Performance Contracting, Inc. v. Rapid Response Construction, Inc.

CourtDistrict Court, District of Columbia
DecidedJune 27, 2011
DocketCivil Action No. 2009-0639
StatusPublished

This text of Performance Contracting, Inc. v. Rapid Response Construction, Inc. (Performance Contracting, Inc. v. Rapid Response Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Performance Contracting, Inc. v. Rapid Response Construction, Inc., (D.D.C. 2011).

Opinion

SUMMARY MEMORANDUM AND OPINION; NOT INTENDED FOR PUBLICATION.

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

PERFORMANCE CONTRACTING, INC.,

Plaintiff, Civil Action No. 09-cv-00639 (RLW) v.

RAPID RESPONSE CONSTRUCTION, INC.,

Defendant.

MEMORANDUM OPINION

Plaintiff Performance Contracting, Inc. (“Performance”) brings this action against

Defendant Rapid Response Construction, Inc. (“Rapid”). Performance alleges that it

accidentally overpaid Rapid for its work under a construction subcontract. Performance further

alleges that Rapid’s refusal to repay this amount results in a material breach of contract (Count

I), and that Rapid is unjustly enriched as a result of its continued retention of this payment

(Count II). This matter is presently before the Court on Rapid’s Motion to Dismiss the

Complaint with Prejudice or, in the Alternative, for Summary Judgment. Having considered the

Motion, Opposition, and Reply, Rapid’s Motion is denied.

I. BACKGROUND1

Performance entered into a subcontract agreement with Rapid to perform certain

construction work. Compl. ¶ 8. The subcontract included a provision that Performance would

withhold five percent (5%) of the contract value owed to Rapid, called the retention, until

1 Unless otherwise noted, this account of the facts reflects the factual allegations in Performance’s complaint and does not incorporate Rapid’s response to those factual allegations.

SUMMARY MEMORANDUM AND OPINION; NOT INTENDED FOR PUBLICATION.

Performance received final payment from the general contractor, Hunt Construction Group, Inc.

(“Hunt”), and the project was completed. Id. ¶ 9 and Ex. 1, Subcontract Attachment C § 7.

Initially, Rapid and a company called Blake & Day Construction (“B&D”) subcontracted

as a joint venture to Performance. Comp. ¶ 11. However, a dispute arose between the parties,

and B&D filed a lawsuit naming Rapid, Hunt, and Performance as defendants. Id. The parties

eventually settled the litigation, and as part of the settlement terms, Hunt and Performance

agreed to escrow all proceeds from the contracts related to Rapid, with Rapid and B&D to decide

independently how to distribute the escrowed proceeds. Id.

After the project was completed, Performance performed a routine audit in September

2006 and discovered that Performance had inadvertently paid Rapid the same $166,147.00

retention amount twice. Id. ¶ 12. Performance informed Rapid of the double payment and

attempted to make arrangements for refund/return of the extra $166,147.00. Id. ¶ 13.

Thereafter, Performance met with officials from Rapid who acknowledged the overpayment and

began negotiating how Rapid could repay Performance. Id. ¶ 14. On February 24, 2009,

Performance sent Rapid a letter and supporting documentation regarding the overpayment via

United Parcel Service (UPS). Id. ¶ 15 & Ex. 3 (2/24/2009 Letter & Exhibits). UPS delivered the

package to Rapid on February 25, but it was returned to Performance a month later, having been

opened and taped shut bearing a notation from UPS that “RECEIVER DID NOT WANT,

REFUSED DELIVERY” and indicating that the original receiver was Rapid Response. Comp. ¶

15 & Ex. 5 (UPS Return).

Rapid has failed or otherwise refused to refund the overpayment amount of $166,147.00.

Comp. ¶ 16. In its Complaint, Performance claims that Rapid’s failure to remit a refund of the

overpayment after being timely notified is a material breach of the subcontract agreement.

SUMMARY MEMORANDUM AND OPINION; NOT INTENDED FOR PUBLICATION.

Comp. ¶¶ 17-23. Performance also claims that Rapid did not earn the additional $166,147.00,

and has thus been unjustly enriched by the accidental overpayment. Id. ¶¶ 24-30.

