Pavers, Inc. v. BD. OF REGENTS OF UNIV. OF NE.

755 N.W.2d 400, 276 Neb. 559
CourtNebraska Supreme Court
DecidedSeptember 12, 2008
DocketS-07-671
StatusPublished
Cited by33 cases

This text of 755 N.W.2d 400 (Pavers, Inc. v. BD. OF REGENTS OF UNIV. OF NE.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pavers, Inc. v. BD. OF REGENTS OF UNIV. OF NE., 755 N.W.2d 400, 276 Neb. 559 (Neb. 2008).

Opinion

755 N.W.2d 400 (2008)
276 Neb. 559

PAVERS, INC., a Nebraska corporation, Appellee and Cross-Appellant,
v.
BOARD OF REGENTS OF the UNIVERSITY OF NEBRASKA, a public body corporate of the State of Nebraska, Appellant and Cross-Appellee.

No. S-07-671.

Supreme Court of Nebraska.

September 12, 2008.

*402 Craig C. Dirrim and Terry C. Dougherty, of Woods & Aitken, L.L.P., Lincoln, and John C. Wiltse, Senior Associate General Counsel, University of Nebraska, for appellant.

Timothy R. Engler, Adam J. Prochaska, and John Selzer, of Harding & Schultz, P.C., L.L.O., Lincoln, for appellee.

WRIGHT, CONNOLLY, GERRARD, McCORMACK, and MILLER-LERMAN, JJ., and SIEVERS and MOORE, Judges.

WRIGHT, J.

I. NATURE OF CASE

This is a contract claim by Pavers, Inc., against the Board of Regents of the University of Nebraska (University). The dispute involves a contract for the performance of earthwork for a student housing project at 16th and Y Streets in Lincoln, Nebraska. The contract was composed of several documents prepared by the University, and the bid included price quotes for 11 separate construction activities.

While Pavers was performing the contract, it became apparent that 3 of the 11 activities would greatly exceed the estimated costs as set forth in the contract. Upon completion of the contract, the University paid Pavers what the University considered to be a reasonable amount, but did not pay the additional amount Pavers claimed for soil disposal, seepage water removal, and seepage water disposal.

Pavers filed a claim with the State Claims Board but then withdrew its claim and initiated an action in the Lancaster County District Court. The matter proceeded to trial, and the court awarded Pavers a judgment on its claim against the University. The University has appealed, and Pavers has cross-appealed.

II. SCOPE OF REVIEW

[1] Whether a statute is constitutional is a question of law; accordingly, the Nebraska Supreme Court is obligated to *403 reach a conclusion independent of the decision reached by the court below. Stenger v. Department of Motor Vehicles, 274 Neb. 819, 743 N.W.2d 758 (2008).

[2, 3] The interpretation of a contract involves a question of law, in connection with which an appellate court has an obligation to reach its conclusions independently of the determinations made by the court below. State ex rel. Bruning v. R.J. Reynolds Tobacco Co., 275 Neb. 310, 746 N.W.2d 672 (2008). The meaning of a contract and whether a contract is ambiguous are questions of law. Kluver v. Deaver, 271 Neb. 595, 714 N.W.2d 1 (2006).

[4, 5] In a bench trial of a law action, a trial court's factual findings have the effect of a jury verdict and will not be set aside on appeal unless clearly erroneous. Henriksen v. Gleason, 263 Neb. 840, 643 N.W.2d 652 (2002). The appellate court does not reweigh the evidence but considers the judgment in a light most favorable to the successful party and resolves evidentiary conflicts in favor of the successful party, who is entitled to every reasonable inference deducible from the evidence. Id.

III. FACTS

The University and Pavers contracted for earthwork, grading, and overexcavation for a student housing project at 16th and Y Streets in Lincoln. There were 11 separate construction activities in the contract. The University's bid proposal form described and specified a quantity for each activity. The contractors bid a unit price for each quantity of work. In order to obtain an estimate for each activity, the unit prices bid on the activity were multiplied by the University's estimated quantity of work for the respective activity. The estimates for all 11 activities were added together to arrive at the "Base Bid."

