Panhandle Eastern Pipe Line Company v. Federal Power Commission

386 F.2d 607, 1967 U.S. App. LEXIS 4372, 72 P.U.R.3d 63
CourtCourt of Appeals for the Third Circuit
DecidedNovember 29, 1967
Docket16499_1
StatusPublished
Cited by6 cases

This text of 386 F.2d 607 (Panhandle Eastern Pipe Line Company v. Federal Power Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Panhandle Eastern Pipe Line Company v. Federal Power Commission, 386 F.2d 607, 1967 U.S. App. LEXIS 4372, 72 P.U.R.3d 63 (3d Cir. 1967).

Opinion

OPINION OF THE COURT

MARIS, Circuit Judge.

In this proceeding the court is asked by Panhandle Eastern Pipe Line Company to review an order of December 23, 1966 and an amending order of February 14, 1967 issued by the Federal Power Commission. The proceeding had its origin in an application filed August 13, 1965 by Panhandle for a certificate of public convenience and necessity for the construction and operation of additional pipeline facilities required to furnish natural gas to a new refractories plant, then under construction, of H. K. Porter Company in what later became a part of the City of Fulton, Missouri. Panhandle had contracted to supply Porter with up to 3,000 Mcf per day, on an interruptible basis, at 40 cents per Mcf.

Panhandle owns and operates a 6 inch lateral pipeline from a point on its main transmission lines in Audrain County, Missouri, to the City of Fulton, which is situate in Callaway County, Missouri, a distance of 21.4 miles. This line was constructed in 1931 to serve the Harbi-son-Walker Refractories Company in the City of Fulton, and through it Panhandle directly supplies Harbison-Walker with interruptible gas. Five years later the City constructed a municipal gas distribution system and thereafter Panhandle through the same lateral supplied the City with the gas it needed.

Deeming its existing lateral of insufficient capacity to supply the gas required by Porter in addition to that supplied to its existing customers, Panhandle applied to the Commission for authority to construct an 8 inch pipeline to loop the existing lateral for a distance of 14.1 miles. It also sought Commission approval for the construction of a 4 inch pipeline 1.25 miles long to connect the existing lateral with the Porter refractory and a metering and regulating station. About five weeks after the expiration of the time which the Commission had fixed for filing petitions to intervene in the proceeding the City of Fulton filed such a petition. In its petition the City asserted that it desired and was able, through a pipeline to the plant which it had constructed, to supply the gas needs of the Porter plant at a lower rate than that proposed by Panhandle and it requested an order requiring Panhandle to sell gas to it for resale to Por *609 ter. The City offered to build its own pipeline to intersect Panhandle’s existing lateral, if Panhandle should refuse to expand its capacity and it requested a certificate therefor. Although opposed by Panhandle as untimely the intervention of the City was granted by the Commission which set the case for hearing. Panhandle’s petition for rehearing of the order granting intervention by the City was denied on March 14, 1966, the Commission stating that the City was competing with Panhandle for the right to sell gas to Porter and, although it had not technically complied with the requirement that it file a formal application, all the data which the regulations required the City as an applicant to furnish were being supplied in the hearing of the case then taking place. In the order the Commission stated that the City had the burden of proof and if at the conclusion of the hearing it had not met its burden Panhandle might move to dismiss its application.

On June 30, 1966 Panhandle requested a temporary certificate to build and operate the 1.25 miles line from its existing lateral to the Porter plant to enable it to serve that company to the extent of the lateral’s capacity during the pendency of the proceedings on Panhandle’s application for a permanent certificate. The City opposed this application and offered to permit Panhandle to serve Porter through the City’s connection until decision on the merits should be reached. Alternatively, the City requested a temporary allocation of gas under Panhandle’s interruptible rate schedule to permit the City to serve Porter. The Commission on August 10, 1966 refused to authorize the construction of the 1.25 miles line but issued a temporary certificate authorizing Panhandle to transport and deliver through the City’s distribution facilities up to 3000 Mef per day for direct sale by Panhandle to Porter. Panhandle declined to accept the temporary certificate, however, and the City, at Porter’s request, commenced serving that company from its allocation under its existing contract with Panhandle.

Following the formal hearings the hearing examiner filed an initial decision on June 21, 1966 generally approving Panhandle’s project and finding the City’s proposals to be inadequate and economically infeasible. The examiner’s initial decision was not adopted by the Commission, however, which on December 23, 1966 filed its opinion and order in which it found the proof submitted by both Panhandle and the City inconclusive and the record inadequate to permit a final decision on the merits. The Commission issued a certificate to Panhandle authorizing the construction of the 14.1 miles loop, but not the 1.25 miles line to connect its lateral with the Porter plant. It also directed Panhandle to sell to the City on an interruptible basis the gas needed by Porter until the Commission should otherwise order. The Commission’s order gave Panhandle the option of accepting or declining the certificate which authorized the looping of the lateral, and, in case of refusal, provided that the proceedings should be remanded to an examiner for further hearing. In this connection the Commission stated in its decision:

“If Panhandle declines the Certificate, the further proceedings which will be required can yield a record on capacity, looping, lateral line ' policy, and related matters, to enable a resolution of all legal and policy questions.” 36 F.P.C. 1107,1110.

Panhandle filed an application for reconsideration which the Commission, after making minor modifications in the order of December 23, 1966, denied by opinion and order entered February 14, 1967. Panhandle declined the certificate proffered by the order of December 23, 1966, which action rendered that order inoperative except as it provides for the sale of additional gas by Panhandle to the City pending further order of the Commission. The proceedings were accordingly remanded and are now before a hearing examiner of the Commission.

Panhandle urges in this court that the Commission erred (1) in that it violated its own published rules and regulations in *610 permitting the City’s untimely intervention and in considering its informal application for the allocation of gas to serve Porter, (2) in that it violated its prior order of March 14, 1966 in this proceeding by not dismissing the City’s application when it failed to meet its burden of proof, and (3) in that it violated section 7(a) of the Natural Gas Act, 15 U.S.C.A. § 717f(a), and section 5(a) of the Administrative Procedure Act, now 5 U.S.C. § 554(b), by failing to give notice to Harbison-Walker of the City’s application and by its order directing Panhandle to supply gas to the City for sale to Porter which would impair its ability to render service to Harbison-Walker. We have Considered all of these contentions and find them to be without merit.

Panhandle had no right to have its application granted merely because no one had protested or intervened in opposition within the period fixed by the Commission for such action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
386 F.2d 607, 1967 U.S. App. LEXIS 4372, 72 P.U.R.3d 63, Counsel Stack Legal Research, https://law.counselstack.com/opinion/panhandle-eastern-pipe-line-company-v-federal-power-commission-ca3-1967.