People Ex Rel. Williams Engineering & Contracting Co. v. Metz

85 N.E. 1070, 193 N.Y. 148, 1908 N.Y. LEXIS 631
CourtNew York Court of Appeals
DecidedOctober 13, 1908
StatusPublished
Cited by35 cases

This text of 85 N.E. 1070 (People Ex Rel. Williams Engineering & Contracting Co. v. Metz) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
People Ex Rel. Williams Engineering & Contracting Co. v. Metz, 85 N.E. 1070, 193 N.Y. 148, 1908 N.Y. LEXIS 631 (N.Y. 1908).

Opinion

Vann, J.

This proceeding was initiated by an order made at a Special Term of the Supreme Court, requiring the comptroller of the city of Flew York to show cause why he should not bé required to pay to the relator the sum of $9,634.75, as well as the further sum of $4,545.37, each being a partial payment upon a contract to complete the storm relief sewer in the borough of the Bronx. The facts were undisputed. It appeared that a prior contract, dated March 6th, 1906, had been made by one Flanagan to construct said sewer at unit prices estimated to amount to. the sum of $635,844.36. After Mr. Flanagan had been paid $310,718.35 for partial performance of said contract it was declared abandoned by the city under a provision thereof authorizing such action in certain cases, and on the 6th of .November, 1907, a new contract was made with the relator, as the lowest bidder after due advertisement, to complete the sewer for the lump sum of $428,831.50. Thereupon the relator entered upon the performance of its contract, and the sums mentioned in the order to show cause are respectively 85 per cent of the earliest amounts eaimed thereunder. They were payable as *153 soon as earned and were the only sums that had been earned when this proceeding was commenced.

Payment was refused by the comptroller upon the ground that the relator had violated a statute known as the Labor Law, in that it allowed its workmen to work more than eight hours a day when there was no extraordinary emergency and had failed to pay wages at the rate prevailing in the locality where the work was done. Both of these specifications were supported by proof and neither was denied by the relator. No explanation was given and no excuse presented. The relator, however, sought to justify its position on the grounds, first, that the Labor Law did not apply to the contract in question, because it was a continuation of that made with Flanagan before the Labor Law was passed ; second, that the Labor Law is unconstitutional. The comptroller admitted the allegations of the relator that it had performed the work and earned the compensation claimed, but resisted payment solely upon the grounds mentioned.

The court at Special Term granted a writ of peremptory mandamus commanding the comptroller to pay the sums claimed by the relator, and upon appeal to the Appellate Division the order was affirmed. Two of the justices, however, dissented upon the ground that the Labor Law is constitutional and absolutely prohibits payment on the facts disclosed by the record.

The first ground upon which the comptroller resisted payment merits little attention. Whatever the rights of Flanagan, the first contractor, or his sureties may be as against the city, as to the relator the new contract is independent of the old and stands the same as if no other had been made. The relator sustains no relation to Flanagan or his sureties that is recognized by law. It is entitled to nothing for what he did and is responsible for no default of his. The old contract may be of importance to the old contractor in his relation to the city, but it is of no concern to the new contractor in its relations to the city. The contract of the relator is with the city alone and the old contract is referred to in the new only *154 to measure the work to be done thereunder. The relator agreed to do the work thus described and the city agreed to pay a fixed price therefor. The work has been partly done according to the contract and partial payment must be made as agreed unless the Labor Law now in force, which was passed after the date of the first contract and before the date of the second, intervenes and prevents. The only question, therefore, worthy of extended discussion, is whether that statute, is valid in so far as it regulates wages and hours of labor on public work.

The first Labor Law was passed in 1897, was twice amended in 1899 and once in 1900. (L. 1897, ch. 415 ; L. 1899, chs. 192 and 567; L. 1900, ch. 298.) In 1901 it was adjudged unconstitutional according to the Constitution as it then stood, first, because it required the expenditure of money of the city or that of the local property owners for other than city purposes; second, because it invaded rights of liberty and property in that it denied to the city and the contractor the right to agree with their employees upon the measure of their compensation. (People ex rel. Rodgers v. Coler, 166 N. Y. 1; People ex rel. Treat v. Coler, 166 N. Y. 144.)

