People of Michigan v. Christopher Robert Clinton

CourtMichigan Court of Appeals
DecidedAugust 17, 2023
Docket361702
StatusUnpublished

This text of People of Michigan v. Christopher Robert Clinton (People of Michigan v. Christopher Robert Clinton) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
People of Michigan v. Christopher Robert Clinton, (Mich. Ct. App. 2023).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

PEOPLE OF THE STATE OF MICHIGAN, UNPUBLISHED August 17, 2023 Plaintiff-Appellee,

V No. 361702 Macomb Circuit Court CHRISTOPHER ROBERT CLINTON, LC No. 2019-001812-FH

Defendant-Appellant.

Before: O’BRIEN, P.J., and CAVANAGH and MARKEY, JJ.

PER CURIAM.

Defendant appeals as of right his bench-trial conviction of larceny by conversion of property with a value of $1,000 or more but less than $20,000, MCL 750.362; MCL 750.356(3)(a). We affirm.

I. BACKGROUND

The complainant, Ben Clowers, contracted with defendant to install an air-conditioning unit, a furnace, ductwork, and gas and water lines for a residential property that Clowers owned. The estimate for the project was $8,550, and Clowers paid a $5,500 deposit. Clowers alleged that defendant never delivered the equipment or performed any of the agreed-upon work, and failed to return the deposit.

The trial court held a bench trial on January 12, 2022, and February 23, 2022. Clowers testified that he and defendant agreed that the work would begin on August 27, 2018, and conclude on August 29, 2018. Despite Clowers and defendant exchanging frequent messages and telephone calls, the first activity on the project was not until August 29, 2018, when defendant and his employee installed an older air-conditioning unit in the building. Clowers testified that defendant’s employee was at the site on August 30, 2018, but sat in his vehicle and in the building, and did not have any equipment. Clowers stated that defendant’s assistant returned on August 31, 2018, and did not perform any of the contracted work. Clowers testified that, on September 1, 2018, defendant and his employee used a trenching machine to begin a trench for the water and gas lines, but had to stop because of inclement weather that collapsed some of the trench. Clowers continued that defendant’s employee resumed work on the trench the next day, but had to stop

-1- when he broke the building’s drain tile. He then began a second trench in an area that did not need a trench and broke the main sewer pipe.

Clowers testified that he contacted defendant on September 3, 2018, and directed him to cancel the project because of damage to the property, defendant not showing up to work, and a lack of honesty. Along with canceling the project, Clowers demanded either a refund or the equipment that should have been purchased with the deposit. Clowers testified that defendant stated that he would attempt to redeem the project, but Clowers was no longer interested.

Clowers testified that defendant arrived at the site on September 4, 2023, without the deposit or equipment. Clowers’ two brothers and mother were present when defendant arrived. Clowers stated that defendant promised to obtain and deliver the purchased equipment. Clowers testified that his foot was broken at the time, so one of his brothers offered to drive with defendant to pick up the equipment. Clowers stated that he was suspicious and followed them in his own vehicle. Clowers testified that instead of going to get the equipment, defendant drove to a police station, where both Clowers and defendant filed reports. Clowers testified that before leaving the police station, defendant told him that he would return to finish the job. Clowers stated that defendant arrived with the police the next day and collected his trenching machine, and promised to return to reimburse Clowers.

Clowers and defendant communicated on September 7, 2018, with defendant promising to bring the furnace and air conditioner, and again on September 10, with defendant promising to have the furnace delivered and installed. Clowers testified that defendant never delivered or installed a furnace, air-conditioning package, ductwork supply and return with registers, or any portion of his deposit money. Clowers stated that defendant returned to him only two pieces of ductwork and two plastic lines. About two weeks later, Clowers accessed the email link for the estimate and discovered defendant had added $6,000 to the original estimate. Clowers stated that the new estimates were for digging a trench for the electrician, replacing the main sewer, adding a water or gas line, and a 30-gallon power vent water heater, that were not a part of the original agreement. Clowers denied that he agreed to add any services to the original plan and asserted that defendant had never mentioned waiting for other services to be completed before he could work.

