Patriot Contracting, LLC and Stephen J. Friedman v. Mid-Main Properties, LP

CourtCourt of Appeals of Texas
DecidedApril 28, 2022
Docket14-20-00724-CV
StatusPublished

This text of Patriot Contracting, LLC and Stephen J. Friedman v. Mid-Main Properties, LP (Patriot Contracting, LLC and Stephen J. Friedman v. Mid-Main Properties, LP) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Patriot Contracting, LLC and Stephen J. Friedman v. Mid-Main Properties, LP, (Tex. Ct. App. 2022).

Opinion

Affirmed and Opinion filed April 28, 2022.

In The

Fourteenth Court of Appeals

NO. 14-20-00724-CV

PATRIOT CONTRACTING, LLC AND STEPHEN J. FRIEDMAN, Appellants

V.

MID-MAIN PROPERTIES, LP, Appellee

On Appeal from the 113th District Court Harris County, Texas Trial Court Cause No. 2017-19892

OPINION

Patriot Contracting, LLC and Stephen J. Friedman appeal the trial court’s order denying their motion to dismiss under the Texas Citizens Participation Act (“TCPA”), as well as the court’s finding that the motion was frivolous and intended solely for delay. The trial court determined among other things that the motion was untimely, and the primary issue in this appeal is whether factual allegations in appellee’s amended counterclaim triggered a new sixty-day deadline to file the motion. We hold that the trial court did not err in concluding that appellants’ motion was untimely because appellee’s eighth amended counterclaim did not allege new essential facts and therefore did not trigger a new sixty-day deadline in which to file the motion. We also conclude that the trial court did not abuse its discretion in finding that the motion was frivolous.

We affirm.

Background

Appellee Mid-Main Properties, LP is a commercial property developer. In 2014, Mid-Main hired appellant Patriot Contracting, LLC as the general contractor for a construction project in the Houston Midtown area. Appellant Stephen J. Friedman owns Patriot.

The project involved constructing four residential apartment towers above a common parking garage with retail space at ground level. Construction began in late 2014. According to Mid-Main, over the next two and one-half years, Patriot and its subcontractors performed defective work that caused significant damage and delay. Patriot also allegedly demanded excess payments from Mid-Main because Patriot had difficulty paying its subcontractors. Mid-Main claims that Patriot abandoned the project twice in April 2017, and Mid-Main terminated the contract after Patriot’s second abandonment.

During the project, Patriot submitted pay applications, which sought retainage amounts and represented that Patriot had paid its subcontractors amounts due. According to Mid-Main, however, Patriot did not substantially complete the work for which it sought payment and did not obtain unconditional releases and lien waivers from its subcontractors—both preconditions to earning the retainage. Based on Mid-Main’s alleged failure to pay the amounts requested in the applications,

2 Patriot recorded a mechanic’s lien against the project in May 2017. Patriot’s lien put Mid-Main at risk of defaulting on its construction loan. Mid-Main claims that Friedman repeatedly contacted Mid-Main’s construction lender in an unsuccessful attempt to buy Mid-Main’s loan and acquire the project at a significant discount.

Eventually, Mid-Main made its own arrangements with subcontractors to finish construction through “restart agreements.” According to Mid-Main, Friedman told subcontractors not to return to the project and advised them to demand retainage from Mid-Main in exchange for entering a restart agreement, even though Mid-Main had paid some retainage to Patriot previously. Because of Friedman’s and Patriot’s actions, Mid-Main contends it made duplicative retainage payments to subcontractors to resume construction. Nonetheless, the project construction was completed in February 2018.

Patriot sued one of its subcontractors in March 2017 and later added Mid- Main as a defendant. On June 16, 2017, Mid-Main filed a counterclaim against Patriot, in which Mid-Main asserted claims for common law fraud related to the allegedly false pay applications and for a declaratory judgment that Patriot’s lien was void.1 Mid-Main amended its counterclaim several times, adding and deleting claims over time. The key pleadings for our purposes are Mid-Main’s Seventh and Eighth Amended Counterclaims. Mid-Main filed its Seventh Amended Counterclaim on December 20, 2019. In that pleading, Mid-Main asserted the following claims: (1) breach of contract; (2) breach of warranty; (3) negligence; (4) negligent misrepresentation; (5) fraud; (6) personal liability of Friedman under Texas Property Code section 53.085 for signing false affidavits supporting the disputed pay applications; (7) breach of surety bonds; (8) declaratory judgment;

1 The underlying lawsuit also involves subcontractors and Patriot’s surety, Travelers, but claims related to these parties are not at issue.