II. LEGAL STANDARD

“To survive a motion to dismiss under Rule 12(b)(6), a complaint must contain sufficient

factual matter, acceptable as true, to state a claim to relief that is plausible on its face.”

Anderson v. Holder, 691 F.Supp.2d 57, 61 (D.D.C. 2010) (brackets omitted) (quoting Ashcroft v.

Iqbal, --- U.S. ----, 129 S.Ct. 1937, 1949, 173 L.Ed.2d 868 (2009) (citing Bell Atl. Corp. v.

Twombly, 550 U.S. 544, 556, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007)) (internal quotes

omitted).

A court considering a Rule 12(b)(6) motion must construe the complaint in the light most

favorable to plaintiff and must accept as true all reasonable factual inferences drawn from well-

pleaded factual allegations. In re United Mine Workers of Am. Employee Benefit Plans Litig.,

854 F.Supp. 914, 915 (D.D.C. 1994).

In deciding a motion brought under Rule 12(b)(6), a court does not consider matters

outside the pleadings, but may consider on a motion to dismiss “the facts alleged in the

complaint, documents attached as exhibits or incorporated by reference in the complaint.”

Gustave-Schmidt v. Chao, 226 F.Supp.2d 191, 196 (D.D.C.2002).

However, when the Court must consider “matters outside the pleadings” to reach its

conclusion, a motion to dismiss “must be treated as one for summary judgment under Rule 56.”

Fed. R. Civ. P. 12(d); see also Yates v. District of Columbia, 324 F.3d 724, 725 (D.C. Cir. 2003);

Winston v. Clough, 712 F.Supp.2d 1, 6 (D.D.C. 2010) (“[W]here both parties submit material

outside the pleadings and the parties are not taken by surprise or deprived of a reasonable

opportunity to contest facts averred outside the pleadings and the issues involved are discrete

SUMMARY MEMORANDUM AND OPINION; NOT INTENDED FOR PUBLICATION.

legal issues, the court may convert the motion to a motion for summary judgment without

providing notice or the opportunity for discovery to the parties.”) (internal citations omitted).

Summary judgment is appropriately granted when the moving party demonstrates that

there is no genuine issue as to any material fact and that moving party is entitled to judgment as a

matter of law. Moore v. Hartman, 571 F.3d 62, 66 (D.C. Cir. 2009) (citing Fed. R. Civ. P. 56(c)

and Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247 (1986)). “In considering a motion for

summary judgment, [a court is to draw] all ‘justifiable inferences' from the evidence ... in favor

of the nonmovant.” Cruz-Packer v. Dist. of Columbia, 539 F.Supp.2d 181, 189 (D.D.C. 2008)

(quoting Anderson, 477 U.S. at 255); Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475

U.S. 574, 587 (1986).

III. DISCUSSION

Rapid argues that Performance’s claims should be dismissed because the claims are time-

barred. Def.’s Mem. at 7. The parties agree that under District of Columbia law, a three-year

statute of limitations applies to claims for breach of contract and unjust enrichment. See D.C.

Code § 12-301(7)-(8). Plaintiff filed its complaint on April 6, 2009. Thus, any claims that

accrue prior to April 6, 2006—three years before the filing of the complaint—are time-barred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Smith-Haynie, J. C. v. Davis, Addison
155 F.3d 575 (D.C. Circuit, 1998)
Yates v. District of Columbia
324 F.3d 724 (D.C. Circuit, 2003)
Moore v. Hartman
571 F.3d 62 (D.C. Circuit, 2009)
Myrna O'Dell Firestone v. Leonard K. Firestone
76 F.3d 1205 (D.C. Circuit, 1996)
Cruz-Packer v. District of Columbia
539 F. Supp. 2d 181 (District of Columbia, 2008)
Gustave-Schmidt v. Chao
226 F. Supp. 2d 191 (District of Columbia, 2002)
Anderson v. Holder
691 F. Supp. 2d 57 (District of Columbia, 2010)
Winston v. Clough
712 F. Supp. 2d 1 (District of Columbia, 2010)
Smith v. Brown & Williamson Tobacco Corp.
3 F. Supp. 2d 1473 (District of Columbia, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Performance Contracting, Inc. v. Rapid Response Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/performance-contracting-inc-v-rapid-response-const-dcd-2011.