Perficient v. Thomas Munley

43 F.4th 887
CourtCourt of Appeals for the Eighth Circuit
DecidedAugust 9, 2022
Docket21-2121
StatusPublished
Cited by4 cases

This text of 43 F.4th 887 (Perficient v. Thomas Munley) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perficient v. Thomas Munley, 43 F.4th 887 (8th Cir. 2022).

Opinion

United States Court of Appeals For the Eighth Circuit ___________________________

No. 21-2121 ___________________________

Perficient, Inc.

Plaintiff - Appellee

v.

Thomas Munley

Defendant - Appellant

Spaulding Ridge, LLC

Defendant ____________

Appeal from United States District Court for the Eastern District of Missouri - St. Louis ____________

Submitted: January 13, 2022 Filed: August 9, 2022 ____________

Before LOKEN, GRUENDER, and GRASZ, Circuit Judges. ____________

GRUENDER, Circuit Judge. The district court 1 granted Perficient, Inc.’s motion for summary judgment against Thomas Munley and Spaulding Ridge, LLC. It awarded nominal damages and attorney’s fees to Perficient, but its orders did not quantify the amount of the award. Munley appealed. Perficient filed a motion to dismiss for lack of appellate jurisdiction, arguing that the orders from which Munley appealed are not final. We grant the motion and dismiss for lack of jurisdiction.

I.

Perficient moved for summary judgment against its former employee Munley and Munley’s new employer Spaulding Ridge in a lawsuit involving non- competition and confidentiality agreements that Munley signed when he worked for Perficient. Munley also filed a motion for summary judgment. On April 15, 2021, the district court entered two orders granting Perficient’s motion and denying Munley’s. In these orders, the district court observed that Munley was liable to Perficient on its breach-of-contract claim. The district court determined, however, that no actual damages resulted from Munley’s breach. It instead found that Perficient was entitled to nominal damages. It also concluded that the attorney’s fees sustained by Perficient as a result of Munley’s breach were consequential damages of the breach, which were compensable as part of the damages element of the breach-of-contract claim. The district court did not specify any amount of either nominal damages or attorney’s fees; rather, it ordered that Perficient file a motion in support of its request for damages and attorney’s fees and that Munley file a response. The second order states that “[f]ollowing this briefing, the Court will enter a final judgment.” On May 14, 2021, before any judgment was entered, Munley filed a notice of appeal as to the April 15, 2021 orders. On June 2, 2021, Perficient filed a motion to dismiss for lack of jurisdiction.

1 The Honorable John A. Ross, United States District Judge for the Eastern District of Missouri.

-2- II.

Generally, a party in a civil case who desires to appeal must file a notice of appeal “within 30 days after entry of the judgment or order appealed from.” Fed. R. App. P. 4(a)(1)(A). The requirement of a timely notice of appeal is mandatory and jurisdictional. Arnold v. Wood, 238 F.3d 992, 995 (8th Cir. 2001). Federal courts of appeal have jurisdiction over appeals from “final decisions” of United States district courts. 28 U.S.C. § 1291.

Munley argues that the April 15, 2021 orders constituted a final judgment from which he timely appealed. Perficient contends that Munley’s notice of appeal was premature because the district court had not entered a final judgment from which an appeal could be taken.

We conclude that Munley’s notice of appeal was premature because the April 15, 2021 orders were not final, appealable orders. See 28 U.S.C. § 1291. “A final decision within the meaning of § 1291 ‘ends the litigation on the merits and leaves nothing for the court to do but execute the judgment.’” Dieser v. Cont’l Cas. Co., 440 F.3d 920, 923 (8th Cir. 2006) (quoting Borntrager v. Cent. States, Se. & Sw. Areas Pension Fund, 425 F.3d 1087, 1091 (8th Cir. 2005)). “A judgment awarding damages but not deciding the amount of the damages or finding liability but not fixing the extent of the liability is not a final decision within the meaning of § 1291.” Id.; see also St. Mary’s Health Ctr. of Jefferson City v. Bowen, 821 F.2d 493, 498 (8th Cir. 1987) (citing Parks v. Pavkovic, 753 F.2d 1397, 1404 (7th Cir.), cert. denied, 473 U.S. 906 (1985) (“Normally an order that merely decides liability and leaves the determination of damages to future proceedings does not finally dispose of any claim; it is just a preliminary ruling on the plaintiff’s damage claim.”)); Albright v. UNUM Life Ins. Co. of Am., 59 F.3d 1089, 1092 (10th Cir. 1995) ((brackets omitted) (quoting 16 Charles A. Wright & Arthur R. Miller, Federal Practice and Procedure § 4009 (3d ed.)) (“[A]n order that determines liability but leaves damages to be calculated is not final.”).

-3- However, a judgment awarding damages but not specifying the amount may still be considered final “if only ministerial tasks in determining damages remain.” Goodwin v. United States, 67 F.3d 149, 151 (8th Cir. 1995); see also Kohlbeck v. Wyndham Vacation Resorts, Inc., 7 F.4th 729, 736 (8th Cir. 2021) (concluding that the district court’s task was more than ministerial where it had yet to determine the amount of damages); Minn., Dep’t. of Revenue v. United States, 184 F.3d 725, 726 n.1 (8th Cir. 1999). The determination of damages is “ministerial” where it “requir[es] no independent legal judgment.” Cappuccio v. Prime Cap. Funding LLC, 649 F.3d 180, 187 (3d Cir. 2011); see also Woosley v. Avco Corp., 944 F.2d 313, 316-317 (6th Cir. 1991) (concluding that the determination of damages is “ministerial” where it consists merely of the calculation of a predetermined amount; that is, it is a mechanical or computational task).

Here, the district court awarded nominal damages but did not determine the amount of those damages. See Dieser, 440 F.3d at 923. Perficient did not request a specific amount of nominal damages, nor did the district court quantify the amount of nominal damages it intended to award in its orders. Cf. Green v. Study, 250 S.W.3d 799, 801-02 (Mo. Ct. App. 2008) (holding that the judgment was not final where it “state[d] no amount of punitive or nominal damages”). In fact, the district court explicitly left the nominal damage amount unresolved; it ordered that Perficient “may file any motion in support of its request for damages” and that Munley could respond. See Kohlbeck, 7 F.4th at 736 (stating that the district court’s order granting summary judgment was not final where it determined liability and ordered the parties to file a motion to determine the damages amount).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
43 F.4th 887, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perficient-v-thomas-munley-ca8-2022.