Panzieri-Hogan Co. v. Bender

205 A.D. 398, 199 N.Y.S. 887, 1923 N.Y. App. Div. LEXIS 5033
Appellate Division of the Supreme Court of the State of New York·Decided May 16, 1923·Published·Cited by 3 cases

Opinions

Hinman, J.:

This action was brought to recover a balance of $2,011.17, conceded to remain unpaid by defendant to plaintiE upon a con[399] tract for building construction. The answer, putting in issue no allegation of the complaint, alleges, by way of defense and counterclaim, that defendant, through plaintiff’s failure to complete the building within the stipulated time, sustained damages through loss of rents to an amount equivalent to the balance unpaid upon the contract. The reply, besides putting in issue most of the material allegations of the counterclaim, avers, as an excuse for the delay in the completion of the construction, a strike on the part of the employees of the plaintiff and its subcontractors, absolving it from liability for the delay under the terms of the contract. The case came to us after a former trial in which a verdict was directed for the plaintiff. The question whether a strike had exonerated plaintiff from liability was not reached in our former decision. We held that the amounts of rents lost by defendant in consequence of the delay in completing the building were damages within the contemplation of the parties, recoverable by the defendant, unless it should develop, on a new trial, that plaintiff was relieved therefrom because of a strike. (202 App. Div. 94.)

The decisive question before us now is whether the strike clause of the contract defeated the defendant’s right to recover such damages under his counterclaim. The contract provides: “ If the

said party of the second part shall be delayed in performing said work or furnishing said material by reason of strike or strikes on the part of workmen or employees, or on the part of the workmen or employees of any sub-contractor, then the time for the completion of said work shall be extended for a period equal to the duration of any such strike or strikes.”

Plaintiff was a member of the Albany Builders’ Exchange composed of various local contractors, while its laborers, carpenters and masons and the workmen of its subcontractors belonged to labor unions which constituted a local association known as the Building Trades Council. By agreement between the Albany Builders’ Exchange and the Building Trades Council, in force for the year beginning May 1, 1920, and ending April 30, 1921, to which arrangement the plaintiff was a party as a member of the Exchange, a scale of wages had been established for the year, effective as to the laborers, carpenters and masons of the plaintiff and as to the workmen of its subcontractors. That arrangement was in effect in September, 1920, when the contract between plaintiff and defendant was made. The main portion of the construction was to be completed January 1, 1921, and that was accomplished. The contract provided, however, for a possible suspension of certain work of connecting two buildings, if a specified interference therewith should arise, with the understanding that said work [400] should-not take more than twenty-one working days after notice from defendant to plaintiff to proceed with-it. On April 2.6, 1921,. defendant notified plaintiff to proceed to connect the two' buildings. April 30, 1921, the time when-the wage scale agreement would expire, was approaching and the members of the Albany Builders’ Exchange, including plaintiff, agreed - among themselves upon a reduced scale of wages which they would pay to laborers, carpenters, masons and other workmen such as were ; employed -by the-plaintiff’s subcontractors,- commencing Hay 1, 1921. The proposed reduction was the subject of discussion between the contractors and the labor unions, the latter demanding that the old , wage scale be extended for another year, to which the - plaintiff and the other' contractors declined to accede. ■ ■

During the first four days after defendant notified plaintiff to proceed with the work of connecting the two buildings, plaintiff’s men and those of its subcontractors worked in full -force.: After May first the men did not report for work because work at the old scale of wages was refused for the year then beginning. The strike among the labor unions in the building trades was general'thrdughout the city. This condition lasted until the latter part of July, 1921. For several days after May first plaintiff was unable to obtain any kind of help to carry on the contract. Plaintiff requested the labor unions to furnish men, offering to pay the wages then being offered by the other contractors and any amount additional as might be adjusted later when the' strike was settled;- but the unions refused unless plaintiff would sign the agreement continuing the old scale of wages for a year. Commencing May fifth plaintiff proceeded with the work with such workmen as it could obtain. They were very few in number, especially at the outset-,- some experienced and competent and some not. As' labor conditions improved- and as fast as it could,, the plaintiff increased its: for-de' and satisfactorily completed the- work on July 26, 1921. Subsequent to May 1, 1921, plaintiff did not pay the old scale of’ wages. It paid the. same wages that were paid by other con-' tractors in the city of Albany at the time and the same wages that continued tó prevail at the time of the trial. The-subcontractors had similar experiences. ■

No question is'raised as to the fact that this disagreement with its employees caused the plaintiff to fail - to complete the work within the stipulated time and was sufficient in duration to rólieve the plaintiff from liability if it was a strike within the meaning-of the strike clause of the contract. The point raised by the defendant is that it was not a strike; but a lockout which plaintiff-itself inaugurated; that the delay was caused, riot because its [401] employees had gone on strike for an increase in wages; but solely because plaintiff refused to employ its labor except at reduced pay.

Free access — add to your briefcase to read the full text and ask questions with AI

Panzieri-Hogan Co. v. Bender, 205 A.D. 398, 199 N.Y.S. 887, 1923 N.Y. App. Div. LEXIS 5033 (N.Y. Ct. App. 1923).

205 A.D. 398 (Panzieri-Hogan Co. v. Bender) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Curtis Elev. Co., Inc. v. Hampshire House
362 A.2d 73 (New Jersey Superior Court App Division, 1976)
Almada v. Administrator
77 A.2d 765 (Supreme Court of Connecticut, 1951)
Barnes v. Hall
146 S.W.2d 929 (Court of Appeals of Kentucky (pre-1976), 1940)