Pelaez Construction, LLC v. Green Field Construction Group, LLC

CourtNew Jersey Superior Court Appellate Division
DecidedDecember 19, 2025
DocketA-0371-24
StatusUnpublished

This text of Pelaez Construction, LLC v. Green Field Construction Group, LLC (Pelaez Construction, LLC v. Green Field Construction Group, LLC) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pelaez Construction, LLC v. Green Field Construction Group, LLC, (N.J. Ct. App. 2025).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited . R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-0371-24

PELAEZ CONSTRUCTION, LLC,

Plaintiff-Appellant,

v.

GREEN FIELD CONSTRUCTION GROUP, LLC, GREEN FIELD BUILDERS GROUP, as Successor to Green Field Construction Group, LLC, SEAN BRENNAN and MICHAEL TENNYSON,

Defendants-Respondents. _______________________________

Argued October 15, 2025 – Decided December 19, 2025

Before Judges DeAlmeida and Torregrossa-O'Connor.

On appeal from the Superior Court of New Jersey, Law Division, Middlesex County, Docket No. L-2155-21.

John J. Pribish argued the cause for appellant (Pribish- Reiss, LLP, attorneys; John J. Pribish, on the briefs).

Peter M. Kutil (King & King, LLP) argued the cause for respondents Sean Brennan and Michael Tennyson. PER CURIAM

Plaintiff Pelaez Construction, LLC filed suit against defendants Green

Field Construction Group, LLC, Green Field Builders Group, LLC 1 (company

defendants), Sean Brennan and Michael Tennyson (individual defendants),

(collectively, defendants), in connection with unpaid construction work plaintiff

performed for defendants. Plaintiff now appeals from the trial court's July 8,

2024 order, after a hearing pursuant to Rule 4:43-2(b) (proof hearing), entering

judgment against the company defendants in the amount of $202,500, but

finding Brennan and Tennyson not individually responsible for damages.

Plaintiff also appeals from the trial court's August 30, 2024 order denying

reconsideration.

Specifically, plaintiff contends the trial court erred in finding, at the proof

hearing's conclusion, plaintiff failed to show the individual defendants were

personally responsible for damages, when, at the hearing's outset, the court

stated liability was already established by a prior order entering default against

1 Green Field Construction Group, LLC no longer conducts business. Brennan, the Chief Financial Officer and partner, owned thirty percent of the company; Tennyson, an officer and director, also owned thirty percent. Green Field Builders Group, LLC is a successor entity created in 2020. During the litigation, both Brennan and Tennyson were officers and directors of Green Field Builders; Brennan owned thirty percent of the company and Tennyson owned seventy percent. A-0371-24 2 all defendants, jointly and severally, and restricted the proof hearing's scope to

damages only. A series of motion orders finding the individual defendants

willfully obstructed discovery and striking their pleadings and defenses,2

predated the entry of default. Plaintiff argues it reasonably relied on the trial

court's narrow hearing parameters and consequently tailored its presentation to

proof of unpaid fees for construction services it satisfactorily performed for

defendants. It further argues the trial court's determination overlooks the basis

for the default and rewards the individual defendants' willful obstruction of

discovery. Plaintiff also contends the trial court improperly calculated damages

in the amount of $202,500.

After review of the record under applicable legal principles, we affirm the

court's damage calculation, but we are constrained to vacate the portion of the

court's order denying judgment against the individual defendants. We remand

for a new hearing in accordance with this opinion and the prior court orders

entering default against the individual defendants jointly and severally and

striking defendants' pleadings based on their non-compliance with discovery.

2 The first motion judge granted plaintiff's motions to compel discovery and later to strike defendants' pleadings first without, and ultimately, with prejudice. The second motion judge entered the default judgment jointly and severally against all defendants based on the discovery violations. Those orders were never appealed. A-0371-24 3 I.

A.

To contextualize the issues before us, we summarize only the relevant

background and history of the litigation. The services for which plaintiff sought

payment were related to Green Field Construction's 2018 agreement with Pier

Village Urban Renewal, LLC (Pier Village) to construct retail and residential

units in Long Branch, on the project known as The Lofts at Pier Village (the

Lofts). Originally hired as a subcontractor by Hevy Construction 3 to install

drywall and insulation for the Lofts project, plaintiff later agreed orally with

Brennan, acting on Green Field Construction's behalf, to finish certain

remaining Lofts work when Pier Village terminated Hevy. The parties do not

dispute plaintiff satisfactorily completed the work as well as additional tasks

performed at Brennan's request.