The dispute in this case involves three activities within the contract: soil disposal, seepage water removal, and seepage water disposal. Pavers bid a unit price of $27.60 per ton for soil disposal, which is referred to as "work unit 9." It bid $3.90 per gallon for removal of seepage water, which is referred to as "work unit 10," and $3.45 per gallon for seepage water disposal, which is referred to as "work unit 11."

During the performance of the contract, the actual quantities of seepage water and contaminated soil to be removed and disposed of greatly exceeded the amounts estimated by the University. The contract estimated that Pavers would dispose of 1,400 tons of soil, whereas the actual amount disposed of was 8,071.29 tons. The contract estimated that Pavers would remove and dispose of 1,200 gallons of seepage water, whereas the actual amount removed and disposed of was 173,900 gallons. Pavers claimed that these overruns increased the amounts due under the contract by $184,127.60 for soil disposal, $673,530 for seepage water removal, and $595,815 for seepage water disposal.

On November 5, 2003, Pavers faxed a letter to the University's consultant stating that Pavers was experiencing substantial over-runs in the removal of the contaminated materials. However, Pavers did not submit a "Change Order" for these overruns until after the project was completed. The University's lead project manager, Tracy Aksamit, testified that it was anticipated at the outset that a change order would be issued after the project was over in order to take into account any increases or decreases in quantities. Aksamit stated that it was not necessary for Pavers to submit a change order before doing the work.

The district court found that "[t]he University's consultant and inspector" were aware of the cost overruns because they *404 were on the project site regularly. It further found that despite having knowledge of the overruns, the University instructed Pavers to proceed with the work because the project needed to be completed as quickly as possible.

Based on the unit prices submitted in its bid and the quantities of work performed, Pavers sought payment in the total amount of $1,714,996.40. However, based on its interpretation of the contract, the University did not pay the unit prices bid by Pavers for work units 9 through 11. Instead, the University paid a total of $379,336.54, which it claimed was fair and equitable for the work done on the contract.

Pavers filed a claim with the State Claims Board to compel full payment. The board notified Pavers that pursuant to Neb.Rev.Stat. § 81-8,305 (Reissue 2003), either party could object in writing to submission of the dispute to the board and initiate an action in the district court for Lancaster County. Pavers then filed a written objection to submission of the dispute to the board and initiated this breach of contract action in the district court.

The University moved to dismiss, claiming that § 81-8,305 is unconstitutional because it allows a claimant to initiate an action in the district court in violation of article VIII, § 9, of the Nebraska Constitution. The court found the statute to be constitutional, and the University's motion was overruled.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ACI Worldwide Corp. v. Baldwin Hackett & Meeks
296 Neb. 818 (Nebraska Supreme Court, 2017)
Nautilus Ins. Co. v. Cheran Investments
Nebraska Court of Appeals, 2014
Gridiron Mgmt. Group v. Travelers Indemnity Co.
286 Neb. 901 (Nebraska Supreme Court, 2013)
Yant v. City of Grand Island
784 N.W.2d 101 (Nebraska Supreme Court, 2010)
Davenport Ltd. v. 75th & Dodge I
780 N.W.2d 416 (Nebraska Supreme Court, 2010)
Kuhn v. WELLS FARGO BANK OF NEBRASKA
771 N.W.2d 103 (Nebraska Supreme Court, 2009)
Kruid v. Farm Bureau Mut. Ins. Co.
770 N.W.2d 652 (Nebraska Court of Appeals, 2009)
Agena v. Lancaster Cty. Bd. of Equal.
276 Neb. 851 (Nebraska Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
755 N.W.2d 400, 276 Neb. 559, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pavers-inc-v-bd-of-regents-of-univ-of-ne-neb-2008.