Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission

663 A.2d 281, 1995 Pa. Commw. LEXIS 354
CourtCommonwealth Court of Pennsylvania
DecidedAugust 1, 1995
StatusPublished
Cited by10 cases

This text of 663 A.2d 281 (Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission, 663 A.2d 281, 1995 Pa. Commw. LEXIS 354 (Pa. Ct. App. 1995).

Opinion

KELTON, Senior Judge.

The Pennsylvania Electric Company (Pe-nelec) petitions for review of the May 24, 1994 decision of the Public Utility Commission (the Commission) in which the Commission granted a tariff waiver to Lewistown Specialty Yams, Inc. (Lewistown).

The principal issue before us is whether, under the Public Utility Code,1 the Commission exceeded its authority in granting a customer, Lewistown, a waiver of the eligibility requirements of a more advantageous tariff rate, in the absence of any finding that the relevant tariff rate is unjust, unreasonable or discriminatory.2 We conclude that the Commission lacked the authority to require Penelec, by the grant of a waiver, to provide service to Lewistown under a more advantageous rate, for which Lewistown does not otherwise qualify. However, because the Commission, in granting a waiver, did not address Lewistown’s claim that the relevant rate is unjust, unreasonable, and discriminatory, we vacate and remand this case for further proceedings.

Background

Lewistown, a Penelec customer, conducts an electricity-intensive process for the manufacture of polyester yarns. Lewistown filed a Formal Complaint against Penelec alleging that Penelec was charging Lewistown an unjust, disadvantageous, and discriminatory rate in violation of Sections 1301, 1303, and 1304 of the Public Utility Code.3 At the time, Lewistown was receiving electricity under Penelee’s General Primary (GP) rate classification. Lewistown averred that Pene-lec violated Section 1303 by failing to charge Lewistown under Penelec’s Large Primary (LP) classification, the most advantageous rate. Lewistown’s claim was premised on Penelec’s alleged refusal to sell, at a fair price, a substation that would enable Lewis-town to qualify for electric service under Rate LP.4 Additionally, Lewistown averred [283]*283that application of Rate GP to Lewistown subjects it to unreasonable prejudice or disadvantage in violation of Section 1304. Specifically, Lewistown alleged that its energy use is over ten times the average use of other Rate GP customers and approximately equal to the use of the average Rate LP customer. Therefore, Lewistown alleged that it has overpaid Penelec by about $200,000.00 per year.

The Administrative Law Judge (ALJ) issued, on April 30, 1993, a Recommended Decision denying the Complaint. The ALJ determined that Lewistown does not qualify for Rate LP and that the Commission lacks the authority to require Penelec to sell the substation to Lewistown. Therefore, the ALJ concluded that Lewistown had not proven that Penelec violated Section 1303 by failing to compute Lewistown’s bills under Rate LP. Additionally, the ALJ concluded that Lewistown had failed to show that Pene-lec is charging unjust and discriminatory rates under Sections 1301 and 1304. Lewis-town filed Exceptions to the Recommended Decision and Penelec filed Reply Exceptions.

The Commission issued a December 10, 1993 Opinion and Tentative Order, adopting the ALJ’s findings of fact, but modifying the ALJ’s Recommended Decision to grant a tariff waiver to Lewistown for service under the LP rate schedule. In its Opinion and Tentative Order, the Commission noted that Lew-istown’s usage demands and load profile more closely resemble those of a Rate LP customer than those of a Rate GP customer. Specifically, the Commission noted that Lew-istown’s annual Kwh energy consumption is nearly fifteen times greater than Penelec’s average Rate GP customer and greater than the average Rate LP customer. The Commission determined that if Penelec were to lease or sell the substation to Lewistown, Lewistown would qualify for Rate LP.

