Perfetti Van Melle USA Inc. v. Dematic Corp.

CourtDistrict Court, E.D. Kentucky
DecidedJanuary 21, 2025
Docket2:24-cv-00190
StatusUnknown

This text of Perfetti Van Melle USA Inc. v. Dematic Corp. (Perfetti Van Melle USA Inc. v. Dematic Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perfetti Van Melle USA Inc. v. Dematic Corp., (E.D. Ky. 2025).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF KENTUCKY NORTHERN DIVISION (at Covington)

PERFETTI VAN MELLE USA INC., ) ) Plaintiff, ) Civil Action No. 2: 24-190-DCR ) V. ) ) DEMATIC CORP., ) MEMORANDUM OPINION ) AND ORDER Defendant. )

*** *** *** *** Defendant Dematic Corp. has filed a motion to dismiss all claims asserted by Plaintiff Perfetti Van Melle USA Inc. pursuant to under Rule 12(b)(6) of the Federal Rules of Civil Procedure. [Record No. 7] The motion will be granted because the plaintiff’s Complaint fails to state viable claims alleging breach of warranty, unjust enrichment, and fraudulent misrepresentation. I. Background Plaintiff Perfetti Van Melle USA Inc. (“PvM”) manufactures and distributes confectionery and chewing gum under brand names including AirHeads, Mentos, and Trident. [Record No. 1-1 at 3] Defendant Dematic Corp. (“Dematic”) is an engineering firm that designs, builds, and installs equipment that automates tasks in warehouse production. Id. In 2018, the parties contracted (“the Agreement”) for Dematic to design and install a custom Mass Put Module (“Module”) in PvM’s warehouse. The Module would allow pallets to be loaded and wrapped along a conveyor system. [Record Nos. 1-1 at 3–4 and 7 at 3] The Agreement specified a payment schedule, warranty provisions, process and significance of final acceptance, and the effect of subsequent change orders. [Record No. 1-1 at 4–5] PvM paid $2,030,067.47 for the Module which was divided into several payments. [See

Record No. 1-1 at 4, 6.] The final payment represented a ten percent retainer that the parties intended to be due thirty days after final acceptance of the Module. [Record No. 1-1 at 4] A two-year warranty was included in the total purchase price. The parties intended for the warranty to go into effect thirty days after final acceptance. See id. at 4–5, 8. Once that warranty period expired, all defect claims were to be waived except those identified through written notice provided by PvM to Dematic prior to expiration. Id. at 4–5. Final acceptance of the Module was to occur when Dematic finished its work under the

Agreement and testing was completed to PvM’s satisfaction. [Record No. 7 at 3] Final acceptance was an important part of the execution of the Agreement because it modified the remedies available to PvM. Before final acceptance, PvM had broad remedies and could unilaterally terminate the Agreement; however, after final acceptance, PvM’s “sole and exclusive” remedy was a warranty claim. [Record Nos. 8 at 4 and 7 at 4] The acceptance process included testing of the Module and criteria to determine whether it met performance

and operational standards outlined in the Agreement. [Record No. 1-1 at 51–54] Final acceptance also played a role in triggering the beginning of the warranty period. See id. at 4– 5, 8. The Agreement outlined the effect of a change order: “[u]nless expressly modified by a Change Order, . . . the provisions of the Agreement and these General Terms and Conditions will govern all work performed under such Change Order.” Id. at 88. The parties agreed upon four change orders between 2019 and 2021, and the final change order (“Change Order”) was executed by the parties in December 2021. Id. at 5. The Change Order deducted $165,988.42 from the total cost, and noted: In full consideration for the deduct amounts stated on this Order, the Parties agree: (1) Final Acceptance of the System was achieved on February 17, 2020, and (2) Each Party, on behalf of itself and its affiliated companies, hereby irrevocably and unconditionally release, acquit, and forever discharges the other Party and its affiliated, companies, successors and assigns from any and all known and unknown, foreseen and unforeseen, past or present claims, counterclaims, cross-claims, third-party claims, obligations, liabilities, damages, rights, losses, expenses, (including attorneys’ fees), costs, and/or causes of action of every kind or nature arising from or relating in any way to the Agreement. Id. at 116. Under the Agreement signed in October 2018, the Module was slated to be installed and through final acceptance in June 2019. Id. at 6. However, due to delays caused by Dematic and the COVID-19 pandemic, it still had not been installed by January 2020. Id. Despite this, Dematic invoiced PvM the ten percent retainer almost two years before PvM’s final acceptance of the Module. Id. The parties continued to address installation issues and disputed charges into October 2021 when Dematic proffered the Change Order. Id. PvM agreed to the Change Order two months later. Id. The Change Order stipulated that final acceptance occurred on February 17, 2020, and contained the above release language. Id. at 116. That final acceptance triggered the two-year warranty, which would end in February 2022. Although PvM continued to have problems with performance and safety of the Module, the parties continued to work toward a resolution. Id. at 7. However, the parties’ relationship changed in late summer 2022 when Dematic stopped responding to PvM. Id. Dematic did not solve or remedy the Module’s problems under the warranty but, instead, offered to send its representatives to train PvM’s staff at PvM’s expense. Id. PvM brought this action alleging three claims against Dematic: (1) breach of warranty (Count I), (2) unjust enrichment (Count II), (3) fraudulent misrepresentation (Count III). Dematic moved to dismiss all three counts. II. Legal Standard

