Peoples Gas Light & Coke Co. v. Joel Kennedy Construction Corp.

829 N.E.2d 866, 357 Ill. App. 3d 579, 293 Ill. Dec. 941, 2005 Ill. App. LEXIS 462
Appellate Court of Illinois·Decided May 16, 2005·No. 1-03-1449, 1-03-2799, 1-03-3718 cons.·Published·Cited by 2 cases

Opinion

PRESIDING JUSTICE CAHILL

delivered the opinion of the court:

We are asked to decide whether negligence and trespass claims that arise out of the Illinois Underground Utility Facilities Damage Prevention Act (Act) (220 ILCS 50/1 et seq. (West 1998)) are superseded by section 11 of the Act and subject to the two-year statute of limitations found in section 12 of the Act (220 ILCS 50/11, 12 (West 1998)). We conclude that the two-year statute of limitations applies only to the statutorily defined acts or omissions set out in section 11, and not the common law counts of negligence and trespass in the complaints before us. For the reasons that follow, we reverse the trial court’s dismissal of the complaints and remand for further proceedings.

This case comes to us as a consolidated appeal taken from three separate lawsuits filed by plaintiff, Peoples Gas Light and Coke Company, against defendants, Joel Kennedy Construction Corp. (Kennedy Construction), and G&V Construction Company, Inc. (G&V Construction). The trial court dismissed plaintiffs negligence and trespass claims in all three cases after finding them barred by the two-year statute of limitations found in section 12 of the Act. The allegations of all three complaints are virtually identical.

The first complaint was filed July 9, 2002, against Kennedy Construction. Count I of the complaint alleged that on August 18, 1998, Kennedy Construction trespassed on plaintiffs interest in land located at 6633 North Loron Avenue, in Chicago. Plaintiff had a possessory interest in the land for maintaining underground gas facilities. Plaintiff alleged Kennedy Construction damaged its underground gas facility while performing excavation work on the land. Count II alleged Kennedy Construction performed the excavation work in a negligent manner. Kennedy Construction moved to dismiss counts I and II of plaintiffs complaint under section 2 — 619(a)(5) of the Code of Civil Procedure (Code) (735 ILCS 5/2 — 619(a)(5) (West 1998)). Kennedy Construction argued plaintiffs claims arose under section 11 of the Act and are barred by the two-year statute of limitations found in section 12 of the Act (220 ILCS 50/11, 12 (West 1998)). The trial court agreed and dismissed counts I and II. The court later entered judgment for plaintiff on the remaining counts in plaintiffs complaint. Plaintiff appeals the dismissal of counts I and II under Supreme Court Rule 303 (155 Ill. 2d R. 303).

Plaintiff brought a second action against Kennedy Construction on July 15, 2002. Counts I and II of the complaint alleged trespass and negligence, respectively, arising from excavation work performed at 1234 North Lawndale Avenue, in Chicago, on August 20, 1999. The trial court dismissed these counts under section 2 — 619(a)(5) of the Code as barred by section 12 of the Act. The trial court entered a finding under Supreme Court Rule 304(a) (155 Ill. 2d R. 304(a)), and plaintiff appeals.

On May 9, 2003, plaintiff filed a similar complaint against G&V Construction. Counts I and II of plaintiffs complaint alleged negligence and trespass arising from excavation work performed at 1443 West 41st Street, in Chicago, on October 5, 2000. Counts V and VI of the complaint alleged negligence and trespass arising from excavation work performed at 3100 North Sheridan Road, in Chicago, on November 3, 1999. Counts I, II, V and VI were dismissed under section 2 — 619(a)(5) of the Code as barred by section 12 of the Act. Plaintiff appeals under Rule 304(a).

The question common to these appeals is whether plaintiffs negligence and trespass claims are superseded by section 11 of the Act and thereby subject to the two-year statute of limitations found in section 12 of the Act. Our review is de novo. See Borowiec v. Gateway 2000, Inc., 209 Ill. 2d 376, 413, 808 N.E.2d 957 (2004) (motions to dismiss under section 2 — 619 of the Code present questions of law and are reviewed de novo)-, People ex rel. Graf v. Village of Lake Bluff, 206 Ill. 2d 541, 549, 795 N.E.2d 281 (2002) (issues of statutory construction present questions of law and are reviewed de novo).

Section 12 of the Act reads: “[n]o action may he brought under Section 11 of this Act unless commenced within 2 years after the date of violation of this Act.” 220 ILCS 50/12 (West 1998). Section 11 of the Act reads in part:

“Every person who, while engaging in excavation or demolition, wilfully fails to comply with the Act by failing to provide the notice to the owners or operators of the underground facilities or CATS facility near the excavation or demolition area through the StateWide One-Call Notice System as required by Section 4 of this Act and damages any underground utility facilities or CATS facilities, shall be subject to a fine of no more than $200 for each separate offense and shall be liable for the damage caused to owners or operators of the facility.
Every person who, while engaging in excavation or demolition and has provided the notice to the owners or operators of the underground utility facilities or CATS facilities in and near the excavation or demolition area through the State-Wide One-Call Notice System as required by Section 4 of this Act but otherwise wilfully fails to comply with this Act and damages any underground utility facilities or CATS facilities, shall be subject to a fine of no more than $100 for each separate offense and shall be hable for the damage caused to the owners or operators of the facility.
Every person who, while engaging in excavation or demolition and has provided the notice to the owners or operators of the underground utility facilities or CATS facilities in and near the excavation or demolition area through the State-Wide One-Call Notice System as required by Section 4 of this Act but otherwise, while acting reasonably, damages any underground utility facilities or CATS facilities, shall not be subject to a fine but shall be hable for the damage caused to the owners or operators of the facility provided the underground utility facility or CATS facility is properly marked as provided in Section 10 of this Act.” (Emphasis added.) 220 ILCS 50/11 (West 1998).

The parties have made elaborate arguments concerning the applicability of section 11 to plaintiffs negligence and trespass claims. We do not address the plethora of arguments raised by the parties because we find the issue to be fairly straightforward.

Section 11 describes what will constitute sanctionable conduct under the Act. The first two paragraphs provide penalties for wilful violations of the Act. The third paragraph explains that a person who, “while acting reasonably” and in compliance with the Act, damages an underground utility facility will not be subject to a penalty but will be liable for the damage caused to the underground utility facility.

Free access — add to your briefcase to read the full text and ask questions with AI

Peoples Gas Light & Coke Co. v. Joel Kennedy Construction Corp., 829 N.E.2d 866, 357 Ill. App. 3d 579, 293 Ill. Dec. 941, 2005 Ill. App. LEXIS 462 (Ill. Ct. App. 2005).

829 N.E.2d 866 (Peoples Gas Light & Coke Co. v. Joel Kennedy Construction Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.