Pennsylvania Railroad Company v. SS Marie Leonhardt

202 F. Supp. 368, 1962 U.S. Dist. LEXIS 4720
CourtDistrict Court, E.D. Pennsylvania
DecidedJanuary 30, 1962
Docket13 of 1959
StatusPublished
Cited by26 cases

This text of 202 F. Supp. 368 (Pennsylvania Railroad Company v. SS Marie Leonhardt) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennsylvania Railroad Company v. SS Marie Leonhardt, 202 F. Supp. 368, 1962 U.S. Dist. LEXIS 4720 (E.D. Pa. 1962).

Opinion

*370 CALEB M. WRIGHT, District Judge.

Libel in rem filed by the Pennsylvania Railroad against the S. S. Marie Leonhardt. Answer and cross-libel in person-am filed against the Railroad by Leonhardt & Blumberg, claimant and owner of the vessel. Each party avers that the other was solely at fault in causing the vessel to collide with the Delair drawbridge on the Delaware River, which is operated and maintained by the libellant Railroad. The libel alleges negligent and improper navigation of the vessel as it approached the bridge; the answer and cross-libel deny negligence in the navigation of the vessel, alleging the collision to be solely attributable to the negligent operation of the drawbridge by the Railroad and its agents. Both libel and cross-libel contain appropriate prayers for damages suffered as a result of the collision. Jurisdiction to entertain the cause is conferred by 46 U.S.C. A. § 740.

Shortly after 11:30 a. m. on January 9, 1959, the Marie Leonhardt departed from Pier 122, South, on the Delaware River at Philadelphia with a cargo of bulk iron ore and proceeded upriver towards her destination at the Fairless Steel Works at Morrisville, Pa. 1 Her draft was 23'-6" even keel. 2 Present on the navigating bridge of the vessel were Pilot Rutherford, the ship’s master Henkel, a helmsman, a mate, Lieutenant Johnson and Commander' Porter. 3 Porter and Johnson, officers of the United States Coast Guard, were aboard the vessel to make an inspection of conditions upriver. 4 The day was clear; the wind from the northwest at 22 knots with gusts up to 27. The tide was flooding with a current estimated at 2 knots. 5 The tug Joan McAllister accompanied the vessel upstream. 6 Pilot Rutherford was in possession of a portable radiotelephone receiver-transmitter.

The Delair Bridge spans the Delaware River between Delair, New Jersey, and Philadelphia. It is equipped with a rotary drawspan, which was revolved 90° counter clockwise to permit the attempted passage of the Marie on the day in question. 7 Walter Dougherty was on duty as drawtender in the shanty on the movable span, and Charles Howell was the block operator situated in the Jersey Tower at the easterly end of the bridge. 8 Dougherty operated the machinery to activate the movable span by means of controls in his shanty, but before this was possible it was necessary for the tower operator to electronically release the drawspan. 9 The bridge was equipped with a radiotelephone located in the tower and operated by Howell. 10 A telephone line between tower and drawtender’s shanty enabled Dougherty and Howell to communicate. Radio communication between the drawtender and approaching vessels was impossible because the bridge radio was located in the Jersey Tower. 11 The tower operator communicated with the dispatcher at the 30th Street Station (Philadelphia) by another telephone line; permission to open the draw was secured from the dispatcher before the tower operator re *371 leased the movable span to the drawtender. 12

The following factual issues are the subject of sharp disagreement between the parties:

1) Precisely when the pilot first notified the bridge by radiotelephone of the presence of the vessel and his intention to transit the draw; whether this first call was answered by Howell in the tower.

2) How many, if any, radiotelephone communications between the pilot and tower operator occurred subsequent to the first.

3) Whether whistle signals were sounded by the vessel.

4) The time at which the drawspan began to open; the time when it was fully opened.

These form the crux of the disputed facts. Testimony of the various witnesses is in irreconcilable conflict concerning these and related factual issues.

The court finds that the pilot first informed the bridge of his presence and intention to transit the draw at 12:26, when in the vicinity of Port Richmond. 13 Upon receipt of this call, the tower operator promptly notified the drawtender. 14 Whether the tower operator responded to this call and apprised the ship of the anticipated arrival of a scheduled westbound passenger train at 12:31 is a subject of controversy 15 which need not be resolved in view of subsequent events. 16

The tower operator testified that. no subsequent radio communication between himself and the vessel occurred until sometime after the collision; 17 testimony of those aboard ship directly contravenes this statement. 18 In evaluation of the testimony of various witnesses, the court has found that of the Coast Guard officers most persuasive. Commander Porter and Lieutenant Johnson were wholly disinterested witnesses whose very purpose in making the voyage was to closely observe and record all incidents of the vessel’s upriver passage. 19 The court has therefore relied heavily on their statements to resolve conflicting factual testimony.

*372 Accordingly, the court finds that the pilot radioed again at 12:34, 20 when the vessel was some 2100 yards below the bridge, and was advised by the tower operator in response that an approaching train would necessitate a three minute delay in opening the draw. 21 The pilot made no reply to this communication by the bridge. 22 From this point the ship moved at the slowest possible rate, favoring the Pennsylvania side of the channel 23 in its approach to the draw; her engines were stopped except for momentary “slow ahead” bells to maintain proper position of her bow in the channel. 24 The average ground speed of the vessel thereafter was estimated at 4 to 6 knots. 25 Throughout the approach the vessel appeared to respond properly, with prompt, accurate execution of the pilot’s engine orders and rudder commands. 26

Free access — add to your briefcase to read the full text and ask questions with AI

Related

COLROSS v. IMPERATO
D. New Jersey, 2022
United States v. Citgo Asphalt Refining Company
718 F.3d 184 (Third Circuit, 2013)
Matheny v. Tennessee Valley Authority
523 F. Supp. 2d 697 (M.D. Tennessee, 2007)
Galentine v. Estate of Stekervetz
273 F. Supp. 2d 538 (D. Delaware, 2003)
Folkstone Maritime, Limited v. Csx Corporation
64 F.3d 1037 (Third Circuit, 1995)
Folkstone Maritime, Ltd. v. CSX Corp.
64 F.3d 1037 (Seventh Circuit, 1995)
Spivey Marine & Harbor Service Co. v. State
46 Ill. Ct. Cl. 41 (Court of Claims of Illinois, 1994)
In re the Complaint of J.E. Brenneman Co.
782 F. Supp. 1021 (E.D. Pennsylvania, 1992)
Williamson Leasing Co. v. American Commercial Lines, Inc.
616 F. Supp. 1330 (E.D. Louisiana, 1985)
State of Conn. v. Tug Cynthia Moran
607 F. Supp. 24 (D. Connecticut, 1984)
S. C. Loveland, Inc. v. East West Towing, Inc.
608 F.2d 160 (Fifth Circuit, 1979)
Erie Lackawanna Railway Co. v. Timpany
495 F.2d 830 (Second Circuit, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
202 F. Supp. 368, 1962 U.S. Dist. LEXIS 4720, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennsylvania-railroad-company-v-ss-marie-leonhardt-paed-1962.