Papalote Creek v. CO River Auth

CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 16, 2021
Docket19-50850
StatusUnpublished

This text of Papalote Creek v. CO River Auth (Papalote Creek v. CO River Auth) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Papalote Creek v. CO River Auth, (5th Cir. 2021).

Opinion

Case: 19-50850 Document: 00515941160 Page: 1 Date Filed: 07/16/2021

IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT United States Court of Appeals Fifth Circuit

FILED No. 19-50850 July 16, 2021 Lyle W. Cayce Clerk

PAPALOTE CREEK II, L.L.C., formerly known as Papalote Creek Windfarm II, L.L.C.,

Plaintiff - Appellant

v.

LOWER COLORADO RIVER AUTHORITY,

Defendant - Appellee

************************************************************************

Plaintiff - Appellee

PAPALOTE CREEK II, L.L.C., formerly known as Papalote Creek Windfarm II, L.L.C.,

Defendant - Appellant

Appeal from the United States District Court for the Western District of Texas USDC No. 1:16-CV-1097 USDC No. 1:19-CV-284

Before DENNIS, ELROD, and COSTA, Circuit Judges. Case: 19-50850 Document: 00515941160 Page: 2 Date Filed: 07/16/2021

No. 19-50850 PER CURIAM:* This appeal concerns the proper interpretation of the long-term Power Purchase Agreement (PPA) between the parties and its provisions limiting the parties’ liability and damages in the event of breach of the agreement. This Court has twice before reversed district court orders compelling arbitration of the parties’ underlying disputes. First, this court held that the district court lacked jurisdiction to order arbitration of the question because at that time there was no dispute ripe for adjudication. See Lower Colo. River Auth. v. Papalote Creek II, L.L.C. (Papalote I), 858 F.3d 916 (5th Cir. 2017). Next, this court held that the parties’ underlying dispute did not fall within the scope of the PPA’s narrow arbitration clause. Papalote Creek II, L.L.C. v. Lower Colo. River Auth. (Papalote II), 918 F.3d 450 (5th Cir. 2019). In this appeal, we are called upon to decide whether, in a third action by the Lower Colorado River Authority (LCRA) seeking a declaratory judgment, the district court erred in interpreting the PPA and its key provisions to limit to $60 million LCRA’s liability for damages for failure to perform its material obligations under the agreement. We see no reversible error in the district court’s contractual interpretation and summary judgment rulings. Therefore, we AFFIRM the district court’s judgment. I. FACTUAL AND PROCEDURAL BACKGROUND The previous panels of this court, in Papalote I and Papalote II, described the factual and procedural background of these cases, in pertinent parts, as follows:

* Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4.

2 Case: 19-50850 Document: 00515941160 Page: 3 Date Filed: 07/16/2021

No. 19-50850 “Plaintiff–Appellee [LCRA] is a conservation and reclamation district based in Austin, Texas, and a political subdivision of the State of Texas. LCRA sells wholesale electric power to municipal-owned utilities and electric cooperatives in Texas. In December 2009, LCRA entered into [the PPA] with Defendant–Appellant Papalote Creek Wind Farm II, L.L.C. (Papalote), a Delaware limited liability company that builds and operates wind farms. Papalote planned to build an 87-turbine wind farm in Texas, and under the PPA, LCRA agreed to purchase all of the energy generated by the Project at a fixed price for an 18-year term. .... Papalote completed construction of the [wind farm] in 2010, and in the ensuing years, LCRA complied with its obligations under the PPA by purchasing all of the energy generated by the Project. In April 2015, however, LCRA initiated discussions with Papalote regarding the PPA. Although the parties dispute the precise nature of these discussions, neither party appears to have threatened to breach the PPA. Ultimately, in June 2015, LCRA sent Papalote a letter stating that, pursuant to § 13.2, LCRA was initiating the arbitration process to resolve the dispute between LCRA and Papalote regarding LCRA’s limitation of liability under the PPA and its impact on LCRA’s performance obligations. LCRA also noted that it intend[ed] to continue to fully perform its obligations under the PPA during the arbitration process. After Papalote requested more information about the purported dispute, LCRA sent another letter explaining that the dispute was whether LCRA’s liability is limited to $60,000,000 under the PPA. .... On October 10, 2016, LCRA notified Papalote that it would cease taking energy under the PPA beginning on October 12, 2016, and that its resulting liquidated damages would be capped at $60 million per § 9.3.” Papalote I, 858 3 Case: 19-50850 Document: 00515941160 Page: 4 Date Filed: 07/16/2021

