People's Counsel v. Public Service Commission

455 A.2d 391, 1982 D.C. App. LEXIS 497, 1982 WL 893114
District of Columbia Court of Appeals·Decided November 30, 1982·No. 79-1037, 79-1073·Published·Cited by 17 cases

Opinions

MACK, Associate Judge:

The Potomac Electric Power Company (hereinafter “Pepeo” or “the Company”) and the People’s Counsel appeal pursuant to D.C.Dode 1973, § 43-705, from an order of the Public Service Commission (hereinafter “PSC” or “the Commission”) which granted a rate increase to Pepeo for retail service in the District of Columbia in Formal Case No. 685. We reject petitioners’ claims and affirm the order of the Public Service Commission on all challenged grounds with the exception of the decision to exclude unam-ortized credit from termination of the Douglas Point plant project from Pepco’s rate base. We find that the Commission inadequately articulated the reasons for its decision to allocate all gains from the termination of this project to ratepayers and therefore remand this aspect of Formal Case No. 685 in order to allow the agency to clarify its rationale for this decision.

Procedural History

Pepeo filed an application for an increase in retail service rates for District of Columbia customers with the Public Service Commission on July 26,1977, designated Formal Case No. 685 by the Commission. As later [393]*393amended, the application requested a $44.8 million revenue increase based on 1977 test year data. Consumer interests were represented by the Office of People’s Counsel, statutory representative of utility consumers pursuant to D.C.Code 1978 Supp., § 43-205, and intervenor status was granted to several other parties who represented various interests. After conducting lengthy hearings and receiving a substantial volume of evidence from the various parties, the Commission concluded hearings and closed the record on May 2,1978.

Following the close of the record Pepeo sought extraordinary relief on several occasions. On December 6, 1978, this court denied a mandamus petition by which Pepeo sought to compel the PSC to issue a decision in Formal Case No. 685. On December 21, 1978, Pepeo applied to the Commission for a $19.8 million emergency interim rate increase pending the issuance of a final order in Case No. 685.

The Commission issued Proposed Opinion and Order No. 6096 on June 14, 1979 and invited the parties to file exceptions to the findings and conclusions therein. A day later the Commission issued Order No. 6098, granting Pepeo an emergency interim rate increase totalling $5,782,000. After reviewing the parties’ exceptions to Proposed Order No. 6096 the Commission issued Order No. 7000. Order No. 7000 essentially adopted the proposals outlined in Order No. 6096 and granted Pepeo a permanent rate increase of $5,890,000.

Both Pepeo and People’s Counsel filed Applications for Reconsideration of Order No. 7000. The Commission failed to rule on these filings within 30 days and, therefore, denied them by operation of law. Each party then filed a petition of appeal in this court. Pepeo was granted intervenor status in the People’s Counsel appeal but People’s Counsel’s motion to intervene in the Pepeo appeal was denied as untimely. On November 7, 1980, we granted the Public Service Commission’s motion to consolidate^the two appeals.

Issues Presented

The parties appeal the Commission’s order on several grounds, which we briefly enumerate here before proceeding to analyze each.

Pepeo alleges that the Commission acted arbitrarily and unreasonably in four respects and therefore set rates at levels so low as to be confiscatory. Pepeo challenges the Commission’s use of 1977 test year data to set rates in 1979, the reduction in the authorized rate of return on its common stock equity, a change in the accounting treatment of funds invested in plant construction, and, finally, the allocation of financial gains realized as a result of the termination of the Douglas Point nuclear power plant project.

People’s Counsel argues that the Commission erred in two respects: first, in using the 48% federal corporate tax rate in effect during the test year to determine revenue requirements rather than the 46% rate in effect in 1979 and second, in deciding to exclude accrued interest from cash working capital calculations.

