Missouri Edison Company v. Federal Power Commission, Panhandle Eastern Pipe Line Co., Intervenor

479 F.2d 1185, 156 U.S. App. D.C. 202, 1 P.U.R.4th 183, 1973 U.S. App. LEXIS 11037
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 20, 1973
Docket72-1406
StatusPublished
Cited by4 cases

This text of 479 F.2d 1185 (Missouri Edison Company v. Federal Power Commission, Panhandle Eastern Pipe Line Co., Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Missouri Edison Company v. Federal Power Commission, Panhandle Eastern Pipe Line Co., Intervenor, 479 F.2d 1185, 156 U.S. App. D.C. 202, 1 P.U.R.4th 183, 1973 U.S. App. LEXIS 11037 (D.C. Cir. 1973).

Opinion

Mr. Justice CLARK:

This is another of a series of eases beginning a score of years ago and continuing through 1969, in which Panhandle Eastern Pipe Line Company, a major interstate pipeline system, has opposed the effectuation of the long-established policy of the Federal Power Commission “to favor service to industrial customers by local distributors.” Panhandle Eastern Pipe Line Co., Op. 274, 13 FPC 301, aff’d, Panhandle Eastern Pipe Line Co. v. FPC, 232 F.2d 467 (3 Cir. 1956), cert. den., 352 U.S. 891, 77 S.Ct. 129, 1 L.Ed. 2d 86; Panhandle Eastern Pipe Line Co., Op. 510, 36 FPC 1107, reh. den., Op. 510-A, 37 FPC 314, aff’d, Panhandle Pipe Line Co. v. FPC, 386 F.2d 607 (3 Cir. 1967); Panhandle Eastern Pipe Line Co., Op. 539, 39 FPC 581 (1968), *1186 reh. den., 39 FPC 1100; Panhandle Eastern Pipe Line Co., Op. 566, 42 FPC 621 (1969).

Here, Missouri Edison Company (Mo Ed), which operates under the jurisdiction of the Missouri Public Service Commission, serves some 22 communities in northeastern Missouri and has its headquarters in Louisiana, Missouri, a town of 4500 people. It requested an order of the Federal Power Commission directing Panhandle to sell and deliver to it 15,000 mcf of gas daily for resale to Hercules, Inc. at its chemical works also located at the City of Louisiana and within Mo Ed’s service community. Hercules has been furnished gas direct from Panhandle’s pipeline since 1942 under contracts, the last of which expired in 1969, after which Panhandle continued service by agreement on a month to month basis. The service is by direct attachment to Panhandle’s pipeline and is, therefore, not regulated by either federal or state authority. In 1969, the year the last Panhandle contract expired, Hercules’ chemical works at Louisiana suffered a million dollar operating loss. In an effort to continue the plant in operation, it requested Panhandle to reduce its gas rate, but to no avail. Hercules then turned to Mo Ed and subsequently reached an agreement to acquire gas from that company at a three percent resale charge above cost. Mo Ed was also a customer of Panhandle, buying its requirements exclusively from the latter under a contract requiring a maximum of 12,500 Mcf of gas to be delivered daily on demand of Mo Ed. Panhandle delivered slightly over 1 million mcf under this contract in 1969, and the resale of this gas contributed some 12 percent to Mo Ed’s total revenues. Originally Mo Ed’s application with the Commission was made under Panhandle’s G-2 demand rate schedule 1 which provided for delivery on a firm basis. However, on suggestion of the Commission’s staff, the application was amended to provide for delivery on an interruptible basis under Panhandle’s 1-2 interruptible rate schedule, 2 the identical rate schedule under which Hercules was then receiving gas from Panhandle. Both the Commission’s staff and the Examiner approved the conversion of the sale from a direct pipeline one to an indirect distributor delivery, in keeping with prior Commission decisions. However, the Commission has overturned these recommendations and denied the application. We reverse.

1. The Findings of the Commission

In its original opinion the Commission first stated a conviction that it “should not adhere with uncompromising rigidity to a policy of preferred shifting of interruptible loads from a pipeline to a distributor.” Appendix Vol. I, p. 124. As to the effect of the conversion on Panhandle’s ability to serve its other customers, the Commission concurred in the Examiner’s finding that there was no impairment. But other economic factors compelled a different result, it said, from that of the Examiner: It was the business of the pipeline to meet the requirements of its customers; however, the customers’ demands were highly uneven, reflecting seasonal requirements; to avoid waste and added cost associated with partially filled transmission lines the pipeline sells interruptible service or installs storage capacity for gas. The contribution of an interruptible load to the pipeline’s balancing program, however, is smaller when that load is “attached” by the customer rather than directly by the pipeline. Thus, “flexibility *1187 and related improved efficiency of the pipeline is diminished whenever a segment of interruptible service is transferred from direct pipelines attachment to indirect attachment through a distributor.” Id. at 125-126. In Mo Ed’s case the transfer of the Hercules account from Panhandle to Mo Ed would diminish the benefits which the interruptible character of the Hercules sale contributes to the load balancing operations of the Panhandle system since one-third of the annual volumes that Mo Ed proposes to deliver to Hercules would come under Panhandle’s firm service rate schedule (G-2). The transfer would only create additional pressure on the Panhandle system. The Commission also noted that under conditions of gas supply shortage, gas storage should be substituted for interruptible deliveries. It would be unwise to encourage the direct attachment interruptible gas customers to migrate to distributors since this would frustrate pipeline curtailment plans, increase industrial usage, and undermine the flexibility of the pipeline during period of gas supply shortage.

2. The Rehearing Application and Its Denial:

On rehearing Mo Ed pointed out that it sought a supply of gas under Panhandle’s 1-2 rate schedule to serve Hercules on an interruptible basis; its proposal was intended merely to supplant the current non-jurisdictional, direct attachment service of Panhandle. No change in the type of service was contemplated, and the only question presented was whether Panhandle should serve Hercules by direct attachment to its pipeline or indirectly through Mo Ed. Mo Ed further noted that Panhandle’s 1-2 rate schedule specifically provided that “all gas sold on an interruptible basis to both direct and resale customers may be interrupted at any time and in any amount in the sole discretion of” Panhandle. However, in order to “lay this false argument to rest,” Mo Ed explicitly agreed as a condition of receiving the proposed 1-2 service that Panhandle’s 1-2 sale to Mo Ed should be subject to the identical interruptions and curtailment by Panhandle as had been the direct sale by the latter to Hercules.

The Commission, in denying the application for rehearing, relied on its original opinion holding that Mo Ed had not discharged any element of its burden of proof. It had not shown that the transfer was necessary or desirable in the public interest and would not place an undue burden on Panhandle or cause an impairment of Panhandle’s ability to render adequate service to its customers. It further found that the transfer would “firm up” a substantial portion of an in-terruptible industrial demand, as indicated in its original decision, by permitting Mo Ed to serve Hercules with “valley gas,” 3 even when 1-2 gas had been curtailed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
479 F.2d 1185, 156 U.S. App. D.C. 202, 1 P.U.R.4th 183, 1973 U.S. App. LEXIS 11037, Counsel Stack Legal Research, https://law.counselstack.com/opinion/missouri-edison-company-v-federal-power-commission-panhandle-eastern-pipe-cadc-1973.