PennEast Pipeline Company, LLC v. A Permanent Easement of 0.60 acre +/- and a temporary easement of 0.60 acre +/- in Towamensing Township, Carbon County, Pennsylvania, Tax Parcel Nos. 16-56-A73 and 16B-56-A7

CourtDistrict Court, M.D. Pennsylvania
DecidedSeptember 29, 2022
Docket3:18-cv-00281-MEM
StatusUnknown

This text of PennEast Pipeline Company, LLC v. A Permanent Easement of 0.60 acre +/- and a temporary easement of 0.60 acre +/- in Towamensing Township, Carbon County, Pennsylvania, Tax Parcel Nos. 16-56-A73 and 16B-56-A7 (PennEast Pipeline Company, LLC v. A Permanent Easement of 0.60 acre +/- and a temporary easement of 0.60 acre +/- in Towamensing Township, Carbon County, Pennsylvania, Tax Parcel Nos. 16-56-A73 and 16B-56-A7) is published on Counsel Stack Legal Research, covering District Court, M.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PennEast Pipeline Company, LLC v. A Permanent Easement of 0.60 acre +/- and a temporary easement of 0.60 acre +/- in Towamensing Township, Carbon County, Pennsylvania, Tax Parcel Nos. 16-56-A73 and 16B-56-A7, (M.D. Pa. 2022).

Opinion

UNITED STATES DISTRICT COURT MIDDLE DISTRICT OF PENNSYLVANIA

PENNEAST PIPELINE COMPANY : LLC, : Plaintiff CIVIL ACTION NO. 3:18-281 : v. (JUDGE MANNION) : A PERMANENT EASEMENT OF 0.60 ACRE +/- AND A : TEMPORARY EASEMENT OF 0.60 ACRE +/- IN TOWAMENSING : TOWNSHIP, CARBON COUNTY, PENNSYLVANIA, TAX PARCEL : NOS. 16-56-A73 AND 16B-56-A7; SUSANA BULLRICH; BANK OF : AMERICA, N.A.; AND ALL KNOWN OWNERS :

Defendants :

MEMORANDUM I. BACKGROUND Defendant has requested this court vacate the two December 3, 2018 orders, (Doc. 40 and Doc. 42.), as a matter of justice. This court previously granted partial summary judgment and a preliminary injunction for the plaintiff granting: 1. A permanent right of way and easement of 0.60 ± as depicted on Exhibits A-1 and A-2 hereto for the purpose of constructing, operating, maintaining, altering, repairing, replacing and removing a 36-inch diameter pipeline and all related equipment and appurtenances thereto (including but not limited to cathodic protection equipment) for the transportation of natural gas, as approved by the Order of the Federal Energy Regulatory Commission, dated January 19, 2018, Docket No. CP-15-558-000 (“FERC Order”); and conducting all other activities as approved by the FERC Order; together with all rights and benefits necessary for the full enjoyment and use of the right of way and easement, including rights of ingress and egress for the above-stated purposes. Further, Defendants shall not excavate, change the grade of or place any water impoundments or structures on the right of way and easement without the written consent of Plaintiff, nor may Defendants plant any trees, including trees considered as a growing crop, on the permanent right of way and easement; or use said permanent right of way or any part thereof in such a way as to interfere with Plaintiff’s immediate and unimpeded access to said permanent right of way, or otherwise interfere with Plaintiff’s lawful exercise of any of the rights herein granted without first having obtained Plaintiff’s approval in writing; and Defendants will not permit others to do any of said acts without first having obtained Plaintiff’s approval in writing. Plaintiff shall have the right from time to time at no additional cost to Defendants to cut and remove all trees including trees considered as a growing crop, all undergrowth and any other obstructions that may injure, endanger or interfere with the construction and use of said pipeline and all related equipment and appurtenances thereto; 2. A temporary workspace easement totaling 0.60 acre ± as described on Exhibits A-1 and A-2 hereto for use during the pipeline construction and restoration period only for the purpose of ingress, egress and regress and to enter upon, clear off and use for construction and all activities required by the FERC ORDER.

These orders were issued pursuant to plaintiff’s authorization through the Federal Energy Regulatory Commission (“FERC”) to construct a natural gas pipeline. On December 16, 2021, FERC vacated the authorization for the PennEast Project, pending a leave of court to the District of Columbia Court

of Appeals. (Doc. 71-1). On February 8, 2022, the District of Columbia Court of Appeals then remanded the case to FERC to vacate the authorizations and dismiss the pending certificate for the PennEast project. (Doc. 72-2).

