Pearce v. POWER & TELEPHONE OF KENTUCKY, INC.

533 So. 2d 46, 1988 WL 103151
CourtLouisiana Court of Appeal
DecidedOctober 5, 1988
Docket87-658
StatusPublished
Cited by10 cases

This text of 533 So. 2d 46 (Pearce v. POWER & TELEPHONE OF KENTUCKY, INC.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pearce v. POWER & TELEPHONE OF KENTUCKY, INC., 533 So. 2d 46, 1988 WL 103151 (La. Ct. App. 1988).

Opinion

533 So.2d 46 (1988)

Dennis R. PEARCE and Terry L. Pearce, Plaintiffs-Appellants-Appellees,
v.
POWER AND TELEPHONE OF KENTUCKY, INC., Central La. Telephone Company, Inc., and Century Telephone Enterprises, Inc., Defendants-Appellants-Appellees.

No. 87-658.

Court of Appeal of Louisiana, Third Circuit.

October 5, 1988.
Rehearing Denied November 21, 1988.

*47 Dan B. McKay, Jr., Bunkie, for plaintiffs-appellants-appellees.

William R. Boles, Jr., Monroe, Peter J. Lemoine, Bunkie, defendants-appellants-appellees.

Before DOMENGEAUX, KNOLL and KING, JJ.

KING, Judge.

There are two issues presented by this appeal. The first is whether or not the trial court was correct in finding that plaintiffs were subcontractors rather than employees of defendants and entitled to additional compensation for work performed outside the scope of their original contract. The second is whether defendants were entitled to damages resulting from plaintiffs' faulty work.

Dennis R. Pearce and his brother, Terry L. Pearce, (hereinafter plaintiffs) filed suit against defendants, Power and Telephone of Kentucky, Inc. (hereinafter Power), Central Louisiana Telephone Company, Inc. (hereinafter Central) and its parent company, Century Telephone Enterprises, Inc. (hereinafter Century), to recover for labor and services. Defendants filed a reconventional demand for damages claiming that plaintiffs breached their contract by faulty work. After trial on the merits, the trial court rendered judgment in favor of one of the plaintiffs-defendants in reconvention for $330.00 and against defendants-plaintiffs in reconvention. A written judgment was signed. Plaintiffs appeal seeking an increase in the amount awarded by the trial court and defendants appeal seeking reversal of plaintiffs' judgment against them and judgment on their reconventional demand against plaintiffs. We affirm.

FACTS

Plaintiffs, Dennis R. Pearce (hereinafter Dennis) and his brother, Terry L. Pearce (hereinafter Terry), are telephone cable splicers by trade. In the summer of 1985, Dennis contracted for his services with defendant, Power. Power had been contracted by defendants, Central, and its parent company, Century, to install and repair underground and aerial telephone cables located in Avoyelles Parish, Louisiana.

Dennis had previously worked for Power on another cable splicing job in Mississippi and was offered work on the Louisiana job contracted by Power with Central. Larry Sprouse, President of Power, called Dennis in Tennessee and offered to pay him on a per-unit basis, and not by the hour as he was previously paid in Mississippi. Dennis agreed and came to Cottonport, Louisiana to meet T.L. Lewis, who was in charge of the new construction project. Dennis testified that when he arrived in Cottonport, Louisiana, there were no splicing supplies with which he could start work, so he borrowed enough supplies from a friend in Bunkie, Louisiana and began the project.

After working on and off for about a month, for a total of about 86 hours, Larry Sprouse contacted Dennis and informed him that, for safety reasons and to expedite completion, it was necessary for Dennis to keep a man on the job at least six days a week. Dennis was unable to do this and had originally planned to work only on weekends on the Cottonport project. Dennis testified that at this time he also realized he could not work for the per-unit price basis which he had agreed upon earlier, especially since there would be no payment until the project was complete and tested. Dennis complained to Larry Sprouse about not being able to stay on the job without an advance to cover his expenses. Sprouse advanced Dennis $1,000.00 to induce him to remain on the job. Shortly thereafter, Dennis, unhappy with the per-unit price agreement, quit the job and returned to Tennessee.

Within a week, Sprouse had contacted Dennis and requested him to return and complete the job. Dennis refused to do so, but his brother, Terry, offered to complete the job for Dennis. Sprouse agreed to this arrangement.

