal to the sample in kind and [348]*348quality. Where the sale is by the manufacturer of the goods there is an implied warranty that the goods sold are free from latent defects not discoverable by ordinary examination; but the rule is otherwise where the sale is by a dealer who is not the manufacturer of the goods. There is no warranty of fitness for the purpose intended, nor ordinarily that the goods are merchantable, although the facts and circumstances of the case may justify the inference that this condition is superadded to the contract. The warranty implied is not strictly speaking a warranty of quality, but merely that the seller shall deliver goods of the quality of the sample.”

This court in Hurley-Mason Co. v. Stebbins, Walker & Spinning, 79 Wash. 366, 140 Pac. 381, L. R. A. 1915 B 1131, said:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J. W. Anderson Co. v. Tomlinson Chair Manufacturing Co.
172 S.E. 538 (Supreme Court of North Carolina, 1934)
Yarno v. Hedlund Box & Lumber Co.
225 P. 659 (Washington Supreme Court, 1924)
Durbin v. Denham
210 P. 165 (Oregon Supreme Court, 1922)
Lamb v. Otto