After plaintiff lost authorization from FERC, plaintiff filed a notice of dismissal pursuant to Federal Rule of Civil Procedure 71.1(i)(1)(A) on September 27, 2021. Defendant objected to the dismissal pursuant to F.R.C.P. 71.1(i)(1)(C) stating that plaintiff already took title, a lesser interest,

or possession, which therefore required compensation. Presently before the court remains defendant’s motion to vacate the orders granting partial summary judgment and a preliminary injunction. The

parties have sufficiently briefed the matter and the issues are ripe for disposition.

II. STANDARD

A motion to dissolve an injunction asks the court to determine “whether the movant has made a showing that changed circumstances warrant the discontinuation of the order.” Township of Franklin Sewerage Auth. v.

Middlesex County Utils. Auth., 787 F.2d 117, 121 (3d Cir. 1986). III. DISCUSSION a. Motion to vacate the court’s December 3, 2018 Orders

“A district court is entitled to reconsider its interlocutory orders ‘when it is consonant with justice to do so.’” Alea N. Am. Ins. Co. v. Salem Masonry Co., 301 F. App'x 119, 121 (3d Cir. 2008) (citing United States v. Jerry, 487

F.2d 600, 605 (3d Cir.1973)).Alea N. Am. Ins. Co., 301 F. App'x at 121. A motion to dissolve an injunction requires the court to assess “whether the movant has made a showing that changed circumstances warrant the discontinuation of the order.” Township of Franklin Sewerage Auth., 787 F.2d

at 121. The circumstances underlying this case have significantly changed and in the interest of justice, this court must act. Plaintiff lost authorization from

FERC to continue the project that originally granted plaintiff the ability to begin condemnation proceedings. Without such authorization, the condemnation and preliminary injunction no longer serve a public purpose for a natural gas pipeline. Thus, plaintiff is no longer entitled to a “permanent right of way and

easement,” (Doc. 40), nor is plaintiff entitled to the preliminary injunction granting immediate access to defendant’s property, (Doc. 42). Because authorization for the project has been wholly revoked, this

court hereby vacates the December 3, 2018 orders granting a permanent right of way and easement and the preliminary injunction granting plaintiff immediate access to the property.

b. Notice of Dismissal pursuant to F.R.C.P. 71.1(i)(1)(A)

Under F.R.C.P. 71.1(i)(1)(A), a plaintiff may dismiss a suit, “if no compensation hearing on a piece of property has begun, and if plaintiff has not acquired title or a lesser interest or taken possession, the plaintiff may, without court order, dismiss the action as to that property by filing a notice of dismissal briefly describing the property.” F.R.C.P. 71.1(i)(1)(A). Plaintiff filed a notice of dismissal on September 28, 2021 pursuant to F.R.C.P. 71.1(i)(1)(A). However, plaintiff’s notice of dismissal ignored a

significant component of the rule that bars dismissal, “if no compensation hearing on a piece of property has begun, and if plaintiff has not acquired title or a lesser interest or taken possession…” F.R.C.P. 71.1(i)(1)(A) (emphasis

added). The Supreme Court of the United States has explained that a taking has occurred in a condemnation action “not…when the [condemnor] filed its declaration of taking,” but “when [the condemnor] entered into possession of

the land. United States v. Dow, 357 U.S. 17, 21 (1958). The court further elaborated that one enters into possession of the land when they exercise a right to “immediate possession” of the land at issue. Id. at 19. This understanding is synonymous with Pennsylvania’s eminent domain law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Dow
357 U.S. 17 (Supreme Court, 1958)
United States v. Bernard Jerry, and Edgar Saunders
487 F.2d 600 (Third Circuit, 1973)
Alea North America Insurance v. Salem Masonry Co.
301 F. App'x 119 (Third Circuit, 2008)
West Penn Power Co. v. Thomas
416 A.2d 578 (Commonwealth Court of Pennsylvania, 1980)
In re Philadelphia Electric Co. Right of Way
622 A.2d 408 (Commonwealth Court of Pennsylvania, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
PennEast Pipeline Company, LLC v. A Permanent Easement of 0.60 acre +/- and a temporary easement of 0.60 acre +/- in Towamensing Township, Carbon County, Pennsylvania, Tax Parcel Nos. 16-56-A73 and 16B-56-A7, Counsel Stack Legal Research, https://law.counselstack.com/opinion/penneast-pipeline-company-llc-v-a-permanent-easement-of-060-acre-and-pamd-2022.