Pasker, Gould, Ames & Weaver, Inc. v. Morse

887 P.2d 872, 254 Utah Adv. Rep. 12, 1994 Utah App. LEXIS 183, 1994 WL 705509
CourtCourt of Appeals of Utah
DecidedDecember 15, 1994
Docket940015-CA
StatusPublished
Cited by12 cases

This text of 887 P.2d 872 (Pasker, Gould, Ames & Weaver, Inc. v. Morse) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pasker, Gould, Ames & Weaver, Inc. v. Morse, 887 P.2d 872, 254 Utah Adv. Rep. 12, 1994 Utah App. LEXIS 183, 1994 WL 705509 (Utah Ct. App. 1994).

Opinion

GREENWOOD, Judge:

Appellant James A. Morse, Jr. (Morse) appeals the bench trial judgment against him, awarding damages for breach of contract. We affirm.

I. BACKGROUND 1

In April of 1987, Morse entered into a contract (the Contract) with Holland-Pasker & Associates (Holland-Pasker), for architectural services on a five-story atrium-style office building to be built on property owned by Morse. This building was identified at trial as Building A.

The Contract called for a fixed fee of $88,-000 to be paid in installments upon completion of four phases of the project as follows: 2 (1) 15% for the schematic design phase; (2) *874 15% for the design development phase; (3) 50% for the construction document phase; and (4) 20% for the construction phase. The Contract stipulated that Holland-Pasker could not proceed beyond the schematic design phase until payment for that phase was received. The Contract further provided that payment for the schematic design phase was due upon the occurrence of any one of the following events: (1) the owner obtains financing for the project; (2) the owner sells the property; or (3) the property buyer assumes responsibility for payment of the Contract.

During the course of the project, Morse worked closely with Holland-Pasker, visiting its offices an average of three times a week. Because Morse was unable to obtain financing on the building as originally designed, he asked Holland-Pasker to design a smaller building for the property. This smaller building was identified at trial as Building B. The Contract applied only to services associated with Building A.

Holland-Pasker provided Morse with numerous plans and renderings for both Building A and Building B. These included specific floor plans which Morse used in seeking potential tenants and investors. The floor plans were highly detailed and included the structural, mechanical, and electrical elements of each floor.

Ultimately, neither Building A nor Building B was built on the property. In 1991, Morse entered into a joint venture agreement with South Towne Towers, whereby Morse sold the property to South Towne Towers in exchange for an ownership interest in the company. South Towne Towers eventually constructed a building on the property, but on a different site than envisioned for either Building A or Building B. Despite numerous billings, Morse paid Holland-Pasker only $3,000 for its architectural services.

Pasker, Gould, Ames, & Weaver (Pasker) brought suit as successor-in-interest to Holland-Pasker, alleging breach of contract and quantum meruit. Pasker alleged it had completed the schematic design and design development phases of the Contract, and was therefore entitled to 30% of the $88,000 fixed fee, pursuant to the Contract.

After a one-day bench trial, the trial court entered the following findings of fact which are pertinent to this appeal:

(1) Pasker completed the schematic phase of the Contract, during which Morse worked with Pasker on a daily basis.
(2) At the end of the schematic design phase Morse requested that Pasker proceed immediately to the design development phase in an effort to secure tenants for the office building.
(3) Pasker complied with this request and completed the design development phase.
(4) Pasker is entitled to 30% ($26,400) of the basic compensation pursuant to the terms of the Contract for completing both the schematic design and the design development phases.
(5) Pasker is also entitled to $3,581 for services of consultants and other reimbursable expenses.
(6) The project for which the services were provided was sold to a joint venture and project financing was obtained, satisfying the condition precedent for payment for the schematic phase.
(7) Morse has paid only $3,000 against the obligation, and has breached the Contract by failing to pay the full amount.
(8) Morse owes Pasker $26,981, plus interest.

The trial court concluded that Morse had breached the Contract by failing to make payment according to the terms of the Contract and that Morse had requested Pasker to perform architectural services that he knew or should have known were available only for compensation. The trial court entered judgment in favor of Pasker in the amount of $26,981, plus interest, for a total of $33,936.92.

II. ISSUES

We address the following issues on appeal: (1) Did the trial court abuse its discretion by admitting evidence on the issue of Pasker’s right to payment for the design development phase of the Contract? (2) Are the findings of fact and evidence sufficient to constitute *875 waiver of a Contract provision, thus justifying payment for the design development phase? (3) Was the evidence sufficient to demonstrate that preconditions for payment on the schematic design phase had been met? (4) Was the evidence sufficient to conclude that work on the design development phase was completed? 3

III. STANDARD OF REVIEW

A trial court’s conclusions of law are reviewed on appeal for correctness. Saunders v. Sharp, 806 P.2d 198, 199-200 (Utah 1991) (per curiam). We review a trial court’s findings of fact under a clearly erroneous standard and will not lightly disturb those findings. Alta Indus. Ltd. v. Hurst, 846 P.2d 1282, 1286 (Utah 1993). To demonstrate that the trial court’s findings of fact are clearly erroneous, the appellant must first marshal all the evidence in support of those findings. Gillmor v. Wright, 850 P.2d 431, 433 (Utah 1993). Additionally, viewing the evidence in a light most favorable to the trial court, the appellant must demonstrate that the evidence is insufficient to support the findings of fact. Id. A trial court’s decisions regarding admission of evidence are generally accorded a good deal of discretion, State v. Pena, 869 P.2d 932, 938 (Utah 1994), and its decision on a motion to amend pleadings falls within the scope of its sound discretion. Westley v. Farmer’s Ins. Exch., 663 P.2d 93, 94 (Utah 1983).

IV. ANALYSIS

A. Recovery for the Design Development Phase

Morse argues that Pasker did not properly plead in its complaint for payment for the design development phase and that the trial court erred in tacitly allowing amendment of the pleadings by admitting evidence regarding work completed on that phase of the Contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In the Matter of the Estate of Juanita Valcarce (Valcarce v. Valcarce)
2013 UT App 95 (Court of Appeals of Utah, 2013)
Mid-America Pipeline Co. v. Four-Four, Inc.
2009 UT 43 (Utah Supreme Court, 2009)
Moran v. City of Del City
2003 OK 57 (Supreme Court of Oklahoma, 2003)
Harris v. IES Associates, Inc.
2003 UT App 112 (Court of Appeals of Utah, 2003)
Salt Lake Tribune Publishing Co. v. AT & T Corp.
320 F.3d 1081 (Tenth Circuit, 2003)
Pacific Development, L.C. v. Orton
1999 UT App 217 (Court of Appeals of Utah, 1999)
Bailey-Allen Co., Inc. v. Kurzet
945 P.2d 180 (Court of Appeals of Utah, 1997)
Castillo v. Atlanta Casualty Co.
939 P.2d 1204 (Court of Appeals of Utah, 1997)
Phillips v. Hatfield
904 P.2d 1108 (Court of Appeals of Utah, 1995)
C & Y CORP. v. General Biometrics, Inc.
896 P.2d 47 (Court of Appeals of Utah, 1995)
Living Scriptures, Inc. v. Kudlik
890 P.2d 7 (Court of Appeals of Utah, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
887 P.2d 872, 254 Utah Adv. Rep. 12, 1994 Utah App. LEXIS 183, 1994 WL 705509, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pasker-gould-ames-weaver-inc-v-morse-utahctapp-1994.