Patagonia Area Resource Alliance v. Usfs

CourtCourt of Appeals for the Ninth Circuit
DecidedMay 15, 2024
Docket23-16167
StatusUnpublished

This text of Patagonia Area Resource Alliance v. Usfs (Patagonia Area Resource Alliance v. Usfs) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Patagonia Area Resource Alliance v. Usfs, (9th Cir. 2024).

Opinion

FILED NOT FOR PUBLICATION MAY 15 2024 UNITED STATES COURT OF APPEALS MOLLY C. DWYER, CLERK U.S. COURT OF APPEALS

FOR THE NINTH CIRCUIT

PATAGONIA AREA RESOURCE No. 23-16167 ALLIANCE; et al., D.C. No. 4:23-cv-00280-JGZ Plaintiffs-Appellants,

v. MEMORANDUM*

UNITED STATES FOREST SERVICE; KERWIN S. DEWBERRY, Forest Supervisor, Coronado National Forest,

Defendants-Appellees,

and

ARIZONA STANDARD LLC; SOUTH32 HERMOSA, INC., AKA Arizona Minerals, Inc.,

Intervenor-Defendants- Appellees.

Appeal from the United States District Court for the District of Arizona Jennifer G. Zipps, District Judge, Presiding

Argued and Submitted March 25, 2024 Pasadena, California

* This disposition is not appropriate for publication and is not precedent except as provided by Ninth Circuit Rule 36-3. Before: RAWLINSON, LEE, and BRESS, Circuit Judges.

Patagonia Area Resource Alliance, et al. (Appellants), appeal the district

court’s denial of their motion for a preliminary injunction against drilling activities

on two mining projects located within the Coronado National Forest, Arizona

Standard LLC’s Sunnyside Project and South32 Hermosa Inc.’s Flux Canyon

Project. We have jurisdiction pursuant to 28 U.S.C. § 1292 and we affirm in part

and dismiss in part.

A district court’s preliminary injunction order “is subject to limited review

and will be reversed only if the district court ‘abused its discretion or based its

decision on an erroneous legal standard or on clearly erroneous findings of fact.’”

Save Our Sonoran, Inc. v. Flowers, 408 F.3d 1113, 1120–21 (9th Cir. 2005), as

amended (citation omitted). In determining whether a party is entitled to a

preliminary injunction, the court considers likelihood of success on the merits,

irreparable harm, the balance of equities, and the public interest. See Winter v. Nat.

Res. Def. Council, Inc., 555 U.S. 7, 20 (2008).1

1. The district court did not abuse its discretion in concluding that

1 At oral argument, the parties agreed that drilling for the Flux Canyon Project had been completed, rendering this portion of the appeal moot. See Native Vill. of Nuiqsut v. Bureau of Land Mgmt., 9 F.4th 1201, 1208–09 (9th Cir. 2021). We dismiss the appeal as to this project. 2 Appellants were unlikely to succeed on the merits of their claims under the

National Environmental Policy Act (NEPA).

Addressing the Sunnyside Project, Appellants argue that the United States

Forest Service (USFS) inadequately considered the cumulative effects of the now

completed Flux Canyon Project, in addition to two other upcoming projects. We

disagree. The USFS took a hard look at the cumulative impact in the table

contained in its environmental assessment (EA), and was not required to separately

discuss the Flux Canyon Project in its narrative analyses. See Cascadia Wildlands

v. Bureau of Indian Affairs, 801 F.3d 1105, 1112 (9th Cir. 2015). The USFS did

not arbitrarily omit the Hermosa Critical Minerals Project (CMP) from its EA

because the available information—which came largely from press releases that

included neither a project timeline nor a plan of operations—was too speculative to

trigger a duty to supplement the EA. See North Idaho Cmty. Action Network v.

