Parrish & Hazard's Appeal

83 Pa. 111, 1877 Pa. LEXIS 32
CourtSupreme Court of Pennsylvania
DecidedMay 7, 1877
StatusPublished
Cited by11 cases

This text of 83 Pa. 111 (Parrish & Hazard's Appeal) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parrish & Hazard's Appeal, 83 Pa. 111, 1877 Pa. LEXIS 32 (Pa. 1877).

Opinion

Mr. Justice Woodward

delivered the opinion of the court, May 7th 1877.

When the contracts were made under which the claims of the mechanics’ lien creditors are asserted in this proceeding, the furnace of the Dunbar Iron Company had been completed and in operation for many years. No work in the way of erection or construction had been done subsequently to 1870, when a furnace stack of stone had been torn down, and one of iron put up in its place. In the spring of 1872, the company requiring more power than the engines they had in use afforded, determined to introduce new machinery. Contracts were accordingly made with Robinson, Rea & Co. for a vertical engine ; with Brenneman & Ward for six boilers and their connected materials and fixtures; and with James M. Riter for a boiler-stack. For the balances remaining unpaid for the work done under their contracts the liens of these creditors were filed.

On the 5th of June 1875, the real estate of the Dunbar Iron Company was sold by the sheriff of Fayette county, by virtue of a levari facias in a judgment on a mortgage executed to Charles Parrish and Fisher Hazard as trustees, to secure bonds to be issued by the company to the amount of $400,000. The mortgage was dated the 1st day of June 1872, was acknowledged on the 20th of that month, and was recorded and became a lien on the 17th of July 1872. The trustees purchased the property at the sheriff’s sale for $155,000. As bonds amounting to about $300,000 had been negotiated and were outstanding, the whole fund was claimed on [120]*120distribution to be applicable to the mortgage-debt. The auditor to whom the claims of the parties were referred, appropriated the money to the extent of the balances due on the mechanics’ lien to their payment, and his report was confirmed by the Common Pleas. At the argument here, the right of the appellants to the amount thus appropriated was asserted on various grounds, and their views were pressed by their counsel with great vigor and great ability. The principal point urged was that the work done añd materials furnished by the appellees were not, by any fair construction of the statutes, subjects of mechanics’ liens.

It is very clear that the value of the furnace property was largely enhanced by the machinery and fixtures which the Dunbar Company obtained under their contracts with the lien creditors. The account . of Robinson, Rea & Co. amounted to $24,745.95 ; that of Brenneman & Ward to $9148.45 ;• and that of Riter to $473’6.80. It is very clear also that the structures supporting, enclosing and covering the machinery Avere put up substantially, for permanent purposes, and at heavy cost. The enclosing buildings were not erected for some months after the work of the appellees was completed, but they were necessary to the perfection of the general plan of the improvements and for the protection of the engine and boilers and their fixtures. The extent and importance of the structures may be shown by a condensation of the description of them in the audit- or’s report. The foundation of the new engine was solid masonry, ten feet square and six feet in depth. The house enclosing it, which Avas erected at the distance of about ninety-three feet from the furnace, was framed, weather-boarded, Avith windows in it, covered by a comb roof and thirty-five feet high. The boiler-house Avas built at about the same distance from the furnace as the engine-house. The two buildings Avere about forty-tAvo feet apart. The foundations of the boilers Avere seven Avails, each sixty-seven feet long, from eighteen inches to two feet thick, and from two to three and a half feet high. Brick walls were built on the stone foundations to the height of six feet, extending nearly to the tops of the boilers and enclosing them. Some three or four months after the boilers were set up, a frame building to cover and protect them Avas erected. It Avas supported by posts set on stones outside the boiler Avails', Avas strengthened by girders, plates and rafters, was weather-boarded from the eaves down to the brick wall, except in front of the boilers, and had a comb roof of boards. The iron boiler-stack, ninety feet high and ten and a half feet in diameter, Avas built on a stone foundation twenty feet square, deeply sunk in the ground, and raised ten feet above the surface. Extended and expensive as these improvements- were, it becomes an interesting as Avell as an important inquiry Avhether these creditors, Avhose contributions to the value of the Dunbar Company’s property have been so material, are within or Avithout the protection of laAvs which secure compen[121]*121sation to mechanics for their labor and property employed in the erection of buildings under all ordinary contracts.

