Penthouse Media Group, Inc. v. Pachulski Stang Ziehl & Jones LLP

406 B.R. 453, 2009 U.S. Dist. LEXIS 46617, 2009 WL 1542556
CourtDistrict Court, S.D. New York
DecidedJune 2, 2009
Docket09 Civ. 85(SAS)
StatusPublished
Cited by9 cases

This text of 406 B.R. 453 (Penthouse Media Group, Inc. v. Pachulski Stang Ziehl & Jones LLP) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Penthouse Media Group, Inc. v. Pachulski Stang Ziehl & Jones LLP, 406 B.R. 453, 2009 U.S. Dist. LEXIS 46617, 2009 WL 1542556 (S.D.N.Y. 2009).

Opinion

OPINION AND ORDER

SHIRAA. SCHEINDLIN, District Judge.

Third Party Plaintiff Penthouse Media Group, Inc. (“PMG”) appeals an Order of the United States Bankruptcy Court for the Southern District of New York dated December 11, 2008 (the “Order”). In that Order, Chief Judge Stuart M. Bernstein granted summary judgment in favor of Third Party Defendant Pachulski Stang Ziehl & Jones LLP (“Pachulski”) and dismissed PMG’s complaint for professional malpractice. For the following reasons, the Order of the bankruptcy court is reversed.

I. BACKGROUND 1

A. The Bankruptcy Plan

In August 2003-in a case titled In re General Media, Inc.—PMG’s predecessors-in-interest, General Media, Inc. and various affiliates (together, “the Debtor”), filed voluntary petitions for relief under Chapter 11 of the Bankruptcy Code. 2 In September 2003, Pachulski was retained by the Debtor to assist in the formulation of their Chapter 11 Bankruptcy Plan. 3 In August 2004, the Fourth Amended Plan of Reorganization (the “Plan”) was completed and confirmed. 4 According to Section 7.1.1 of the Plan, notice of the general rejection bar date (“Rejection Claims Bar Date”)-which should have been applicable to then-employee Jane Homlish Krynicki’s employment contract was to have been served on each party to an executory contract. 5 In October 2004, PMG was still unaware that Pachulski had failed to serve the requisite notice on Krynicki and establish a bar date for claims related to the terminations of Debtor’s rejected severance plans pursuant to Section 7.3 of the Plan. 6

*456 B. Pachulski’s Final Fee Application

In early October 2004, PMG terminated Krynicki’s employment. 7 Later that same month, Krynicki’s lawyer contacted PMG and demanded payment of severance. 8

On October 22, Pachulski served and filed its final fee application for services rendered to the Debtor. 9 On November 30, Judge Bernstein held a hearing on Pachulski’s fee application. 10 PMG did not oppose the application, and it was approved by the bankruptcy court on that day. 11 Pachulski continued to serve as PMG’s lawyer in the winding down of the bankruptcy proceeding until September 2005 when it withdrew as counsel to PMG. 12 PMG had also retained the Berk-man firm for assistance in its bankruptcy proceedings and other matters. 13

C. Krynicki’s Lawsuit and PMG’s Third Party Complaint

On February 2, 2005, Krynicki filed her Complaint against PMG and others seeking severance benefits. 14 After the Complaint was filed, PMG repeatedly received assurances from Pachulski that Krynicki had been properly served with notice. 15 Krynicki filed an Amended Complaint on February 6, 2007, asserting, inter alia, a claim for breach of contract. 16 On defendants’ motion to dismiss, Judge Bernstein held that Krynicki had adequately stated a claim for breach of her employment agreement, noting that neither the Rejection Claims Bar Date nor any other bar date applied to Krynicki’s severance pay claim. 17

On July 9, 2007, PMG filed a third-party complaint to implead Pachulski. 18 PMG *457 alleged three causes of action: (1) negligence, (2) breach of fiduciary duty, and (3) professional malpractice. 19 The court subsequently dismissed the negligence and breach of fiduciary duty claims, leaving the malpractice claim in contention. 20

D. PMG’s Third Party Complaint

On October 20, 2008, Pachulski filed a motion for summary judgment, arguing that PMG’s malpractice claim is barred by the doctrines of res judicata and collateral estoppel based on the bankruptcy court’s prior approval of its final fee application. 21 On December 11, 2008, the bankruptcy court granted summary judgment in favor of Pachulski. 22

In the December 11, 2008 Order, Judge Bernstein ruled that res judicata applied to bar PMG’s malpractice claim. 23 In so doing, the bankruptcy court relied heavily on the Western District of New York decision in D.A. Elia Construction Corp. v. Damon & Morey, LLP. 24 Judge Bernstein held that the court’s approval of the fee application was a final order, that the bankruptcy court had jurisdiction to issue such approval, and that PMG and Pachul-ski were identical to the parties in the previous proceeding because PMG was a party-in-interest to the fee application. 25 He also ruled that the causes of action were the same because both the fee application and the malpractice claim “ ‘require a finding as to the nature and the quality of the professional services, and thus, the core of operative facts or central factual question is the same.’ ” 26 Key to the decision was the bankruptcy court’s finding that PMG “should have known of the facts [giving] rise to the malpractice claim” by the time of the fee application hearing. 27 PMG now appeals the grant of summary judgment to Pachulski.

II. LEGAL STANDARD
A. Bankruptcy Appeals

District courts are vested with appellate jurisdiction over bankruptcy courts. 28 Final orders of the bankruptcy court may be appealed to the district court as of right. 29 An order is final if “ ‘Mottling in the order ... indicates any anticipation that the decision will be reconsidered.’ ” 30 A grant of summary judgment is reviewed de novo by the appellate court. 31

*458 B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re: AMC Investors, LLC
D. Delaware, 2024
AMC Investors, LLC
D. Delaware, 2022
AMC Investors II, LLC
D. Delaware, 2022
Source Enterprises, Inc. v. Windels Marx Lane & Mittendorf, LLP
83 A.D.3d 556 (Appellate Division of the Supreme Court of New York, 2011)
Breslin Realty Development Corp. v. Shaw
72 A.D.3d 258 (Appellate Division of the Supreme Court of New York, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
406 B.R. 453, 2009 U.S. Dist. LEXIS 46617, 2009 WL 1542556, Counsel Stack Legal Research, https://law.counselstack.com/opinion/penthouse-media-group-inc-v-pachulski-stang-ziehl-jones-llp-nysd-2009.