No. 19-50850 F.3d at 918–21 (internal quotation marks and alterations omitted). After extensive litigation over whether this matter should be arbitrated, we ruled that the PPA’s arbitration provision did not cover this dispute. See Papalote II, 918 F.3d at 456–57. In March 2019, LCRA filed suit in the federal district court seeking declaratory judgment that its aggregate liability under the PPA is capped at $60 million. The district court consolidated that suit with the case the Papalote II panel remanded for further proceedings, heard oral arguments, and proceeded to consider the merits of the parties’ claims and cross-motions for summary judgment. On August 26, 2019, the district court denied Papalote’s motion for summary judgment and granted LCRA’s cross-motion for summary judgment. The district court concluded that the last sentence of Section 9.3 of the PPA was unambiguous and subject to only one reasonable interpretation, viz., that the PPA limits to $60 million the aggregate damages that LCRA must pay to Papalote for LCRA’s failure to perform its material obligations under the PPA; that section 9.4 of the PPA did not affect the application of section 9.3; and that the liquidated damages paid thus far by LCRA counted toward the $60 million cap established by section 9.3. After carefully considering the 48-page PPA, the oral and written arguments of the parties, the record in this case, and the written reasons of the district court, we are so thoroughly persuaded that the district court’s interpretation of the PPA and its application to this case are correct, that we set forth and adopt as our own the two most pertinent sections of the district court’s written reasons:

4 Case: 19-50850 Document: 00515941160 Page: 5 Date Filed: 07/16/2021

No. 19-50850 II. CONTRACT PROVISIONS 1 The Agreement contains several provisions concerning the damages and remedies in the event of a breach by either party. For starters, the Agreement provides for liquidated damages. Section 4.3 establishes that Papalote is entitled to liquidated damages in the event LCRA fails to take and pay for all energy produced by the wind farm. A corresponding provision, § 4.2, establishes that LCRA is likewise entitled to liquidated damages in the event Papalote breaches its obligation to deliver energy to LCRA. In addition to liquidated damages, a non-breaching party gains access to additional remedies under § 6.2 and § 6.3 if the breaching party defaults by failing to remedy its breach in a timely fashion. In that circumstance, the non- defaulting party gains the right to terminate the Agreement and “accelerate all amounts then owing between the Parties.” The non-defaulting party may also demand the defaulting party pay a Termination Payment, which is calculated according to a formula set out in § 6.3. Finally, and of particular importance here, § 9.3 imposes some limits on aggregate liability.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Medlock v. Ortho Biotech, Inc.
164 F.3d 545 (Tenth Circuit, 1999)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Ruppert v. Alliant Energy Cash Balance Pension Plan
726 F.3d 936 (Seventh Circuit, 2013)
Papalote Creek II, L.L.C. v. Lower Colorado River
918 F.3d 450 (Fifth Circuit, 2019)
Greater Houston Radiation Oncology, P.A. v. Sadler Clinic Ass'n
384 S.W.3d 875 (Court of Appeals of Texas, 2012)
Uri, Inc. v. Kleberg Cnty.
543 S.W.3d 755 (Texas Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Papalote Creek v. CO River Auth, Counsel Stack Legal Research, https://law.counselstack.com/opinion/papalote-creek-v-co-river-auth-ca5-2021.