Paragon Industrial Applications, Inc., and RLI Insurance Company v. Stan Excavating, LLC

432 S.W.3d 542, 2014 WL 1795313, 2014 Tex. App. LEXIS 4809
CourtCourt of Appeals of Texas
DecidedMay 6, 2014
Docket06-14-00001-CV
StatusPublished
Cited by16 cases

This text of 432 S.W.3d 542 (Paragon Industrial Applications, Inc., and RLI Insurance Company v. Stan Excavating, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paragon Industrial Applications, Inc., and RLI Insurance Company v. Stan Excavating, LLC, 432 S.W.3d 542, 2014 WL 1795313, 2014 Tex. App. LEXIS 4809 (Tex. Ct. App. 2014).

Opinion

OPINION

Opinion by

Justice MOSELEY.

In Bowie County, Texas, Stan Excavating, LLC, sued Paragon Industrial Applications, Inc., and its bonding company, RLI Insurance Company, 1 alleging that Paragon failed to pay Stan Excavating for the work it had performed as Paragon’s subcontractor on a road construction project in Nash, Texas. Paragon filed a motion to compel arbitration, 2 arguing that Stan Excavating’s claims fell within the arbitration clause in a subcontract agreement between Paragon and Stan Excavating which mandates that this kind of dispute be heard in an arbitration to be conducted in San Luis Obispo, California. After a hearing, the trial court denied the relief sought by Paragon.

*546 On appeal, Paragon contends that the trial court erred in denying its motions because a valid arbitration agreement existed between the parties. 3 At first viewing, this appears to be a case that would be controlled by laws pertaining to arbitration. It is not. Rather, it is governed by the laws regarding agency.

We affirm the trial court’s judgment because there is some evidence supporting the trial court’s implied finding that David Hagood (who purported to sign the written agreement on behalf of Stan Excavating) lacked the sufficient authority to bind Stan Excavating to the agreement that contained the arbitration clause.

I. Factual and Procedural Background

On November 11, 2011, Paragon intended itself to enter into a contractor/subcontractor agreement with Stan Excavating, wherein Paragon would be the general contractor and Stan Excavating would be the prime subcontractor responsible for hiring the other subcontractors and overseeing the work on the Brinlee Road construction project in Nash, Texas. Hagood executed the contract on Stan Excavating’s behalf, and Paragon’s president, Joyce LeFrancois, executed it on Paragon’s behalf. Hagood was identified in that contract as a co-owner of Stan Excavating. The agreement required Stan Excavating to perform all of the work on and provide all the materials for the Brinlee Road Project. Under the agreement, Stan Excavating would be paid $1,004,865.35 for providing “all labor, equipment, materials, tools, supervision^] and coordination to complete the work identified in the Scope of Work .... ” The specific scope of work stated, in pertinent part, that Stan Exca: vating, as subcontractor, would furnish “all labor, materials, equipment, transportation, taxes[,] and facilities per plans and specifications which shall include, but not be limited to ... [the] Stan Excavating Bid Proposal dated October 11, 2011[,] and [i]n accordance with the plans and specs for Contract # 08-79-04411 — Brinlee Road improvements, The City of Nash, TX.”

When the project was completed, a dispute arose when Paragon refused to pay $43,224.68 of Stan Excavating’s last invoice. When Stan Excavating demanded payment, Paragon informed Stan Excavating that it had paid the disputed funds directly to some of Stan Excavating’s subcontractors who had complained that Stan Excavating failed to pay them for the work they had performed on the project. Stan Excavating filed claims against Paragon for breach of contract, suit on sworn account, quantum meruit, and unjust enrichment. In response, Paragon filed a plea to the jurisdiction, a plea in abatement, and a motion to compel arbitration, arguing that Stan Excavating’s claims fell within the arbitration clause in the contract agreement between Paragon and Stan Excavating; accordingly, Paragon claimed the parties’ dispute must be heard in San Luis Obispo, California, as provided for in the agreement. In Stan Excavating’s amended motion to stay arbitration, it argued that (a) the subcontract agreement was not signed by a person authorized or empowered to enter into contracts on Stan Excavating’s behalf and (b) Stan Excavating’s claims did not fall within the scope of the arbitration clause because they were an action involving a third party. After a hearing, the trial court denied Paragon’s *547 pleas and motions, and this appeal followed.

II. Standard of Review

We review the trial court’s denial of a motion to compel arbitration for an abuse of discretion. See In re Labatt Food Serv., L.P., 279 S.W.3d 640, 643 (Tex.2009) (orig. proceeding); Cleveland Constr., Inc. v. Levco Constr., Inc., 359 S.W.3d 843, 851-52 (Tex.App.-Houston [1st Dist.] 2012, pet. dism’d) (explaining standards of review for arbitration appeals). Under this standard, we defer to the trial court’s factual determinations that are supported by the record and review legal questions de novo. Labatt Food Serv., L.P., 279 S.W.3d at 643.

“In evaluating a motion to compel arbitration, a court must determine first whether a valid arbitration agreement exists, and then whether the agreement encompasses the claims raised.” In re D. Wilson Constr. Co., 196 S.W.3d 774, 781 (Tex.2006) (orig. proceeding); see In re Kellogg Brown & Root, Inc., 166 S.W.3d 732, 737 (Tex.2005) (orig. proceeding). The party moving to compel arbitration bears the burden to show the existence of a valid agreement to arbitrate. J.M. Davidson, Inc. v. Webster, 128 S.W.3d 223, 227 (Tex.2003). Once a party establishes the existence of an arbitration agreement and that the claim falls within the scope of the arbitration agreement, the trial court must compel arbitration and stay its own proceedings unless the party opposing arbitration proves a defense precluding enforcement. In re C & H News Co., 133 S.W.3d 642, 645 (Tex.App.-Corpus Christi 2003, orig. proceeding).

A. Did Paragon satisfy its burden to show a valid agreement to arbitrate?

In its first point of error, Paragon contends that the trial court erred in denying its motions because it met its burden of establishing that there was a valid agreement to arbitrate.

In determining the validity of agreements to arbitrate, we generally apply ordinary principles of state contract law. In re Palm Harbor Homes, Inc., 195 S.W.3d 672, 676 (Tex.2006) (orig. proceeding). The elements of a valid contract are (1) an offer, (2) an acceptance, (3) a meeting of the minds, (4) each party’s consent to the terms, and (5) execution and delivery of the contract with the intent that it be mutual and binding. Prime Prods., Inc. v. S.S.I. Plastics, Inc., 97 S.W.3d 631, 636 (Tex.App.-Houston [1st Dist.] 2002, pet. denied). “Under generally accepted principles of contract interpretation, all writings that pertain to the same transaction will be considered together, even if they were executed at different times and do not expressly refer to one another.” DeWitt Cnty. Elec. Coop., Inc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Readyone Indus., Inc. v. Lopez
551 S.W.3d 305 (Court of Appeals of Texas, 2018)
in Re Esperanza Hughes
Court of Appeals of Texas, 2016
Kmart Stores of Texas, L.L.C. v. Ramirez
510 S.W.3d 559 (Court of Appeals of Texas, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
432 S.W.3d 542, 2014 WL 1795313, 2014 Tex. App. LEXIS 4809, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paragon-industrial-applications-inc-and-rli-insurance-company-v-stan-texapp-2014.