Under the facts found by the auditor there is no room for doubt that all the improvements made were contemplated from the outset, and were all parts of one settled original design. Robinson, Rea & Co. began work on the engine at their shops in Pittsburgh on the 23d of April 1872, under a contract entered into previously. The order for the boilers, drum-heads and fixtures was received by Brenneman & Ward on the 5th of April, and they commenced their work on the 29th. Riter’s contract was entered into on the 10th of April, and the stack was begun sometime in the following June. "At the date of the record of the mortgage, therefore, all these parties were employed in the execution of their contracts.

As has been stated, the mortgage became a lien on the 17th of July 1872. When the first work was done on the ground did not precisely appear before the auditor, but the masonry for- the foundation of the boiler-stack was begun on the 16th of July. There was evidence that at least a week earlier excavations for the foundation had been commenced. The location for the boiler-stack and boilers had been fixed as early as the 6th of July, for the written contract with E. Gr. Lincoln for the masonry ivas made that day. It was decided in Pennock v. Hoover, 5 Rawle 291, under the Act of the 17th of March 1806, that the commencement of a building was the first work done on the ground for the foundation, as part of the work suitable and necessary for. its construction. By this rule, the erection of these structures was begun at least as early as the 16th of July 1872, one day before the mortgage ivas recorded. It is true that excavations for the engine were delayed until September,-but that work was merely a continuation of the work begun in July, and was part of the entire scheme of improvements that had been planned and matured in April. The notice given by breaking the ground for the boiler-stack was notice of all that ivas intended to be done in carrying into effect the details of a single enterprise definitely projected and arranged. All the structures were upon the furnace property ; all were to serve the purposes of the furnace ; all the c.ontracts had been made ; and the machinery had been in the course of construction nearly three months when the first masonry was laid. Inquiry by the trustees or by bondholders would have led to the disclosure of the whole scope of the improvements the company had in contemplation. And the duty of such inquiry was created by the work visibly done for the commencement of the buildings. If the claimants had a right to liens at all for machinery furnished for such detached and subsidiary use as theirs was applied to, they were entitled to them from the 16th of July 1872 ; they had precedence of the trust-mortgage not then recorded; and the claim for the engine was recoverable equally AYith the claims for the boilers and the boiler-stack.

[122]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Walker
28 Pa. D. & C.2d 625 (Lawrence County Court of Common Pleas, 1962)
Schroeter Bros. Hardware Co. v. Croatian "Sokol" Gymnastic Ass'n
58 S.W.2d 995 (Supreme Court of Missouri, 1933)
Roy Building & Loan Ass'n v. King
17 Pa. D. & C. 83 (Delaware County Court of Common Pleas, 1931)
Laurelton State Bank v. Boeger
12 Pa. D. & C. 412 (Centre County Court of Common Pleas, 1929)
George M. Newhall Engineering Co. v. Egolf
185 F. 481 (Third Circuit, 1911)
Pusey & Jones v. Pennsylvania Paper Mills
173 F. 634 (U.S. Circuit Court for the District of Middle Pennsylvania, 1909)
Kountz Bros. v. Consolidated Ice Co.
28 Pa. Super. 266 (Superior Court of Pennsylvania, 1905)
Kolb v. Reformed Episcopal Church of Reconciliation
18 Pa. Super. 477 (Superior Court of Pennsylvania, 1901)
Wheeler v. Pierce, Kelley & Co.
31 A. 649 (Supreme Court of Pennsylvania, 1895)
W. H. Harrison & Bro. v. Homœopathic Ass'n
19 A. 804 (Supreme Court of Pennsylvania, 1890)
Thomas v. Hinkle
17 A. 670 (Supreme Court of Pennsylvania, 1889)

Cite This Page — Counsel Stack

Bluebook (online)
83 Pa. 111, 1877 Pa. LEXIS 32, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parrish-hazards-appeal-pa-1877.