Patrick Coal Corp. v. Office of Surface Mining Reclamation & Enforcement

661 F. Supp. 380, 27 ERC 1338, 27 ERC (BNA) 1338, 1987 U.S. Dist. LEXIS 5162
CourtDistrict Court, W.D. Virginia
DecidedMay 22, 1987
DocketCiv. A. 86-0039-A
StatusPublished
Cited by3 cases

This text of 661 F. Supp. 380 (Patrick Coal Corp. v. Office of Surface Mining Reclamation & Enforcement) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Patrick Coal Corp. v. Office of Surface Mining Reclamation & Enforcement, 661 F. Supp. 380, 27 ERC 1338, 27 ERC (BNA) 1338, 1987 U.S. Dist. LEXIS 5162 (W.D. Va. 1987).

Opinion

MEMORANDUM OPINION

GLEN M. WILLIAMS, District Judge.

The plaintiff, Patrick Coal Company (Patrick), seeks review of the decision of an administrative law judge denying plaintiff’s request for temporary relief from a Notice of Violation (NOV) and Cessation Order (CO) which the defendant, Office of Surface Mining Reclamation and Enforcement (OSM), issued to the plaintiff. The court has jurisdiction pursuant to 30 U.S.C. § 1276 and 28 U.S.C. § 1331.

BACKGROUND

From 1979 to June, 1982, Patrick operated an underground mine known as Middle Creek No. 6 at Poplar Gap, in Buchanan County, Virginia. Patrick conducted its mining operations in the Blair Seam of coal. However, at the time Patrick began operations, pre-existing benches and access roads surrounded the Blair Seam. Specifically, the pre-existing areas which Patrick admitted it used in its mining operations were (1) a portion of the pre-existing bench on the Blair Seam level where it located its portals; (2) the area below the Blair Seam which it used for a stockpile and load-out; and (3) two access roads. In addition, other pre-existing disturbed areas included an access road, leading from the Blair Seam bench to the Eagle Seam bench (hereinafter Eagle Seam access road) and the Eagle Seam bench. The Eagle Seam is located on the bench above the Blair Seam.

In 1982 Patrick engaged an independent surveyor, John Munsey, to determine the total surface area which the operation encompassed. After including the disturbed area from the Blair bench, the stockpile and load-out area, and the two access roads, Munsey concluded the total surface acreage was 1.7 acres. Relying on Munsey’s calculations, on March 16, 1982, Patrick requested that the Virginia Division of Mined Land Reclamation (DMLR) release it from its permit and bond because the mine was less than two (2) acres. On June 9, 1982, DMLR released Patrick’s permit and bond after concluding that Patrick was eligible for the Two-Acre Exemption.

On November 25, 1985, OSM inspectors inspected Patrick’s Middle Creek Mine No. 6 as part of its two-acre task force. One inspector estimated the affected area to be 2.5 acres and found that Patrick had failed to perform certain reclamation work. In estimating the surface area affected, OSM included not only the area previously included in Munsey’s survey, but also included the Eagle Seam access road, leading from the Blair Seam to the Eagle Seam bench, and the Eagle Seam bench itself. Patrick claims that OSM should not have included these additional areas because they were pre-existing. The inspectors, however, found that the Eagle bench contained a diversion ditch which mines use to keep water off the deep mine operating on a lower bench. The inspectors further determined that the access roads and all *382 three benches were connected together and all part of a workable mine design. Additionally, the inspectors estimated that all the disturbances were approximately the same age.

OSM issued a NOV (No. 85-132-523-006) on November 27, 1985 for the reclamation work Patrick had not completed. OSM, however, did not notify the state as prescribed in 30 U.S.C. § 1271(a). On December 23, 1985, Patrick filed an application for review and a Request for Temporary Relief with the Department of Interior, but before an AU considered its requested relief, OSM issued a cessation order (No. 86-132-523-002) on January 6, 1986. On January 15, 1986, Patrick filed a Request for Temporary Relief from the cessation order and on February 4, 1986, filed an Application for Review with regard to the cessation order. On February 3, 1986, Administrative Law Judge Joseph E. McGuire denied Patrick’s temporary relief request. Pursuant to 30 U.S.C. § 1276(a), Patrick filed its complaint in the United States District Court for the Western District of Virginia on February 20, 1986 requesting this court to temporarily enjoin OSM from enforcing the cessation order and the NOV.

OPINION

The issue before the court is whether this court should temporarily enjoin OSM from enforcing the CO and NOV at Patrick’s Middle Creek No. 6 Mine. The Surface Mining Act specifically authorizes district courts to review the decision of an AU and to grant temporary relief from the NOV and/or CO. See 30 U.S.C. § 1276(a)(2), (c). The Fourth Circuit has clearly set forth the standard by which the district court shall enjoin the Secretary:

(1) all parties to the proceedings have been notified and given an opportunity to be heard on a request for temporary relief;
(2) the person requesting such relief shows that there is substantial likelihood that he will prevail on the merits of the final determination of the proceeding; and
(3) such relief will not adversely affect the public health or safety or cause significant environmental harm to land, air, or water resources.

Virginia Surface Mining and Reclamation Association v. Andrus, 604 F.2d 312, 315 (4th Cir.1979). Indeed, the Fourth Circuit’s criteria is the same criteria which Congress adopted in 30 U.S.C. § 1276(c).

It is important to note, however, that a district court in reviewing a request for temporary relief applies a different standard of review than a district court which reviews an AU’s decision on the merits. In reviewing a decision of an AU on the merits or any other related order or decision, a district court must affirm if the findings are ‘supported by substantial evidence on the record considered as a whole.’ § 1276(b). An exception to this rule arises when a district court considers a request for temporary relief pending final determination. In this instance § 1276(c) directs the court to conduct its own examination of the criteria in § 1276(c) to determine if temporary relief is proper. See § 1276(c)(1), (2), and (3).

Harman Mining Corp. v. Office of Surface Mining, 659 F.Supp. 806, 809-10 (W.D.Va.1987). Accordingly, temporary relief is proper if Patrick establishes the criteria in § 1276(c). Criteria 1 and 3 are not in dispute. Therefore, this court’s ability to issue a permanent injunction turns upon Patrick’s showing that it is substantially likely to prevail on the merits.

Patrick claims that it is likely to succeed on the merits for several reasons:

1. That OSM has no jurisdiction over Patrick’s mining operations in Virginia because OSM delegated exclusive regulatory authority to Virginia (DMLR).
2. That, even if OSM has jurisdiction over Patrick, OSM exceeded its statutory authority under 30 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Al Hamilton Contracting Co. v. Kempthorne
639 F. Supp. 2d 597 (W.D. Pennsylvania, 2009)
Pittston Co. v. Lujan
798 F. Supp. 344 (W.D. Virginia, 1992)
Harman Mining Corp. v. Hodel
662 F. Supp. 629 (W.D. Virginia, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
661 F. Supp. 380, 27 ERC 1338, 27 ERC (BNA) 1338, 1987 U.S. Dist. LEXIS 5162, Counsel Stack Legal Research, https://law.counselstack.com/opinion/patrick-coal-corp-v-office-of-surface-mining-reclamation-enforcement-vawd-1987.