Panama City-Bay County Airport & Industrial District v. Kellogg Brown & Root Services, Inc.

140 So. 3d 1112, 2014 WL 2772646, 2014 Fla. App. LEXIS 9238
CourtDistrict Court of Appeal of Florida
DecidedJune 18, 2014
DocketNo. 1D12-4874
StatusPublished
Cited by1 cases

This text of 140 So. 3d 1112 (Panama City-Bay County Airport & Industrial District v. Kellogg Brown & Root Services, Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Panama City-Bay County Airport & Industrial District v. Kellogg Brown & Root Services, Inc., 140 So. 3d 1112, 2014 WL 2772646, 2014 Fla. App. LEXIS 9238 (Fla. Ct. App. 2014).

Opinion

ON APPELLEE/CROSS-APPELLANT’S MOTION FOR REHEARING AND CERTIFICATION

OSTERHAUS, J.

This case arises from the construction of the new airport that opened in Panama City in 2010. After the airport was in operation, a stormwater retention pond had to be reconstructed at a cost of millions of additional dollars because improper-sized sand was installed in the pond. Legal claims multiplied between those with a hand in the project — the airport district, its construction management contractor, the pond’s designer, and the construction company — involving the pond and other drainage, grassing, and sodding work. And though much was settled short of trial, the Panama City-Bay County Airport and Industrial District (“Airport”) [1114]*1114and construction management contractor Kellogg Brown • & Root Services, Inc. (“KBR”), ultimately went to trial. KBR prevailed after assailing the Airport’s witnesses and case at trial on the basis of a settlement agreement the Airport had entered with the construction company. The Airport objected below to having its settlement agreement made known to the jury and now makes a convincing argument on appeal for reversal, remand, and a new trial because the agreement should not have been disclosed.

I.

In 2007, the Airport entered into contracts for the design, oversight, and construction of the Northwest Florida Beaches International Airport in Panama City. The Airport hired Atkins North America, Inc. (“Atkins”) to design plans and specifications for construction of the “horizontal” works of the airport (site preparation, drainage, and paving); contracted with Appellee KBR to perform construction and program management and oversight services; and awarded the prime construction contract to Phoenix Construction Services, Inc. (“Phoenix”).

This appeal mainly involves the construction of a retention pond at the airport site. Plans called for the construction of “Pond C,” an approximately 50-acre stormwater pond that collected and treated water draining from over 1000 acres of the airport site. The pond’s ability to drain water, its permeability, was a critical performance metric dictated by longstanding Florida Department of Environmental Protection (“DEP”) regulations. DEP required that sands installed in the pond be certified as meeting a minimum grain size. But in the course of construction, noncompliant, small-sized sand was installed in the pond. For this reason, the pond had to be reconstructed at an additional cost of over $5.5 million.

Claims and recriminations abounded regarding Pond C and other work at the site. Phoenix sued the Airport for breach of contract and Atkins for professional negligence. The Airport, seeking to recover the additional $5.5 million from Phoenix, Atkins, and/or KBR, asserted counterclaims for breach of contract, bond, and indemnity against Phoenix; crossclaims for professional negligence, breach of contract, and indemnity against Atkins; and third-party indemnity, contract, and negligence claims against KBR. In turn, KBR brought third-party counterclaims for indemnity and breach of contract against the Airport.

As the litigation progressed, the parties resolved a great deal short of trial. In January 2012, the Airport and Phoenix entered a settlement agreement fully releasing one another. Among other things, the Airport admitted liability and liquidated its damages to Phoenix in return for a share of any recovery from the continuing litigation. They also agreed to cooperate in the remaining litigation using a common law firm compensated by Phoenix in addition to the Airport’s own counsel. But they clarified that each was to retain ownership and control of its own claims and could settle its claims independently. In fact, after the Airport and Phoenix settled, each also settled their claims with Atkins.

The only claims remaining by the time of trial were the Airport’s third-party breach of contract and professional negligence claims against KBR; and KBR’s third-party counterclaim for breach of contract and indemnity arising from unpaid invoices. Before trial, the Airport filed a motion in limine to exclude evidence of Phoenix’s settlement offer and of the Airport-Phoenix settlement agreement itself. The trial court granted the motion as to [1115]*1115the terms of the settlement offer, but allowed the settlement agreement to be disclosed to the jury. KBR made the settlement agreement known to the jury and referred to it repeatedly to discredit the Airport’s case and to bolster its own counterclaims. The views KBR expressed at trial were that the settlement agreement showed the Airport’s case to be “not about the pursuit of truth [but] of money,” and amounted to Phoenix “invest[ing] in a lawsuit.”

The jury returned verdicts for KBR, both rejecting the Airport’s breach of contract and negligence claims and ruling for KBR on its counterclaim and assessing damages at more than $360,000, the amount of the unpaid invoices. The Airport moved for a new trial citing the improper disclosure of its settlement agreement (among other things); but its motion was denied. It then timely appealed, but did not appeal the judgment on KBR’s crossclaims. KBR also cross-appealed.

II.

A.

As a threshold matter, we must address the mootness issue that KBR has raised which implicates this court’s jurisdiction. KBR argues that the Airport’s appeal is moot because it has failed to appeal the judgment on KBR’s counterclaim. The essence of KBR’s argument is that the jury defacto decided the Airport’s direct claims by rejecting similar-sounding affirmative defenses that the Airport raised in defense of KBR’s counterclaim.

It is true that “[a]n issue is moot when the controversy has been so fully resolved that a judicial determination can have no actual effect.” Carlin v. State, 939 So.2d 245, 247 (Fla. 1st DCA 2006). But, here, we find little merit to KBR’s mootness argument because the jury’s consideration involved only whether the Airport’s affirmative defenses barred KBR from recovering on particular invoices. This disposition did not, however, implicate the merits of the Airport’s much broader breach of contract and negligence claims. In fact, the trial court specifically instructed the jury to separately consider the Airport’s claims from KBR’s counterclaim. And so, the jury’s ruling that certain invoices should be paid, did not preclude the Airport from prevailing on its separate claims.

B.

The Airport’s main argument is that the trial court committed reversible error by allowing KBR to disclose its settlement agreement with Phoenix to the jury, which it then used to discredit the Airport’s case.

A trial court’s decision to admit or exclude evidence is reviewed for abuse of discretion. Hendricks v. State, 34 So.3d 819, 822 (Fla. 1st DCA 2010). Its discretion, however, “is limited by the evidence code and the applicable case law, and its interpretation of those authorities is subject to de novo review.” Id. Where a settlement agreement is involved, the law is particularly clear: “The fact that a written release or covenant not to sue exists or the fact that any person has been dismissed because of such release or covenant not to sue shall not be made known to the jury.” § 46.015(3), Fla. Stat. (2012) (emphasis added); see also id. § 768.041(3) (applying the same prohibition to tort claims).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
140 So. 3d 1112, 2014 WL 2772646, 2014 Fla. App. LEXIS 9238, Counsel Stack Legal Research, https://law.counselstack.com/opinion/panama-city-bay-county-airport-industrial-district-v-kellogg-brown-fladistctapp-2014.