Performance Contracting Inc. v. DynaSteel Corporation

750 F.3d 608, 2014 WL 1663077, 2014 U.S. App. LEXIS 7869
CourtCourt of Appeals for the Sixth Circuit
DecidedApril 28, 2014
Docket13-1364
StatusPublished
Cited by35 cases

This text of 750 F.3d 608 (Performance Contracting Inc. v. DynaSteel Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Performance Contracting Inc. v. DynaSteel Corporation, 750 F.3d 608, 2014 WL 1663077, 2014 U.S. App. LEXIS 7869 (6th Cir. 2014).

Opinions

McKEAGUE, J., delivered the opinion of the court, in which SILER, J. joined, and WHITE, J., joined in part. WHITE, J. (pp. 617-19), delivered a separate opinion concurring in part.

OPINION

McKEAGUE, Circuit Judge.

This case arises out of a dispute between a general contractor and a subcontractor over payment for services rendered. The ease presents questions concerning the interpretation and application of the Michigan Building Contract Fund Act, commonly referred to as the Michigan Builder’s Trust Fund Act (“Trust Fund Act”). The district court ruled that the facts underlying this case did not trigger application of the Trust Fund Act, and granted summary judgment to the general contractor. For the reasons discussed below, we affirm.

I.

This case concerns the interplay between three parties: a general contractor, the owner of a power plant, and a subcontractor. The general contractor — and a defendant in this case — is DynaSteel, a company that had operations in Tennessee and Mississippi. DynaSteel manufactured ductwork for power plants for nearly forty years, but in 2012, the company dissolved and liquidated its assets. DynaSteel’s Chief Executive Officer, James Russell, Jr., and its Chief Financial Officer, Ronald Russell, are the other defendants to this case. Both Russells live in Tennessee.

Consumers Energy owned a power plant in Essexville, Michigan. On September 30, 2008, Consumers Energy and DynaSteel entered into a Purchase Order contract concerning the Michigan plant, known as the Karn Project. Under the Purchase Order, DynaSteel would — at its facilities in Mississippi and Tennessee— furnish, fabricate, and assemble ductwork [610]*610for the Karn Project, and then complete all packaging, storage, handling, and shipping necessary to send the ductwork to the Michigan plant for installation, which would be completed by a third party. The Purchase Order contained a Michigan choice-of-law provision. Consumers Energy later issued a Project Change Notice to DynaSteel, which requested additional labor on the ductwork. The Project Change Notice contained no choice-of-law provision. Pursuant to the Purchase Order and the Project Change Notice, Consumers Energy would pay DynaSteel $10,634,755 for the Karn Project.

The subcontractor — and plaintiff in this case — is Performance Contracting, Inc. (“PCI”), a company with headquarters in Kansas and an office in Tennessee. PCI and DynaSteel had a longstanding relationship, having worked on a project in Ohio (the Sammis Project) as well as another project in Maryland (the Brandon Shores Project) together. On February 28, 2009, DynaSteel issued a Purchase Order Agreement requesting that PCI supply the insulation requested by Consumers Energy for $1,842,890. This Purchase Order Agreement, which was both issued by DynaSteel and signed by PCI in Tennessee, contained a Tennessee choice-of-law provision.

As the Karn Project progressed, Consumers Energy paid DynaSteel over $2.9 million for DynaSteel’s work, but DynaSteel did not reimburse PCI for PCI’s work, owing PCI $1,542,890. DynaSteel had also not reimbursed PCI for PCI’s work done on the Sammis Project, owing PCI $2,587,079, and the Brandon Shores Projects, owing PCI $749,675. Instead of paying PCI the remaining money it owed or segregating the funds into a separate trust, DynaSteel placed the funds it received from Consumers Energy into a general account in which DynaSteel allegedly comingled it with funds from other projects.

DynaSteel and PCI tried to resolve their differences over the unpaid monies from the Karn, Sammis, and Brandon Shores Projects during several meetings in Tennessee and in Kansas. On November 17, 2009, the parties executed a Payment Plan Proposal that addressed all three projects. The Payment Plan Proposal required DynaSteel to make periodic payments, which would apply to the unpaid projects in chronological order — meaning that monies paid by DynaSteel would first apply to the balances on the Sammis and Brandon Shores Projects, and then after those projects were paid in full, then to the balance outstanding for the Karn Project. The Payment Plan Proposal did not contain a choice-of-law provision. Between November 2009 and June 2010, pursuant to the Payment Plan Proposal, DynaSteel made payments to PCI totaling over $2.1 million. The payments fulfilled DynaSteel’s financial obligations as to the Sammis and Brandon Shores Projects, but did not fulfill its financial obligation as to the Karn Project, with a balance of approximately two million dollars still outstanding.

The unpaid balance led to this current action. On December 14, 2011, PCI filed suit against DynaSteel in the State of Michigan’s Bay County Circuit Court. PCI alleged, among other claims, that DynaSteel violated the Trust Fund Act. On January 13, 2012, DynaSteel removed the case on diversity grounds to the U.S. District Court for the Eastern District of Michigan. Both parties moved for summary judgment on the issue of whether the Trust Fund Act applied to their dispute.

In ruling on the two motions for summary judgment, the district court reached three conclusions. First, the district court held that the original Purchase Order be[611]*611tween PCI and DynaSteel — and not the subsequent Payment Plan Proposal — was controlling, meaning that the Tennessee choice-of-law provision in the Purchase Order remained binding on the parties. Second, the district court held that the Tennessee choice-of-law provision applied to the breach of contract for which PCI sued DynaSteel. Third, the district court ruled that the Trust Fund Act did not apply extraterritorially by its own force — meaning outside of the scope of or independent of the parties’ contract — to this case because in enacting the Trust Fund Act, the “Michigan legislature must have intended some connection to the state” and because PCI and DynaSteel’s “only connection to Michigan [was] the location of [Consumers Energy,] the owner that paid DynaSteel.” Dist. Ct. Opn. at 12-13, PagelD # 1581-82. The district court then granted summary judgment to DynaSteel. This appeal followed.

II.

This court reviews a district court’s grant of summary judgment de novo. Gecewicz v. Henry Ford Macomb Hosp. Corp., 683 F.3d 316, 321 (6th Cir.2012). A “court shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(a). In analyzing a motion for summary judgment, we construe all evidence in the light most favorable to the non-moving party. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). Questions of statutory interpretation are questions of law that are also reviewed de novo. Roberts v. Hamer, 655 F.3d 578, 582 (6th Cir.2011). Under Michigan law, statutory interpretation requires an examination of the plain language of the statute. See In re Certified Question, 468 Mich. 109, 659 N.W.2d 597

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
750 F.3d 608, 2014 WL 1663077, 2014 U.S. App. LEXIS 7869, Counsel Stack Legal Research, https://law.counselstack.com/opinion/performance-contracting-inc-v-dynasteel-corporation-ca6-2014.