North Idaho Community Action Network v. United States Department of Transportation

545 F.3d 1147, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20260, 2008 U.S. App. LEXIS 21002
CourtCourt of Appeals for the Ninth Circuit
DecidedOctober 6, 2008
Docket08-35283
StatusPublished
Cited by69 cases

This text of 545 F.3d 1147 (North Idaho Community Action Network v. United States Department of Transportation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Idaho Community Action Network v. United States Department of Transportation, 545 F.3d 1147, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20260, 2008 U.S. App. LEXIS 21002 (9th Cir. 2008).

Opinion

PER CURIAM:

Plaintiff North Idaho Community Action Network (“NICAN”) appeals the district court’s grant of summary judgment in favor of defendants United States Department of Transportation (the “DOT”), Federal Highway Administration, and Idaho Transportation Department (collectively, the “Agencies”). NICAN challenges a proposed highway construction project on a portion of U.S. Highway 95 located in northern Idaho. NICAN claims that the Agencies violated the National Environmental Policy Act (“NEPA”), 42 U.S.C. § 4321 et seq., and Section 4(f) of the Department of Transportation Act, 49 U.S.C. § 303(c). We affirm in part, reverse in part, and remand with instructions.

FACTS AND PROCEDURAL HISTORY

U.S. Highway 95 (“US-95”) currently runs through the heart of downtown Sand-point, Idaho, and is the only highway that ties northern Idaho to southern Idaho. The proposed highway construction project (the “Project”) will improve US-95 in and around Sandpoint.

The Project will be funded and constructed in four separate phases. The first, second, and fourth phases involve widening the existing highway to four lanes. The third phase involves realigning an approximate two-mile stretch of US-95 to create a byway that will route the highway to the east of Sandpoint and remove through-traffic from the downtown Sand-point area. Because the Agencies deem the third phase to be the most important phase of the Project, the Agencies have proceeded with that phase first.

In September 1999, the Agencies approved a final environmental impact statement (the “1999 EIS”) for the Project. In May 2000, the Agencies issued a record of decision (the “ROD”) for the Project. In the ROD, the Agencies selected the “Sand Creek Byway” as the preferred alternative for the third phase of the Project. As initially planned in the 1999 EIS, the Sand Creek Byway involved constructing two miles of new two-lane highway along the east side of Sand Creek, building a partial interchange/bridge structure over Sand *1152 Creek and Bridge Street, and building a full diamond interchange at the junction of US-95 and State Highway 200.

In April 2005, the Agencies released an environmental assessment (the “2005 EA”) that included various changes to the Project design described in the 1999 EIS. These changes all relate to the third phase of the Project, the Sand Creek Byway, and were made in response to input from various members of the local community. The changes include traffic design modifications — such as building additional off-ramps and adding a third lane for safer merging — as well as aesthetic improvements and mitigation measures — such as constructing a pedestrian and bicycle pathway along Sand Creek and building three artificial habitat enhancement areas in Sand Creek. The 2005 EA concluded that the changes to the Project design would not have significant impacts beyond those already considered in the 1999 EIS. Based on this conclusion, the Agencies issued a Finding of No Significant Impact (“FON-SI”).

In August 2006, the Agencies prepared an environmental reevaluation (the “2006 Reevaluation”) covering the Project. The 2006 Reevaluation set forth additional changes to the Project design and assessed possible environmental effects of those changes. The majority of the changes involve dredging Sand Creek and will result in the removal of approximately 17,035 cubic yards of material from Sand Creek. The 2006 Reevaluation concluded that there was no additional significant impact and that neither a supplemental environmental impact statement (“SEIS”) nor an environmental assessment (“EA”) was required.

In July 2005, after the Agencies released the 2005 EA and issued its FONSI determination, but before the Agencies prepared the 2006 Reevaluation, NICAN filed suit in the district court challenging the Agencies’ approval of the Project. On the parties’ cross-motions for summary judgment, the district court granted summary judgment in favor of the Agencies and against NICAN.

NICAN moved for an injunction pending appeal, which the district court denied. NICAN then sought and obtained an injunction pending appeal from a motions panel of this court. After oral argument in this expedited appeal, we lifted the injunction and allowed construction of the Sand Creek Byway to commence. This Opinion sets forth the explanation for our decision.

STANDARD OF REVIEW

We review a district court’s grant of summary judgment de novo. Nw. Ecosystem Alliance v. U.S. Fish & Wildlife Serv., 475 F.3d 1136, 1140 (9th Cir. 2007). The Administrative Procedure Act (“APA”) provides authority for the court’s review of decisions under NEPA and Section 4(f) of the Department of Transportation Act, 49 U.S.C. § 303(c). See Pit River Tribe v. U.S. Forest Serv., 469 F.3d 768, 778 (9th Cir.2006); Alaska Ctr. for the Env’t v. Armbrister, 131 F.3d 1285, 1288 (9th Cir.1997). Under the APA, a reviewing court may set aside agency actions that are “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A). As this court recently explained:

Review under the arbitrary and capricious standard is narrow, and we do not substitute our judgment for that of the agency. Rather we will reverse a decision as arbitrary and capricious only if the agency relied on factors Congress did not intend it to consider, entirely failed to consider an important aspect of the problem, or offered an explanation that runs counter to the evidence before the agency or is so implausible that it *1153 could not be ascribed to a difference in view or the product of agency expertise.

Lands Council v. McNair, 537 F.3d 981, 987 (9th Cir.2008) (en banc) (internal quotations and citations omitted).

DISCUSSION

I. NEPA

“NEPA ‘is our basic national charter for protection of the environment.’ ” Ctr. for Biological Diversity v. Nat’l Highway Traffic Safety Admin., 538 F.3d 1172, 1185(9th Cir.2008). Although NEPA does not impose any substantive requirements on federal agencies, it does impose procedural requirements. See Lands Council, 537 F.3d at 1000. Through these procedural requirements, NEPA seeks to make certain that agencies “ ‘will have available, and will carefully consider, detailed information concerning significant environmental impacts,’ and ‘that the relevant information will be made available to the larger [public] audience.’ ” Id. (quoting Robertson v. Methow Valley Citizens Council,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
545 F.3d 1147, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20260, 2008 U.S. App. LEXIS 21002, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-idaho-community-action-network-v-united-states-department-of-ca9-2008.