Terry testified that when he spoke with Sprouse about resuming Dennis' work, he *48 was promised a rate of $15.00 per hour for the work and not the per-unit prices to which Dennis had agreed. Terry left Tennessee for Cottonport, Louisiana, with his fiance, whom Terry intended to train as a helper. Terry stated that when he arrived he found a shortage of supplies which caused a delay of a few days before he could begin work. When Terry began work on the job, he stated that he had to check some of Dennis' work and re-do some of his splices. Terry testified and produced documents indicating that he had worked a total of 639 hours on the job, but that when it was completed, he was told to convert the working hours into a per-unit cost basis. He stated that he thought this request was bizarre because he thought he was getting paid by the hour. Terry was told that final payment for the job would not take place until all of the wires spliced by him, Dennis, and their helpers were tested and Dennis had submitted the final bill on a per-unit basis.

After waiting several days for this testing to take place, Terry left the project and returned to Tennessee to get a tester so that he could begin testing the splices himself. Upon his return, Terry was told that he could not test the splices by himself, and that an engineer's presence was needed to verify the correctness of the work on the cables. As there were no engineers available at that time, Terry left Louisiana and returned to Tennessee.

Before leaving Louisiana, Terry sought legal advice concerning what action to take to obtain the monies owed to him and Dennis. After discussing their options with Dennis, Terry returned to Louisiana to sign a lien affidavit in the amount of $6,711.40 representing the amounts he claimed were owed to both him and his brother, Dennis. The lien was filed and recorded in the record of Avoyelles Parish, Louisiana. After an impasse was reached regarding the amount owed to the plaintiffs, they filed suit in December, 1985, naming Power, Central, and Century as defendants. The purpose of the suit was to recover the amount allegedly owed to them as set forth in the lien affidavit. Power answered the plaintiffs' suit with a general denial and reconvened against them for $8,500.00. This amount allegedly represented the cost of the work necessary to re-do the faulty and defective work performed by both plaintiffs. Central and Century answered plaintiffs' suit and cross-claimed against Power in the event Central and Century were cast in judgment to plaintiffs. Plaintiffs later amended their petition alleging that they were employees of Power and increased their demand to reflect unpaid amounts of $1,199.70 and $10,240.35 owed to Dennis and Terry respectively as employees. Plaintiffs' amended suit further requested penalties and attorney's fees as provided for by LSA-R.S. 23:631-632. Power later amended its reconventional demand to seek a total of $9,532.72 in damages plus another $23,503.00 in general damages.

After a trial on the merits, the trial judge granted judgment against defendant, Power, and in favor of Terry, but only for $330.00, plus interest. This sum was granted because it was shown at trial that Terry had performed 22 hours of non-contract work, resplicing a "live" cable which had been accidentally cut by a third party. Although Power admitted that it had agreed to pay Terry $15.00 an hour for this emergency job, Power disputed Terry's testimony that it took him 22 hours and claimed it only took him 6 hours.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Louisiana v. Brynton Kelli Simmons
Louisiana Court of Appeal, 2021
Ratcliff v. Normand
819 So. 2d 434 (Louisiana Court of Appeal, 2002)
Aetna Life & Casualty Co. v. AMI-Electrical & Hoist Service
637 So. 2d 173 (Louisiana Court of Appeal, 1994)
Blunck v. Lloyds Underwriters at London
640 So. 2d 466 (Louisiana Court of Appeal, 1994)
Clement v. Griffin
634 So. 2d 412 (Louisiana Court of Appeal, 1994)
Krampe v. Krampe
625 So. 2d 383 (Louisiana Court of Appeal, 1993)
Succession of McKean
618 So. 2d 1108 (Louisiana Court of Appeal, 1993)
Glankler v. Rapides Parish School Bd.
610 So. 2d 1020 (Louisiana Court of Appeal, 1992)
Sinha v. Dabezies
590 So. 2d 795 (Louisiana Court of Appeal, 1991)
Jaffarzad v. Jones Truck Lines, Inc.
561 So. 2d 144 (Louisiana Court of Appeal, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
533 So. 2d 46, 1988 WL 103151, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pearce-v-power-telephone-of-kentucky-inc-lactapp-1988.