The Commission held, however, that it was without authority to require Penelec to sell or lease its substation to Lewistown. Citing Brockway Glass Co. v. Pennsylvania Public Utility Commission, 63 Pa.Commonwealth Ct. 238, 437 A.2d 1067 (1981) and Re West Penn Power Co., 63 Pa.P.U.C. 557 (1987), the Commission determined, however, that it has the power to grant a tariff waiver where it is not inconsistent with its regulations or policies and is in the public interest. The Commission then determined that Penelec’s refusal to cooperate with Lewistown to negotiate the sale or lease of the substation justified the grant of a waiver. The Commission thus granted Lewistown a waiver of the voltage level delivery requirement set forth in Rate LP in order to remove any impediment to Lewistown’s qualification for Rate LP. The Commission’s rationale had not been advanced by either party; therefore, the Commission made the order tentative to allow the parties to submit exceptions.

Both Penelec and Lewistown filed exceptions to the Tentative Order. By order of May 24, 1994, the Commission determined that it had properly exercised its discretion in granting the tariff waiver but modified its Tentative Order to limit the waiver to a period of five years. The Commission stated that five years would allow Lewistown sufficient opportunity to review the economics of purchasing or leasing the necessary equipment to qualify for service under Rate LP.

Penelec appeals to this Court, arguing that, under Brockway, the Commission lacked the authority to grant a tariff waiver without a finding that the applicable tariff is unlawful; that the Commission failed to give Penelec a meaningful opportunity to challenge the Commission’s decision; and that the Commission’s decision is not supported by substantial evidence. Because we conclude that the Commission exceeded its authority in granting the tariff waiver to Lewis-town, we do not discuss the remaining issues, relating to the waiver issue, raised by Pene-lec.

[284]*284Discussion

The Public Utility Code requires every public utility to file with the Commission tariffs showing all schedules of rates within the jurisdiction of the Commission. 66 Pa. C.S. § 1302. A tariff can include all schedules of rates and all rules, regulations, practices, or contracts involving any rate or rates. 66 Pa.C.S. § 102; Brockway. Tariffs have the force of law and are binding on both the utility and the customer. Brockway.

The Code contains no specific statutory authority for a tariff waiver as granted by the Commission. Section 1309 of the Code requires the Commission, upon a finding that the existing rates of any public utility for any service are unjust, unreasonable or in violation of any provision of law, to determine just and reasonable rates after reasonable notice and hearing, upon its own motion or complaint.5 Although unique circumstances may warrant a separate rate for a customer, see, e.g., Riverton Consolidated Water Co. v. Pennsylvania Public Utility Commission, 186 Pa.Superior Ct. 1, 140 A.2d 114 (1958), the Commission did not establish a separate rate for Lewistown but granted it a waiver of existing rate eligibility requirements.

Additionally, where a utility has more than one rate applicable to a customer, Section 1303 of the Code requires the utility to compute its bills under the rate most advantageous to the customer. 66 Pa.C.S. § 1303. However, there can be no lawful rate except the last tariff published. Brock-way. Here, under the effective tariff, Lewis-town did not qualify for the more advantageous Rate LP, absent the waiver.6

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L. Kingsley v. PPL Electric Utilities and PA PUC
Commonwealth Court of Pennsylvania, 2024
Respond Power, LLC v. PA PUC
Commonwealth Court of Pennsylvania, 2021
PPL Electric Utilities Corp. v. City of Lancaster and PA PUC
125 A.3d 837 (Commonwealth Court of Pennsylvania, 2015)
State Farm Fire & Casualty Co. v. PECO
54 A.3d 921 (Superior Court of Pennsylvania, 2012)
PPL Electric Utilities Corp. v. Pennsylvania Public Utility Commission
912 A.2d 386 (Commonwealth Court of Pennsylvania, 2006)
Philadelphia Suburban Water Co. v. Pennsylvania Public Utility Commission
808 A.2d 1044 (Commonwealth Court of Pennsylvania, 2002)
Knipmeyer v. Bell Atlantic Corp.
51 Pa. D. & C.4th 225 (Philadelphia County Court of Common Pleas, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
663 A.2d 281, 1995 Pa. Commw. LEXIS 354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennsylvania-electric-co-v-pennsylvania-public-utility-commission-pacommwct-1995.