After these adjudications and owing thereto the Constitution was amended for the purpose, as contemporary history and discussion in the legislature show, of authorizing such legislation. Prior to the amendment section one of article twelve was as follows: It shall be the duty of the Legislature to provide for the organization of cities and incorporated villages, and to restrict their power of taxation, assessment, borrowing money, contracting debts, and loaning their credit, so as to prevent abuses in assessments and in contracting debt by such municipal corporations.” By concurrent resolutions passed by the senate and assembly in 1902 and 1903 an amendment to said section was proposed, which was adopted by the People in 1905 and took effect on the first of January, 1906. (L. 1903, vol. 2, p. 1453.) That amendment added to the section as it previously stood the following: and the Legislature may regulate and fix the wages or salaries, the hours of *155 work or labor, and make provision for the protection, welfare and safety of persons employed by the State or by any county, city, town, village or other civil division of the State, or by any contractor or sub-contractor performing work, labor or services for the State, or for any county, city, town, village or other civil division thereof.”

In 1906, acting under the authority of this amendment, the legislature promptly re-enacted the material part of the statute which had been declared unconstitutional. (L. 1906, ch. 506.) After referring to section three of that statute and reciting that the same “ or a part thereof was heretofore declared unconstitutional by the Court of Appeals,” it proceeded to re-enact said section in every substantial particular. The first sentence is as follows: “ Eight hours shall constitute a legal day’s work for all classes of employees in this State except those engaged in farm and domestic service unless otherwise provided by law.” After thus fixing the number of hours which constitute a legal day’s work in the absence of any agreement upon the subject, the legislature continued : “This section does not prevent an agreement for overwork at an increased compensation except upon work by or for the State or a municipal corporation, or by contractors or sub-contractors therewith. Each contract to which the State or a municipal corporation is a party which may involve the employment of laborers, workmen or mechanics shall contain a stipulation that no laborer, workman or mechanic in the employ of the contractor, sub-contractor or other person doing or contracting to do the whole or a part of the work contemplated by the contract shall be permitted or required to work more than eight hours in any one calendar day except in cases of extraordinary emergency caused by fire, flood or danger to life or property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walton v. Comfort Systems
Second Circuit, 2025
Mirabile v. City of Saratoga Springs
67 A.D.3d 1178 (Appellate Division of the Supreme Court of New York, 2009)
New York Charter Schools Ass'n v. DiNapoli
20 Misc. 3d 235 (New York Supreme Court, 2008)
Alacqua v. Baudanza
110 Misc. 2d 774 (Civil Court of the City of New York, 1981)
Flushing National Bank v. Municipal Assistance Corp.
358 N.E.2d 848 (New York Court of Appeals, 1976)
People v. Poveromo
71 Misc. 2d 524 (Suffolk County District Court, 1972)
Garlin v. Murphy
51 Misc. 2d 477 (New York Supreme Court, 1966)
Dutcher v. Hatch
19 A.D.2d 341 (Appellate Division of the Supreme Court of New York, 1963)
City of Buffalo v. Lawley
6 A.D.2d 66 (Appellate Division of the Supreme Court of New York, 1958)
Burke v. Clark
87 Pa. D. & C. 329 (Philadelphia County Court of Common Pleas, 1952)
Chambers v. Owens-Ames-Kimball Co.
62 N.E.2d 496 (Ohio Court of Appeals, 1945)
Mallary, Inc. v. City of New Rochelle
184 Misc. 66 (New York Supreme Court, 1944)
Lapolla v. Board of Education
172 Misc. 364 (New York Supreme Court, 1939)
Anglo-American Direct Tea Trading Co. v. Commissioner
38 B.T.A. 711 (Board of Tax Appeals, 1938)
Bevard v. Baughman
173 A. 40 (Court of Appeals of Maryland, 1934)
City of Vincennes v. Marland Refining Co.
33 F.2d 427 (Seventh Circuit, 1929)
Bareham v. City of Rochester
221 A.D. 36 (Appellate Division of the Supreme Court of New York, 1927)
Campbell v. City of New York
155 N.E. 628 (New York Court of Appeals, 1927)
Morse v. Delaney
128 Misc. 317 (New York Supreme Court, 1926)
Davy v. McNeill
240 P. 482 (New Mexico Supreme Court, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
85 N.E. 1070, 193 N.Y. 148, 1908 N.Y. LEXIS 631, Counsel Stack Legal Research, https://law.counselstack.com/opinion/people-ex-rel-williams-engineering-contracting-co-v-metz-ny-1908.