Dep’t of Transp., 545 F.3d 1147, 1154–55 (9th Cir. 2008) (requiring a

supplemental analysis if “there are significant new circumstances or information,”

unless the information is not sufficient to “meaningfully evaluate the

environmental impacts of any potential [project]”) (citation omitted).2 And the

2 This determination is without prejudice to Appellants’ ability to seek a supplemental analysis if sufficient information becomes available to trigger the USFS’s obligation under 40 C.F.R. § 1502.9(d)(1)(ii). We do not agree with the 3 EA’s analysis of the Hermosa Project was consistent with all available information

that warranted “meaningful consideration” from the agency. Environmental Prot.

Info. Ctr. v. USFS, 451 F.3d 1005, 1014 (9th Cir. 2006).

Next, Appellants contend that the USFS failed to take a “hard look” at the

impact the Sunnyside Project would have on the Mexican spotted owl. However,

the USFS analyzed the project’s temporary impact on the owl, observing that the

affected portion of the owl’s habitat was “relatively small,” and would be

“reclaimed and restored.” The USFS also estimated the project’s ground-level

noise impact, and prohibited any drilling activities during the owl’s nesting season.

Although Appellants point to shortcomings contained in studies relied on by the

USFS, those shortcomings did not impact the USFS’s ultimate analysis. See Earth

Island Inst. v. USFS, 351 F.3d 1291, 1301 (9th Cir. 2003) (“[A]n agency is entitled

to wide discretion in assessing the scientific evidence, . . . [and] courts must defer

to the informed discretion of the responsible federal agencies. . . .”) (citation

omitted).

Finally, Appellants assert that the USFS failed to reasonably evaluate

USFS’s position that it may delay consideration of the cumulative impact of the Sunnyside Project and the Hermosa CMP until it conducts the approval process for the Hermosa CMP. 4 the baseline conditions of the groundwater in the Sunnyside Project area. But

baseline conditions need not be directly measured if they were evaluated under

another reasonable method. See Or. Nat. Desert Ass’n v. Rose, 921 F.3d 1185,

1191 (9th Cir. 2019). The USFS’s reliance on studies conducted within the

Cienega Creek Basin was reasonable, especially when the method suggested by

Appellants would require performance of the very drilling activities to which they

object. And because NEPA “does not require adherence to a particular analytic

protocol,” we defer to the USFS’s chosen method. Id. (citation omitted).

2. The district court did not abuse its discretion in concluding that the

Sunnyside Project would not cause irreparable harm to the Mexican spotted owl or

to the underlying environs. The district court concluded that any effects on the

owl’s local population will be “short-term,” and the Sunnyside Project proposes

reclamation of all affected areas. See Drakes Bay Oyster Co. v. Jewell, 747 F.3d

1073, 1090 (9th Cir. 2014), as amended (explaining that “short-term harms” do not

“implicate NEPA”) (citation omitted).

3. The district court did not abuse its discretion in deciding that the

balance of equities and public interest was not favorable to either party. Although

we recognize an interest in “preserving nature and avoiding irreparable

environmental injury” over economic concerns, All. for the Wild Rockies v.

5 Cottrell, 632 F.3d 1127, 1138 (9th Cir. 2011) (citation omitted), that consideration

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Save Our Sonoran, Inc. v. Flowers
408 F.3d 1113 (Ninth Circuit, 2005)
Cascadia Wildlands v. Bureau of Indian Affairs
801 F.3d 1105 (Ninth Circuit, 2015)
Drakes Bay Oyster Company v. Sally Jewell
747 F.3d 1073 (Ninth Circuit, 2013)
Onda v. Jeff Rose
921 F.3d 1185 (Ninth Circuit, 2019)
Alliance for Wild Rockies v. Cottrell
632 F.3d 1127 (Ninth Circuit, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Patagonia Area Resource Alliance v. Usfs, Counsel Stack Legal Research, https://law.counselstack.com/opinion/patagonia-area-resource-alliance-v-usfs-ca9-2024.