Pennington v. Continental Resources, Inc.

2019 ND 228, 932 N.W.2d 897
CourtNorth Dakota Supreme Court
DecidedAugust 27, 2019
Docket20190063
StatusPublished
Cited by9 cases

This text of 2019 ND 228 (Pennington v. Continental Resources, Inc.) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennington v. Continental Resources, Inc., 2019 ND 228, 932 N.W.2d 897 (N.D. 2019).

Opinion

Crothers, Justice.

[¶1] Rhonda Pennington, Steven Nelson, Donald Nelson, and Charlene Bjornson ("Plaintiffs") appeal a district court judgment ruling a "regulation and delay" provision in their oil and gas leases with Continental Resources extended the term of the leases. We affirm in part, reverse in part, and remand for further proceedings.

I

[¶2] On October 25, 2011, the Plaintiffs executed oil and gas leases for property in McKenzie County. Each lease term was three years with a lessee option to extend for an additional year. The leases were assigned to Continental in September 2014, and it exercised the extension option. The leases included a provision that the leases would not terminate if drilling operations were delayed by an inability to obtain permits.

[¶3] In May 2012, Continental applied for a drilling permit on a 2,560-acre spacing unit that included the lands covered by the leases. The 2,560 acres included lands inhabited by the Dakota Skipper butterfly, which is listed as threatened under the Endangered Species Act. Continental could not begin drilling operations until receiving federal approval. In August 2015, the U.S. Fish and Wildlife Service issued a biological opinion relating to the impact of Continental's proposed drilling on the Dakota Skipper. On October 1, 2015, Continental proposed measures to minimize the impact of its operations on the Dakota Skipper.

[¶4] On October 21, 2015, Continental recorded an affidavit of regulation and delay, stating it had not yet obtained federal regulatory approval to drill, and the primary term of the leases was extended under the "regulation and delay" paragraph of the leases. The following day, Continental applied to terminate the 2,560-acre spacing unit and create a 1,920-acre spacing unit to remove the Dakota Skipper habitat. In November 2015, the Industrial Commission approved the 1,920-acre spacing unit. In January 2016, the commission pooled all of the oil and gas interests in the 1,920-acre spacing unit for the development and operation of the spacing unit. Following the January 2016 order, Continental began drilling operations.

*900 [¶5] In August 2017, the Plaintiffs sued Continental, alleging the leases expired on October 25, 2015, and Continental's delay in obtaining regulatory approval to drill did not extend the leases. Both parties moved for summary judgment. The district court granted Continental's motion, concluding the "regulation and delay" provision extended the leases until regulatory approval could be obtained to begin drilling operations.

II

[¶6] This Court's standard of review for summary judgments is well-established:

"Summary judgment is a procedural device for the prompt resolution of a controversy on the merits without a trial if there are no genuine issues of material fact or inferences that can reasonably be drawn from undisputed facts, or if the only issues to be resolved are questions of law. A party moving for summary judgment has the burden of showing there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. In determining whether summary judgment was appropriately granted, we must view the evidence in the light most favorable to the party opposing the motion, and that party will be given the benefit of all favorable inferences which can reasonably be drawn from the record. On appeal, this Court decides whether the information available to the district court precluded the existence of a genuine issue of material fact and entitled the moving party to judgment as a matter of law. Whether the district court properly granted summary judgment is a question of law which we review de novo on the entire record."

Horob v. Zavanna, LLC , 2016 ND 168 , ¶ 8, 883 N.W.2d 855 (quoting Poppe v. Stockert , 2015 ND 252 , ¶ 4, 870 N.W.2d 187 ).

[¶7] When ruling on a summary judgment motion, a district court may not weigh the evidence, determine credibility or attempt to discern the truth of the matter. Martin v. Marquee Pacific, LLC , 2018 ND 28 , ¶ 10, 906 N.W.2d 65 . Deciding an issue on summary judgment is improper if the court must draw inferences or make findings on disputed material facts. Id.

III

[¶8] Plaintiffs argue the leases expired in October 2015, and the "regulation and delay" provision did not extend them.

[¶9] Oil and gas leases are contracts and are interpreted to give effect to the parties' mutual intent at the time of contracting. Horob , 2016 ND 168 , ¶ 10, 883 N.W.2d 855 ; see also N.D.C.C. § 9-07-03. The parties' intent is ascertained from the writing alone if possible. N.D.C.C. § 9-07-04. "The language of a contract is to govern its interpretation if the language is clear and explicit and does not involve an absurdity." N.D.C.C. § 9-07-02. A contract is interpreted as a whole "so as to give effect to every part if reasonably practicable." N.D.C.C. § 9-07-06. Contract interpretation is a question of law, fully reviewable on appeal. Horob , at ¶ 10. In construing an oil and gas lease, "[w]e attempt to give effect to every clause, sentence, and provision in a contract." Fleck v. Missouri River Royalty Corp. , 2015 ND 287 , ¶ 8, 872 N.W.2d 329 .

[¶10] Here, the lease term is governed under Paragraph 3:

"3. Term of Lease. This lease shall be in force for a primary term of three (3) years from the date hereof, and for as long thereafter as oil or gas or other *901 substances covered hereby are produced in paying quantities from the leased premises or from lands pooled or unitized therewith or this lease is otherwise maintained in effect pursuant to the provisions hereof."

Paragraph 17 of the leases provide the lessee an option to extend the three-year primary term for an additional year. In October 2014, Continental exercised the option and extended the leases.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Henry Hill Oil Services v. Tufto
2023 ND 41 (North Dakota Supreme Court, 2023)
Dwyer v. Sell
2021 ND 139 (North Dakota Supreme Court, 2021)
Pennington v. Continental Resources
2021 ND 105 (North Dakota Supreme Court, 2021)
Three Aces Properties v. United Rentals
2020 ND 258 (North Dakota Supreme Court, 2020)
Feltman v. Gaustad
2020 ND 89 (North Dakota Supreme Court, 2020)
Krebsbach v. Trinity Hospitals, Inc.
2020 ND 24 (North Dakota Supreme Court, 2020)
Pennington v. Continental Resources, Inc.
2019 ND 228 (North Dakota Supreme Court, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2019 ND 228, 932 N.W.2d 897, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennington-v-continental-resources-inc-nd-2019.