Perfetti Van Melle USA, Inc. v. Dematic Corp.

CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 20, 2026
Docket25-5399
StatusUnpublished

This text of Perfetti Van Melle USA, Inc. v. Dematic Corp. (Perfetti Van Melle USA, Inc. v. Dematic Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perfetti Van Melle USA, Inc. v. Dematic Corp., (6th Cir. 2026).

Opinion

NOT RECOMMENDED FOR PUBLICATION File Name: 26a0094n.06

No. 25-5399

UNITED STATES COURT OF APPEALS FILED FOR THE SIXTH CIRCUIT Feb 20, 2026 KELLY L. STEPHENS, Clerk

) PERFETTI VAN MELLE USA, INC., ) Plaintiff-Appellant, ) ON APPEAL FROM THE ) UNITED STATES DISTRICT v. ) COURT FOR THE EASTERN ) DISTRICT OF KENTUCKY DEMATIC CORP., ) Defendant-Appellee. ) OPINION ) )

Before: MOORE, CLAY, and WHITE, Circuit Judges.

WHITE, J., delivered the opinion of the court in which MOORE, J., concurred. CLAY, J. (pp. 19–23), delivered a separate opinion concurring in part and dissenting in part.

HELENE N. WHITE, Circuit Judge. Plaintiff-Appellant Perfetti Van Melle USA, Inc.

(“PvM”) appeals the dismissal of its claims against Defendant-Appellee Dematic Corp.

(“Dematic”) based on a release executed by the parties. Because we conclude that it is unclear

whether the release covers certain of PvM’s claims, we REVERSE and REMAND.

I. Facts

In October 2018, PvM, which manufactures and distributes confectionary and chewing

gum, contracted with Dematic, an engineering firm, for Dematic to design and install a custom

Mass Put Module (the “Module”) in PvM’s warehouse to build, process, and move pallets more

effectively. The contract governing the relationship (the “Contract”), labeled Proposal 140501,

specified a payment and installation schedule, warranty provisions, the process and significance No. 25-5399, Perfetti van Melle v. Dematic

of final acceptance, and the effect of subsequent change orders. The Contract is governed by

Kentucky law.

Under the Contract, PvM was to pay Dematic $1,798,324.00 in installments tied to specific

progress points and particular milestones, with completion intended for June 2019.1 The final

payment, a ten-percent retainer, was due thirty days after final acceptance of the Module. “Final

Acceptance,” as defined in the Contract, occurs when Dematic completes its work and both

physical and functional testing has been conducted to PvM’s satisfaction.2 R. 1-1, PID 58. In

addition to triggering the final payment, Final Acceptance modifies the rights and remedies

available to PvM. “Prior to Acceptance,” PvM retains broad remedies, including the right to

declare a default and, if not timely cured, to “terminate the Agreement” and pay Dematic only the

reasonable value of the goods and services so far provided. Id. at PID 92–93. “After Acceptance,”

however, PvM’s “sole and exclusive remedies” for claims “related to the Agreement or the Goods

or Services” are those set forth in the Contract’s warranty provision. Id. at PID 93.

Pursuant to the warranty, “on the date of the start of the [w]arranty [p]eriod,” goods are to

be delivered “free from defects in material and workmanship” and services are to be “performed

in a professional and workmanlike manner.” Id. at PID 91.3 Failure to conform to these standards

constitutes a warranty defect. The warranty period is measured from the “invoice date of the

retainer fee” and, therefore, follows the date of Final Acceptance. Id. If a warranty defect occurs

1 After the Contract was executed, the parties agreed to changes that increased the total price to $2,026,807.10. PvM alleges that it has paid Dematic $2,030,067.47. 2 Physical Acceptance Testing includes a “walk-through” of the Module by both PvM and Dematic personnel to “verify that the physical equipment is complete and installed per the final drawings and specifications.” R. 1-1, PID 56. Functional Acceptance Testing entails various operational tests to “verify proper function of the [Module] in accordance with the requirements defined in th[e] [Agreement] . . .” Id. at PID 57. 3 The parties initially contracted for a one-year warranty period but added a second-year.

-2- No. 25-5399, Perfetti van Melle v. Dematic

during this period, Dematic must repair or replace the defective goods or re-perform services not

properly performed. If Dematic fails to do so, PvM may rely on a third-party and hold Dematic

liable for related costs.

The Contract additionally provides that the parties “may agree at any time prior to final

payment” to “make additions, deletions, or other revisions by Change Order . . . without

invalidating the Agreement.” Id. at PID 92. “Unless expressly modified by a Change Order” the

Contract’s provisions “will govern all work performed under such Change Order.” Id.