To survive a motion to dismiss, a complaint must “contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible upon its face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 570 (2007)). While the Court need not accept legal conclusions or unwarranted factual inferences, the allegations in a complaint must be accepted as true and all reasonable inferences must be construed in the plaintiff’s favor. Bassett v. Nat’l Collegiate Athletic Ass’n, 528 F.3d 426, 430 (6th Cir. 2008). However, the Court will dismiss a complaint if the factual allegations are

insufficient “to raise a right to relief above the speculative level.” Twombly, 550 U.S. at 555. Courts are generally limited to considering the pleadings, but they may consider certain items without converting the motion to one for summary judgment such as public records, exhibits attached to the complaint, and those attached to the motion to dismiss “so long as they are referred to in the complaint and are central to the claims contained therein.” Bassett, 528 F.3d at 430.

III. Analysis “Contract interpretation, including determining whether a contract is ambiguous, is a question of law for the courts[.]” Butt v. Indep. Club Venture, Ltd., 453 S.W.3d 189, 192 (Ky. Ct. App. 2014) (citing Morganfield Nat'l Bank v. Damien Elder & Sons, 836 S.W.2d 893, 895 (Ky. 1992)). An ambiguous contract is one that a reasonable person would find “‘susceptible to different or inconsistent interpretations.’” Marshall v. Kentucky Farm Bureau Mut. Ins. Co., 618 S.W.3d 499, 502 (Ky. Ct. App. 2020) (quoting Cantrell Supply, Inc. v. Liberty Mutual Ins. Co., 94 S.W.3d 381, 385 (Ky. Ct. App. 2002)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Wysocki v. International Business MacHine Corp.
607 F.3d 1102 (Sixth Circuit, 2010)
Bassett v. National Collegiate Athletic Ass'n
528 F.3d 426 (Sixth Circuit, 2008)
Frear v. P.T.A. Industries, Inc.
103 S.W.3d 99 (Kentucky Supreme Court, 2003)
Ohio Casualty Insurance Co. v. Ruschell
834 S.W.2d 166 (Kentucky Supreme Court, 1992)
O'BRYAN v. Massey-Ferguson, Inc.
413 S.W.2d 891 (Court of Appeals of Kentucky (pre-1976), 1966)
Whitlow v. Whitlow
267 S.W.2d 739 (Court of Appeals of Kentucky (pre-1976), 1954)
Morganfield National Bank v. Damien Elder & Sons
836 S.W.2d 893 (Kentucky Supreme Court, 1992)
City of Louisa v. Newland
705 S.W.2d 916 (Kentucky Supreme Court, 1986)
Cantrell Supply, Inc. v. Liberty Mutual Insurance Co.
94 S.W.3d 381 (Court of Appeals of Kentucky, 2002)
Humana, Inc. v. Blose
247 S.W.3d 892 (Kentucky Supreme Court, 2008)
Butt v. Independence Club Venture, Ltd.
453 S.W.3d 189 (Court of Appeals of Kentucky, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Perfetti Van Melle USA Inc. v. Dematic Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/perfetti-van-melle-usa-inc-v-dematic-corp-kyed-2025.