In April 2021, plaintiff filed an initial complaint against Green Field

Construction and Brennan, asserting breach of contract, fraud, and unjust

enrichment. Plaintiff sought to "recover monies and damages against

[d]efendants Green Field [Construction] and Brennan for having induced

3 We note that Hevy Construction is at times spelled "Heavy Construction" in the trial court transcripts, but it appears the proper spelling is Hevy, and any confusion results from the pronunciation of the company's name in testimony. A-0371-24 4 [p]laintiff to work at . . . [t]he Lofts," which it performed "in a good and

workmanlike manner in a timely fashion," but that Green Field Construction and

Brennan "refused to pay all of the sums . . . due and owing to [p]laintiff." After

default was entered against defendants for failure to answer, and later vacated

by consent, they filed answers asserting separate defenses on July 6, 2021.

Discovery commenced, and plaintiff learned of two ongoing lawsuits: a

federal action in which counterclaims by an unrelated party alleged Brennan and

Tennyson diverted corporate resources and engaged in other corporate

malfeasance in connection with Green Field Construction, and state litigation in

which Pier Village filed a complaint against Tennyson and Brennan, alleging

they misappropriated funds slated to pay subcontractors. As a result, plaintiff

filed an amended complaint in December 2022 adding Tennyson and Green

Field Builders as defendants, and alleging Brennan and Tennyson, as owners of

Green Field Construction, "induc[ed] [Green Field] Construction to [b]reach

[its] [c]ontract with [p]laintiff" by "willfully and deliberately divert[ing] and

misappropriat[ing] those monies which were due to [p]laintiff and used said

monies for their own personal purposes."

Plaintiff served numerous discovery demands on defendants to obtain

relevant information and financial records, including bank statements, checks,

A-0371-24 5 and account ledgers, related to Brennan's and Tennyson's alleged

misappropriation of funds. Throughout a series of motions, defendants asserted

all claims against the individual defendants were unsupported, and plaintiff

successfully extended discovery claiming defendants "thwarted" efforts to

access information related to their involvement. In April 2023, after repeated

unsuccessful discovery requests, plaintiff filed its first motion to compel

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kolczycki v. City of East Orange
722 A.2d 603 (New Jersey Superior Court App Division, 1999)
Morales v. Santiago
526 A.2d 266 (New Jersey Superior Court App Division, 1987)
Douglas v. Harris
173 A.2d 1 (Supreme Court of New Jersey, 1961)
McKeown-Brand v. Trump Castle Hotel & Casino
626 A.2d 425 (Supreme Court of New Jersey, 1993)
Heimbach v. Mueller
550 A.2d 993 (New Jersey Superior Court App Division, 1988)
Borough of Keyport v. Maropakis
753 A.2d 154 (New Jersey Superior Court App Division, 2000)
Cripps v. DiGregorio
824 A.2d 1104 (New Jersey Superior Court App Division, 2003)
Manalapan Realty v. Township Committee of the Township of Manalapan
658 A.2d 1230 (Supreme Court of New Jersey, 1995)
Johnson v. Johnson
224 A.2d 23 (New Jersey Superior Court App Division, 1966)
Flagg v. Essex County Prosecutor
796 A.2d 182 (Supreme Court of New Jersey, 2002)
Interchemical Corp. v. Uncas Printing & Fin. Co.
120 A.2d 880 (New Jersey Superior Court App Division, 1956)
City of Passaic v. Shennett
915 A.2d 1092 (New Jersey Superior Court App Division, 2007)
Jugan v. Pollen
601 A.2d 235 (New Jersey Superior Court App Division, 1992)
Schettino v. Roizman Development, Inc.
730 A.2d 797 (Supreme Court of New Jersey, 1999)
Chakravarti v. Pegasus Consulting Group, Inc.
923 A.2d 233 (New Jersey Superior Court App Division, 2007)
United States v. Scurry
940 A.2d 1164 (Supreme Court of New Jersey, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Pelaez Construction, LLC v. Green Field Construction Group, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pelaez-construction-llc-v-green-field-construction-group-llc-njsuperctappdiv-2025.