3 (9) Friedman tortiously interfered with Mid-Main’s prospective relations by interfering with Mid-Main’s efforts to obtain additional financing for the project; and (10) Patriot and Friedman tortiously interfered with Mid-Main’s restart agreements with subcontractors after Patriot abandoned the project.2

Trial was scheduled to begin in early September 2020. Patriot requested an emergency continuance in August, seeking to continue trial until January 2021. The trial court granted the continuance in part, setting the case for trial on November 2, 2020.

On September 2, in anticipation of trial, Mid-Main filed its Eighth Amended Counterclaim. In that document, Mid-Main did not add any new claims, and it deleted two claims. Mid-Main, however, modified certain assertions in the “factual background” section, which we discuss in detail below.

Patriot filed another emergency motion for continuance on October 5, which the court denied. On October 9, however, the trial court granted another party’s continuance motion and reset trial for November 30, 2020, with pre-trial to occur November 18.

The following week, on October 14, Patriot and Friedman filed a “Motion to Dismiss, for Discovery Stay, and Stay of Trial Pursuant to the [TCPA].” A motion to dismiss a legal action under the TCPA must be filed not later than the sixtieth day after the date the legal action is served.3 Although Patriot and Friedman had not filed a TCPA motion to dismiss any of Mid-Main’s prior counterclaims, they

2 Friedman’s alleged personal liability under Property Code section 53.085 and alleged tortious interference with Mid-Main’s prospective relationships first appeared in Mid-Main’s Fourth Amended Counterclaim filed March 22, 2019. 3 See Tex. Civ. Prac. & Rem. Code § 27.003(b). Appellants filed their motion to dismiss within sixty days of service of Mid-Main’s Eighth Amended Counterclaim.

4 contended their motion was timely as to the Eighth Amended Counterclaim because that pleading alleged new claims and new wrongful acts. Patriot and Friedman contended that Mid-Main’s Eighth Amended Counterclaim contained “new allegations as to tortious interference, false pay applications, and fraudulent lien,” all of which were based on and in response to Friedman’s protected free speech and petition rights and thus should be dismissed. Due to the new alleged claims and acts, appellants asserted that the “TCPA clock was reset.”

Mid-Main responded to the TCPA motion to dismiss with three arguments: (1) the motion was untimely; (2) assuming the motion was timely, the challenged claims are not covered by the TCPA; and (3) further assuming the claims are covered by the TCPA, Mid-Main could establish a prima facie case for each challenged cause of action. Among other exhibits attached to its response, Mid-Main submitted a “redline” version of its Eighth Amended Counterclaim showing the changes made to its Seventh Amended Counterclaim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Akin v. Santa Clara Land Co., Ltd.
34 S.W.3d 334 (Court of Appeals of Texas, 2000)
James W. Paulsen v. Ellen A. Yarrell
455 S.W.3d 192 (Court of Appeals of Texas, 2014)
Estate of Paul Edward Check
438 S.W.3d 829 (Court of Appeals of Texas, 2014)
Homan v. Borman
19 S.W.2d 438 (Court of Appeals of Texas, 1929)
Gloria Hicks v. Group & Pension Administrators, Inc.
473 S.W.3d 518 (Court of Appeals of Texas, 2015)
Justin Jordan v. Benjamin Hall, III
510 S.W.3d 194 (Court of Appeals of Texas, 2016)
John David Adams v. Starside Custom Builders, Llc
547 S.W.3d 890 (Texas Supreme Court, 2018)
Bacharach v. Garcia
485 S.W.3d 600 (Court of Appeals of Texas, 2016)
ExxonMobil Pipeline Co. v. Coleman
512 S.W.3d 895 (Texas Supreme Court, 2017)
Cox Media Group, LLC v. Joselevitz
524 S.W.3d 850 (Court of Appeals of Texas, 2017)
Van Der Linden v. Khan
535 S.W.3d 179 (Court of Appeals of Texas, 2017)
Sullivan v. Tex. Ethics Comm'n
551 S.W.3d 848 (Court of Appeals of Texas, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Patriot Contracting, LLC and Stephen J. Friedman v. Mid-Main Properties, LP, Counsel Stack Legal Research, https://law.counselstack.com/opinion/patriot-contracting-llc-and-stephen-j-friedman-v-mid-main-properties-lp-texapp-2022.