PvM alleges that after the Contract was executed and Dematic invoiced PvM for the initial

down payment, the Module project experienced significant delays that “continued well past 2019”

due to Dematic’s non-performance and the COVID-19 pandemic. Id. at PID 10. In January 2020,

and although the Module’s installation was not yet complete and Final Acceptance had not yet

occurred, Dematic invoiced PvM for the ten-percent retainer. The parties continued to address

installation problems and disputed charges through October 2021.

At that point, Dematic suggested that the parties resolve their issues through a proposed

Change Order dated October 17, 2021. That document is titled “Agreement” in bold, with the

words “Change Order” directly below in a smaller font and normal typeface. Id. at PID 120. The

blank space for “Agreement No.” is filled in with “140501” and the “Change Order No.” blank

space is filled with “4.” Id. The document then states that “[t]he following change(s) are to be

made to the Agreement identified above: Change Order 4 – Reduce Contract value:” Id. Several

invoices are then identified as well as charge reductions related to items in dispute, including a

“[w]arranty TO [‘turnover’],” “[f]reight,” and “[e]lectrical [p]ower drops and [f]loor shims.” Id.

In total, the Change Order deducted $165,988.42 from the total contract price and listed the new

“Revised Agreement Total” as $1,860,818.68. Id.

-3- No. 25-5399, Perfetti van Melle v. Dematic

Directly following the table listing the specific billing adjustments, the document states:

In full consideration for the deduct amounts stated on this Order, the Parties agree: (1) Final Acceptance of the System was achieved on February 17, 2020, and (2) Each Party, on behalf of itself and its affiliated companies, hereby irrevocably and unconditionally release, acquit, and forever discharges the other Party and its affiliated, companies, successors, and assigns from any and all known and unknown, foreseen and unforeseen, past or present claims, counterclaims, cross-claims, third-party claims, obligations, liabilities, damages, rights, losses, expenses (including attorneys’ fees), costs, and/or causes of action of every kind or nature arising from or relating in any way to the Agreement.

Id. (release provision hereafter referred to as the “Release”). PvM executed the document on

December 15, 2021, triggering its obligation to pay the ten-percent retainer. With acceptance

achieved on February 17, 2020, the warranty was set to end on February 17, 2022.4

Notwithstanding the Change Order, the Module’s performance and safety issues continued.

PvM identified several significant failures that it brought to Dematic’s attention “throughout 2021

and into early 2022.” Id. at PID 11. And although the parties met in early 2022 to work towards

a resolution, by late summer 2022, Dematic stopped responding to PvM.

II. Procedural History

In 2024, PvM brought this action against Dematic in Kentucky state court, alleging breach

of warranty, unjust enrichment, and fraudulent misrepresentation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Jones v. Bock
549 U.S. 199 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Raymond Pfeil v. State Street Bank and Trust Co
671 F.3d 585 (Sixth Circuit, 2012)
Vicki Marsh v. Genentech Inc.
693 F.3d 546 (Sixth Circuit, 2012)
Regis Lutz v. Chesapeake Appalachia, L.L.C.
717 F.3d 459 (Sixth Circuit, 2013)
Sherman v. American Water Heater Co., Inc.
50 S.W.3d 455 (Court of Appeals of Tennessee, 2001)
Hensley Manufacturing, Inc. v. Propride, Inc.
579 F.3d 603 (Sixth Circuit, 2009)
Frear v. P.T.A. Industries, Inc.
103 S.W.3d 99 (Kentucky Supreme Court, 2003)
United Parcel Service Co. v. Rickert
996 S.W.2d 464 (Kentucky Supreme Court, 1999)
Abney v. Nationwide Mutual Insurance Co.
215 S.W.3d 699 (Kentucky Supreme Court, 2007)
Barnes v. Community Trust Bank
121 S.W.3d 520 (Court of Appeals of Kentucky, 2003)
Cantrell Supply, Inc. v. Liberty Mutual Insurance Co.
94 S.W.3d 381 (Court of Appeals of Kentucky, 2002)
Codell Construction Co. v. Commonwealth
566 S.W.2d 161 (Court of Appeals of Kentucky, 1977)
Jones v. Sparks
297 S.W.3d 73 (Court of Appeals of Kentucky, 2009)
First Commonwealth Bank of Prestonsburg v. West
55 S.W.3d 829 (Court of Appeals of Kentucky, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Perfetti Van Melle USA, Inc. v. Dematic Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/perfetti-van-melle-usa-inc-v-dematic-corp-ca6-2026.