Passadumkeag Mountain Friends v. Board of Environmental Protection

2014 ME 116, 102 A.3d 1181, 2014 Me. LEXIS 123, 2014 WL 5335281
CourtSupreme Judicial Court of Maine
DecidedOctober 21, 2014
DocketDocket BEP-13-413
StatusPublished
Cited by55 cases

This text of 2014 ME 116 (Passadumkeag Mountain Friends v. Board of Environmental Protection) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Passadumkeag Mountain Friends v. Board of Environmental Protection, 2014 ME 116, 102 A.3d 1181, 2014 Me. LEXIS 123, 2014 WL 5335281 (Me. 2014).

Opinion

JABAR, J.

[¶ 1] Passadumkeag Mountain Friends (PMF), a Maine nonprofit corporation, A-exander F. Cuprak, and Rhonda Cuprak appeal from a decision by the Board of Environmental Protection (the Board) granting Passadumkeag Windpark, LLC, (PW) a permit to develop a wind farm on property owned by Penobscot Forest, LLC, (PF) located on Passadumkeag Ridge in Grand Falls Township. The Board’s decision followed PW and PF’s appeal from the decision of the Department of Environmental Protection (the Department) denying the requested permit. PMF and the Cupraks contend that we should treat the decision of the Department, rather than the decision of the Board, as operative for purposes of appellate review. The Cupraks also contend that, even if the Board’s decision is reviewed on appeal, the record does not support that decision, and that they were denied due process because of ex parte communications between the Board, PW, and PF during the application process. We disagree with these contentions and affirm the Board’s decision.

I. ADMINISTRATIVE PROCESS

[¶ 2] In February 2012, PW applied to the Department for an expedited wind energy development permit pursuant to the Natural Resources Protection Act, 38 M.R.S. §§ 480-A to 480-HH (2012). See 35-A M.R.S. § 3451(4) (2013); 38 M.R.S. § 480-C. It also applied for the Department’s approval of the project pursuant to the site location of development statute. See 38 M.R.S. §§ 482(2)(A), 483-A (2013). Through these applications, PW sought approval to construct a wind farm on Passa-dumkeag Ridge in Grand Falls Township. The project features fourteen 140-meter-high turbines, access roads, a crane path, a meteorological tower, and electrical collection infrastructure including an electrical substation, an operations and maintenance building in Greenbush, and a 17-mile transmission line.

*1184 [¶ 8] While considering PWs application, the Department’s staff made two site visits and held two public meetings. The Department did not hold a public hearing, concluding that there was insufficient “credible conflicting technical information” that would warrant a public hearing. See 38 M.R.S. § 345-A(l-A) (2013); 2 C.M.R. 06 096 002-3 § 7(B) (2013). During the meetings, the Department heard concerns from numerous members of the public, whom it labeled “interested persons,” including the Cupraks, and several individual members of PMF. See 2 C.M.R. 06 096 002-1 § 1(J) (2013).

[¶ 4] The Department ultimately denied the application, finding that construction on Passadumkeag Ridge would dramatically change the undeveloped view of Passadumkeag Mountain from Saponac Pond, and concluding that the project would have an unreasonable adverse impact on the scenic character and existing uses related to the scenic character of Saponac Pond, a scenic resource of state or national significance (SRSNS). The Department also concluded that, with the exception of an unreasonable adverse impact on the scenic character and existing uses of Saponac Pond, the applicant had met all permit criteria. After denial of the application, PW, the applicant, and PF, the owner of the land on which the wind park would be built, both filed timely notices of appeal to the Board. See 38 M.R.S. § 344(2-A) (2013). The Cupraks then filed a letter with the Board stating their objections to the application and the appeal.

[¶ 5] While it was reviewing the Department’s decision, the Board sent several letters to PW regarding the issues and evidence that it would consider, without sending copies to the Cupraks or other interested parties. At its March 21, 2013, meeting, the Board heard arguments from PW, PF, the Department’s staff, and the Cupraks, but it did not take any additional evidence or augment the administrative record.

[¶ 6] On August '20, 2013, the Board issued “Findings of Fact and Order on Appeal.” In it, the Board stated that the scenic consultants hired by PW and the Department “agree that the project will not have an unreasonable adverse impact on the scenic character of Saponac Pond,” and that it found these assessments credible. Based on this determination, the Board granted the permit. Both PMF and the Cupraks timely appealed. See 38 M.R.S. § 346(4) (2013); M.R.App. P. 2(b)(3).

II. DISCUSSION

[¶ 7] Appellants raise three fundamental issues on appeal: (1) whether the decision of the Department, rather than the Board, is the operative decision on appeal; (2) whether there is sufficient evidence to support the Board’s decision; and (3) whether the Cupraks were denied due process as a result of ex parte communications between the Board, PW, and PF during the application process. 1

A. Operative Decision

[¶ 8] PMF and the Cupraks argue that the Board erred in reviewing the Department’s decision de novo, and that the Department, as fact-finder, issues the operative decision for appellate review. Appellants base their arguments on the language of 38 M.R.S. § 341-D (2013), which details the Board’s responsibilities and *1185 duties in reviewing permit applications. Pursuant to section 341~D(4)(D), which applies specifically to “[l]icense or permit decisions regarding an expedited wind energy development,” the Board may supplement the record with additional information at its discretion. Section 341-D(4)(D) does not expressly provide that the Board is not bound by the Department’s findings, unlike section 341-D(4)(A), which pertains to other permit and license appeals. PMF and the Cupraks argue that this omission is an indication of the Legislature’s intent to have the Board give deference to the Department’s findings.

[¶9] However, in Concerned, Citizens to Save Roxbury v. Board of Environmental Protection, we determined that the Board had engaged in an independent review of the record, which included not only the administrative record before the Department, but also some supplemental evidence presented by the parties. 2011 ME 39 ¶ 17, 15 A.3d 1263. Based on that determination, we concluded that the Board’s decision was the operative decision for our appellate review. Id. In our discussion, we noted that the Department’s rules for processing appeals provided that the Board, “is not bound by the [Department’s] findings of fact or conclusions of law.” Id. ¶ 16 (quoting 2 C.M.R. 06 096 002-12 § 24(B)(7) (2003)).

[¶ 10] Although the Board in this case did not supplement the administrative record in the course of its review, it engaged in an independent analysis of the record, made factual findings regarding the credibility of various experts, and concluded that the proposed development would not have an unreasonable adverse impact on Saponac Pond. See 2 C.M.R. 06 096 002-12 § 24(G) (2013) (providing that the “Board is not bound by the [Department’s] findings of fact or conclusions of law”). The Board acted as both fact-finder and decision-maker pursuant to agency rules, and did not err in so doing. The Board’s decision is the operative decision for purposes of this appeal.

B. The Board’s Findings and Conclusions

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2014 ME 116, 102 A.3d 1181, 2014 Me. LEXIS 123, 2014 WL 5335281, Counsel Stack Legal Research, https://law.counselstack.com/opinion/passadumkeag-mountain-friends-v-board-of-environmental-protection-me-2014.