Defendant testified that he had been in the heating and cooling business for 20 years, and that he contracted with Clowers on August 26, 2018, to install a furnace, air conditioner, ductwork, and gas piping in Clowers’ building. Defendant testified that he had a “vague conversation” with Clowers as to when the project would be completed. Defendant testified that he was ready to begin work immediately, but Clowers’ builder had not sufficiently prepared the interior of the building. Defendant asserted that he informed Clowers that he could not proceed without the walls in place, and discussed a building plan with Clowers. Defendant stated that Clowers agreed to amend the contract to include a deeper dig with more expensive equipment so that defendant could add water piping, a water heater, and a main sewer to the gas piping. According to defendant, Clowers also wished for him to dig a trench for the electrical. Defendant stated that the contract price increased from $8,500 to $17,000. Defendant also referred a plumber to Clowers.

Defendant testified that he did not begin work on the project until August 29, 2018, because of complications with his other projects. On that date, defendant and his employee installed a temporary heating and cooling unit for the construction. Defendant also testified that he and his

-2- employee spent an entire Saturday on the job in order to complete digging trenches for utilities. Defendant testified that Clowers asked him how much the job was going to cost (including the work of the plumber, electrician and builder) and defendant replied that it could be up to $50,000 to $100,000. Defendant testified that when Clowers heard this, his attitude changed and “everything kind of just went south.” Defendant testified that Clowers informed him on September 3, 2018, that his employee had damaged a sewer pipe that the employee was supposed to remove, and that Clowers wished to cancel the job. Defendant stated that he instructed his employee to put the pipe back together, and told Clowers that he would return to the site on September 4, 2018, to fix any issues. Defendant testified that he arrived on the site on September 4, 2018, where Clowers struck him with a crutch, and Clowers’ family yelled at him to return the money, so he went to the police. He stated that the police assisted him in recovering the excavator and his other property. Defendant stated that he provided $6,800 of work in a temporary heating and cooling system, digging and installing support boards for the trench, gas and water piping and ductwork supplies on the site, building plans, and four days of his employee’s labor. Defendant stated that, because he believed that Clowers owed him $1,000, he did not return the $5,500 down payment to Clowers.

The trial court issued an opinion and order on March 17, 2022, stating that the evidence established that Clowers’ deposit was to be used to purchase a furnace, air-conditioning package, ductwork supply and return with registers, and a gas line. However, Clowers did not receive this equipment or a refund of his deposit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re WINSHIP
397 U.S. 358 (Supreme Court, 1970)
Barker v. Wingo
407 U.S. 514 (Supreme Court, 1972)
United States v. MacDonald
456 U.S. 1 (Supreme Court, 1982)
People v. Williams
716 N.W.2d 208 (Michigan Supreme Court, 2006)
People v. Hardiman
646 N.W.2d 158 (Michigan Supreme Court, 2002)
People v. Breck
584 N.W.2d 602 (Michigan Court of Appeals, 1998)
People v. O'Shea
385 N.W.2d 768 (Michigan Court of Appeals, 1986)
People v. Carines
597 N.W.2d 130 (Michigan Supreme Court, 1999)
People v. Wickham
503 N.W.2d 701 (Michigan Court of Appeals, 1993)
People v. Christenson
312 N.W.2d 618 (Michigan Supreme Court, 1981)
People v. Bayer
90 N.W.2d 656 (Michigan Supreme Court, 1958)
People v. Sierb
581 N.W.2d 219 (Michigan Supreme Court, 1998)
People v. Cain
605 N.W.2d 28 (Michigan Court of Appeals, 2000)
People v. Mason
634 N.W.2d 382 (Michigan Court of Appeals, 2001)
People v. Hampton
285 N.W.2d 284 (Michigan Supreme Court, 1979)
People v. Holtzer
660 N.W.2d 405 (Michigan Court of Appeals, 2003)
People v. Gistover
472 N.W.2d 27 (Michigan Court of Appeals, 1991)
People v. Smith-Anthony
837 N.W.2d 415 (Michigan Supreme Court, 2013)
People v. Gilmore
564 N.W.2d 158 (Michigan Court of Appeals, 1997)
People v. Ericksen
793 N.W.2d 120 (Michigan Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
People of Michigan v. Christopher Robert Clinton, Counsel Stack Legal Research, https://law.counselstack.com/opinion/people-of-michigan-v-christopher-robert-clinton-michctapp-2023.