Scope of Review

It is well established that the scope of this court’s review of Public Service Commission orders is very narrow. D.C.Code 1973, § 43-706. See Washington Gas Light Co. v. Public Service Commission, D.C.App., 450 A.2d 1187 (1982). It is the Commission, not this court, that must balance the competing interests of utility consumers and investors in the ratemaking process. People’s Counsel v. Public Service Commission, D.C.App., 399 A.2d 43 (1979). In our review of rate orders

[i]t is especially important to accord great respect to the Commission in a complex, esoteric area such as rate making in which the Commission has been entrusted with the difficult task of deciding among many competing arguments and policies. Our determination must focus on whether the result reached is arbitrary and appellant bears the burden of clearly demon[394]*394strating arbitrary action. He cannot meet this burden by advancing alternative techniques from which the Commission could have chosen. [Goodman v. Public Service Commission, 162 U.S.App.D.C. 74, 78-79, 497 F.2d 661, 665-66 (1974) (footnote and citations omitted).]

Petitioners each bear the heavy burden of showing a fatal flaw which renders the Commission’s findings and conclusions unreasonable, arbitrary and capricious, a burden not met by merely setting forth an acceptable alternative to Commission action. Goodman v. Public Service Commission, D.C.App., 309 A.2d 97, 101 (1973).

In reviewing this order our role is to determine whether the overall impact of the rate order is just and reasonable, People’s Counsel v. Public Service Commission, supra, and to ensure that the Commission “respected procedural requirements, ... made findings based on substantial evidence, and ... applied correct legal standards to its substantive deliberations.” Potomac Electric Power Co. v. Public Service Commission, D.C.App., 402 A.2d 14, 18 (en banc), cert. denied, 444 U.S. 926, 100 S.Ct. 265, 62 L.Ed.2d 182 (1979) (quoting Williams v. Washington Metropolitan Area Transit Commission, 134 U.S.App.D.C. 342, 362, 415 F.2d 922, 942 (1968)). See also Washington Gas Light Co., supra.

We now proceed to analyze the contested components of the Commission’s order, since “[i]n any analysis of whether an end result (i.e. the new rate) is not arbitrary, we are aware that ... the result is but the ‘sum of a number of components’ .... If each component or element is not arbitrary or capricious, the end result will be a sound one.” Goodman v. Public Service Commission, supra at 79, 497 F.2d at 666 (citations omitted).1

I.

Free access — add to your briefcase to read the full text and ask questions with AI

People's Counsel v. Public Service Commission, 455 A.2d 391, 1982 D.C. App. LEXIS 497, 1982 WL 893114 (D.C. 1982).

455 A.2d 391 (People's Counsel v. Public Service Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Potomac Electric Power Co. v. Public Service Commission of the District of Columbia
661 A.2d 131 (District of Columbia Court of Appeals, 1995)
Potomac Elec. v. Public Serv. Com'n
661 A.2d 131 (District of Columbia Court of Appeals, 1995)
Office of People's Counsel v. Public Service Commission
610 A.2d 240 (District of Columbia Court of Appeals, 1992)
Chesapeake & Potomac Telephone Co. v. Public Service Commission
514 A.2d 1159 (District of Columbia Court of Appeals, 1986)
Washington Metropolitan Area Transit Authority v. Public Service Commission
486 A.2d 682 (District of Columbia Court of Appeals, 1984)
Washington Gas Light Co. v. Public Service Commission
483 A.2d 1164 (District of Columbia Court of Appeals, 1984)
Office of the People's Counsel v. Public Service Commission of the District of Columbia
482 A.2d 404 (District of Columbia Court of Appeals, 1984)
People's Counsel of the District of Columbia v. Public Service Commission
472 A.2d 860 (District of Columbia Court of Appeals, 1984)
United States v. Pub. Serv. Com'n of Dist. of Columbia
465 A.2d 829 (District of Columbia Court of Appeals, 1983)
People's Counsel v. PUBLIC SERVICE COM'N
462 A.2d 1105 (District of Columbia Court of Appeals, 1983)
People's Counsel v. Public Service Commission
455 A.2d 402 (District of Columbia Court of Appeals, 1982)