Pennsylvania, Steel Co. v. Nace

77 A. 1121, 113 Md. 460, 1910 Md. LEXIS 76
Court of Appeals of Maryland·Decided June 23, 1910·Published·Cited by 14 cases

Opinion

Thomas, J.,

delivered the opinion of the Court.

The Washington and Berkeley Bridge Company, a West Virginia corporation, proposing to build a toll bridge across the Potomac river, at Williamsport, between Berkeley County, West Virginia, and Washington County, Maryland, of sufficient size and strength to sustain a track for trolley cars or other cars to be operated by electricity* steam or other power, and to provide ample room for vehicles and pedestrians, in July, 1907, entered into a contract with Mason D. Pratt, _a civil engineer, whereby he was to make all necessary surveys for the location of the bridge, and proper plans and specifications for the same; supervise the construction of the bridge and' see that the terms of contract with contractors were' “properly and fully carried out,” and in all such matters act as “the company’s agent and representative.” The contract further provided “that in- all transactions the said engineer shall and will fully realize and so *468 act and serve the said company in every way that will insure and subserve its best interest, and that his sole object and purpose will be to serve the company solely and absolutely.”

On the 6th of August, 1908, the Bridge Company contracted with the Elmore and Hamilton Contracting Company for the erection of the concrete piers and abutments of the bridge, in accordance with plans and specifications annexed, to be completed within four months from the date of the contract, which specified that “The decision of the engineer (of the Bridge Company), shall control as to the interpretation of the drawings and specifications during the execution of the work under them,” and on the tenth of August, the Bridge Company entered into a contract with the appellant, the Pennsylvania Steel Company of Philadelphia, a corporation, in which the appellant agreed to “fabricate, deliver, erect and paint sixteen plate girder spans for the above bridge, on piers provided by the (Bridge) Company, including the steel stringers to support a trolley track,” according to specifications annexed, and to “fully finish and complete the same within one month after the completion of the piers and abutments.” This contract also provided that the decision of the “Engineer shall control as to the interpretation of the drawings and specifications during the execution of the work under them,” and the -specifications stated: “the piers are to be built under a separate contract- and will be of concrete, and it is expected that they will be ready for the bridge contractor to begin placing girders not later than November 1st.”

The Elmore and Hamilton Contracting Company began the construction of the piers and abutments about the 1st of September, 1908, and the last pier, pier ten, was completed on the ninth of December. The erection of the steel and ironwork was commenced by the appellant on the 17th of November, 1908. The piers were about one hundred feet apart, and the.steel superstructure of each span consisted of ■two large steel girders, each weighing about ten tons, ex *469 tending front ¡tier to pier, and placed on concrete pedestals on top of the piers, seven floor beams and twelve eye beams, weighing in the aggregate about sixteen and one-half tons. On these floor beams was constructed a railroad track, on which the girders and beams were transported' from the shore to each span as completed for use in the further construction, and on top of the girders was placed a traveling crane or derrick, called a “traveler,” weighing about forty tons and employed in lifting and extending the girders to the next span. The span between piers nine and ten was completed on the 15th of December, and on the 16th of December, while the employees of the appellant, including the appellee, were engaged in erecting the span between piers ten and eleven, pier ten gave way and the steel superstructure between piers nine and ten and the traveler were precipitated into the river, and the appellee sustained the injuries for which this suit was brought.

During the trial, which resulted in a judgment and verdict for the plaintiff, the defendant reserved twenty-two exceptions to the rulings of the Court on the evidence. At the conclusion of the testimony the plaintiff offered two prayers and the defendant seventeen, and the twenty-third exception is to the overruling of defendant’s special exception to plaintiff’s first prayer as modified, to the granting of plaintiff’s first prayer as modified and plaintiff’s second’ prayer, and to the modification of defendant’s fifteenth prayer, and the rejection of defendant’s first, second, third, fifth, sixth, seveirth, eighth, ninth, tenth, eleventh, thirteenth, sixteenth and seventeenth prayers. As the defendant’s first prayer asked the Court to instruct the jury that under the pleadings there was no legally sufficient evidence to entitle the plaintiff to recover, it is necessary to examine the declaration and to consider the evidence somewhat in detail.

Free access — add to your briefcase to read the full text and ask questions with AI

Pennsylvania, Steel Co. v. Nace, 77 A. 1121, 113 Md. 460, 1910 Md. LEXIS 76 (Md. 1910).

77 A. 1121 (Pennsylvania, Steel Co. v. Nace) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hastings v. Mechalske
650 A.2d 274 (Court of Appeals of Maryland, 1994)
Athas v. Hill
476 A.2d 710 (Court of Appeals of Maryland, 1984)
Athas v. Hill
458 A.2d 859 (Court of Special Appeals of Maryland, 1983)
Farley v. Yerman
190 A.2d 773 (Court of Appeals of Maryland, 1963)
Empire State Insurance Co. of Watertown v. Guerriero
69 A.2d 259 (Court of Appeals of Maryland, 1949)
Virginia Dare Stores, Inc. v. Schuman
1 A.2d 897 (Court of Appeals of Maryland, 1938)
Schlueter v. East St. Louis Connecting Railway Co.
296 S.W. 105 (Supreme Court of Missouri, 1927)
Jarka Company v. Gancl
131 A. 754 (Court of Appeals of Maryland, 1926)
Arnold v. Graham
272 S.W. 90 (Missouri Court of Appeals, 1925)
Ford v. Rock Island Ry. Co.
217 S.W. 294 (Supreme Court of Missouri, 1919)
Bartlett-Hayward Co. v. State Ex Rel. Smith
87 A. 499 (Court of Appeals of Maryland, 1913)
Frizzell v. Sullivan
83 A. 651 (Court of Appeals of Maryland, 1912)
Balto. and Ohio R.R. Co. v. Wilson
83 A. 248 (Court of Appeals of Maryland, 1912)
Baltimore & Ohio Railroad v. Wilson
117 Md. 198 (Court of Appeals of Maryland, 1912)